質問 135
Which should be provided by corporate or programme management before the Starting up a Project process commences?
- A. Sufficient information to identify the prospective Executive
- B. A Project Brief
- C. The Project Initiation Documentation
- D. Authority to initiate a project
正解: A
解説:
Section: Volume B
質問 136
Which action should the project manager take during the 'assessing issues' step?
- A. Gain project board feedback on the Issue priority
- B. Consider the impact of alternative options for resolution
- C. Create an exception plan tor project board approval
- D. Determine the initial priority of the issue that has been raised
正解: D
質問 137
Which are characteristics of stakeholders?
1. They are often affected by the project
2. They agree with every project objective
3. They are only/always external to the corporate organization
4. They typically interact with the project
- A. 3 and 4
- B. 1 and 4
- C. 2 and 3
- D. 1 and 2
正解: B
解説:
Section: Volume B
Explanation/Reference: https://www.prince2.com/blog/how-to-identify-stakeholders/
質問 138
Which is a purpose of the Business Case theme?
- A. Establish the controls to manage changes that may impact the project benefits
- B. Identify which role is responsible for producing the Business Case
- C. Establish a viable investment proposition
- D. Identify the project'soutputs
正解: C
質問 139
Where should a Team Manager look for information on the quality required for a product?
- A. Quality Management Strategy
- B. Product Description
- C. Project Initiation Documentation
- D. Team Plan
正解: B
質問 140
Which is a purpose of the Risk theme?
- A. Establish mechanisms to control any unacceptable deviations from plan
- B. Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
- C. Establish a cost-effective procedure to identify, assess and control uncertainty
- D. Establish mechanisms to manage risks at the corporate or programme level of an organization
正解: C
質問 141
How many tasks does the product-based planning technique describe?
- A. Four
- B. One
- C. Three
- D. Two
正解: A
解説:
Section: Volume B
質問 142
Which role is responsible for the quality of the specialist products delivered in the project?
- A. Executive
- B. Project assurance
- C. Senior user
- D. Senior supplier
正解: D
解説:
Section: Volume B
Explanation/Reference: http://www.fmdconsultants.co.uk/p2_roles_and_responsibilities_v01.docx
質問 143
Identify the missing words in the following sentence.
A problem/concern, a request for change and [ ? ] are the three types of issue.
- A. an off-specification
- B. a threat
- C. a deviation from tolerance
- D. a constraint
正解: A
質問 144
Which is a purpose of the Closing a Project process?
- A. Delegate day-to-day management of the end of the project to the Project Manager
- B. Recognize whether objectives set out in the original Project Initiation Documentation have been achieved
- C. Authorize the final stage of the project
- D. Confirm that all benefits defined in the Business Case have been achieved
正解: B
質問 145
Which are characteristics of stakeholders?
1. They are often affected by the project
2. They agree with every project objective
3. They are only/always external to the corporate organization
4. They typically interact with the project
- A. 3 and 4
- B. 1 and 4
- C. 2 and 3
- D. 1 and 2
正解: B
解説:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2.com/blog/how-to-identify-stakeholders/
質問 146
Which of the following is NOT part of quality planning?
- A. Gain acceptance of the project product
- B. Set quality tolerances
- C. Define quality responsibilities
- D. Agree acceptance criteria
正解: A
質問 147
Which is a purpose of the Directing a Project process?
- A. Control the day-to-day running of the project
- B. Create and authorize the project mandate
- C. Delegate day-to-day management of the project to the Project Manager
- D. Ensure that work on products allocated to the team is authorized and agreed
正解: C
質問 148
Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.
- A. Quality Management Strategy
- B. Follow-on action recommendations
- C. Stage Plan
- D. Communication Management Strategy
正解: D
質問 149
Which is a purpose of the 'initiating a project' process?
- A. To provide a fixed point at which acceptance for the project product is confirmed
- B. To produce a stage plan for each stage of a multi-stage project
- C. To enable an organization to understand the work needed to deliver the project's products
- D. To enable the project board to decide whether it is worthwhile to initiate a project
正解: D
解説:
Explanation/Reference:
Reference http://prince2.wiki/Initiating_a_Project#Objective
質問 150
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
- A. Only 2 is true
- B. Only 1 is true
- C. Both 1 and 2 are true
- D. Neither 1 or 2 are true
正解: C
解説:
Section: Volume B
質問 151
When should the Project Board refer to corporate or programme management for a decision?
- A. It is forecast that project level tolerance will be exceeded
- B. The Senior Supplier or Senior User needs to be changed
- C. The stage requires resources
- D. Any request for change needs to be approved
正解: A
質問 152
How should the Team Manager report that tolerances are forecast to be exceeded?
- A. Raise an issue
- B. Grant a concession
- C. Create a Highlight Report
- D. Create an Exception Report
正解: A
質問 153
Which is NOT a purpose of the Initiating a Project process?
- A. Enable the Project Board to decide whether it is worthwhile to initiate a project
- B. Enable a Project Board decision about the commitment of resources to a project
- C. Establish solid foundations for a project
- D. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
正解: A
質問 154
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
- A. Create user and supplier groups
- B. Create a separate Project Board to manage the supplier elements of the project
- C. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board
- D. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.
正解: A
質問 155
When is the 'managing a stage boundary' process used?
- A. Immediately alter the project board has authorized the previous stage
- B. Near the end of each stage
- C. Immediately after the project board has authorized the next stage
- D. Near the end of delivery stages
正解: D
質問 156
Which is an assumption about the PRINCE2 customer/supplier environment?
- A. The supplier will tailor the project's application of PRINCE2
- B. The customer will provide the resources to deliver the products
- C. The customer will specify the desired result
- D. The supplier will pay for the project
正解: C
解説:
Section: Volume B
質問 157
Which statement describes the responsibilities of a risk actionee?
- A. Identifying risks to the project that might occur in their department
- B. Carrying out a risk response action to respond to a particular risk
- C. Owning and authorizing the use of the risk budget to fund risk responses
- D. Managing, monitoring and controlling of all aspects of an assigned risk
正解: B
質問 158
When considering risks, which describes an opportunity in a project?
- A. An uncertain event that could have a negative impact on objectives
- B. An uncertain event that could have a favourable impact on objectives
- C. An event that has occurred resulting in a favourable impact on objectives
- D. An event that has occurred resulting in a negative impact on objectives
正解: B