質問 # 41
If the supporting PQR is used, are the P-no's correct on the attached WPS?

  • A. No
  • B. Not enough information
  • C. Yes
  • D. Could be if properly preheated

正解:A


質問 # 42
When may welding not be performed?

  • A. If the weld area is not in direct sunlight
  • B. If the weld area is in an inert atmosphere
  • C. If the weld area is above 120° F
  • D. If the weld area is frosted or wet

正解:D


質問 # 43
Welding procedures qualified by may be used, subject to the specific approval of the inspector

  • A. the use of API 1104 qualified procedures
  • B. others
  • C. the employer
  • D. the use of AWS pre qualified, D1.1 type procedures

正解:B


質問 # 44
API 570 was developed to provide for the inspection of in-service process piping.

  • A. general guidelines
  • B. recommendations
  • C. an industry standard
  • D. suggestions

正解:C


質問 # 45
Can the inspection interval of the system in question 24 be increased to 8 years?

  • A. If the system was insulated, the interval can be extended
  • B. Yes
  • C. Not enough information given
  • D. No

正解:B


質問 # 46
Piping subject to CUI includes piping insulated for personnel protection, especially:

  • A. carbon steel piping systems
  • B. plastic piping
  • C. glass lined piping
  • D. carbon steel piping systems operating between 25°F-250°F

正解:D


質問 # 47
The three well-known methods of determining soil resistivity are, soil bar, soil box and______.

  • A. Wenner (4-pin) method
  • B. holiday pipe survey
  • C. A-C Bridge
  • D. six pin method

正解:A


質問 # 48
Bolts should extend during the installation of flanged connections.

  • A. at least 0.5 inches (12.7 mm) past their nuts
  • B. completely through their nuts
  • C. only half way through their nuts
  • D. two threads past their nuts

正解:B


質問 # 49
What is the inspection interval for buried piping without cathodic protection, the soil resistivity is 6,500 ohm-cm?

  • A. 5 years
  • B. whenever a leak is suspected
  • C. 10 years
  • D. 15 years

正解:C


質問 # 50
In lieu of the required heat treatment after welding, what may be used as an alternative?

  • A. Quenching
  • B. Normalizing/annealing
  • C. Air Hardening
  • D. Strain Harmonics

正解:B


質問 # 51
To evaluate the effects of fire damage, an assessment should be performed in accordance with____.

  • A. ASME 816.5
  • B. API 598, Section 1
  • C. API RP 2207 Section 2
  • D. API RP 579, Section 11

正解:D


質問 # 52
Temperatures above can damage transducers not equipped with delay line material.

  • A. 280 psi
  • B. There is no limit to temperature
  • C. manufacturer's specification
  • D. 1,000 psi

正解:C


質問 # 53
The formula t = PD/2SE computes the.

  • A. minimum piping thickness
  • B. average piping thickness
  • C. maximum piping thickness
  • D. Minimum required piping thickness

正解:D


質問 # 54
What is the required thickness of straight run pipe subject to internal pressure only, based on the following conditions: NPS 14, SA 285 Gr.C, EFW Spiral seam (No radiography), operating at 216 psi / 378?F

  • A. Not enough information given
  • B. 0.11"
  • C. 1.1"
  • D. 0.06"

正解:B


質問 # 55
A weld is changed from multi pass per side to single pass per side.
How does this effect the PWHT limitation?

  • A. The PWHT must be performed per ASME IX and time increased byone
  • B. This limitation does not apply when a WPS is qualified with a PWHT above the upper transformation temperature
  • C. This limitation does not apply when a WPS is qualified with a PWHT below the upper transformation temperature
  • D. The PWHT is not a consideration

正解:B


質問 # 56
The acronym CUI refers to.

  • A. Corrosion Under Insulation
  • B. Corrosion Under Inside flow
  • C. Carpet Under Infra-structure
  • D. Cold Under-ground In-service piping

正解:A


質問 # 57
......