[2023年04月13日] 心強いPRINCE2FoundationのPDF問題集はPRINCE2Foundation問題 [Q135-Q159]

Share

[2023年04月13日] 心強いPRINCE2FoundationのPDF問題集はPRINCE2Foundation問題

正真正銘のPRINCE2Foundation問題集で無料PDF問題で合格させる


PRINCE2 PRINCE2Foundation 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • The purpose of the PRINCE2® roles management products and themes
トピック 2
  • The purpose objectives and context of the PRINCE2® processes.
トピック 3
  • The characteristics and context of a project and the benefits of adopting PRINCE2®

 

質問 135
Which should be provided by corporate or programme management before the Starting up a Project process commences?

  • A. Sufficient information to identify the prospective Executive
  • B. A Project Brief
  • C. The Project Initiation Documentation
  • D. Authority to initiate a project

正解: A

解説:
Section: Volume B

 

質問 136
Which action should the project manager take during the 'assessing issues' step?

  • A. Gain project board feedback on the Issue priority
  • B. Consider the impact of alternative options for resolution
  • C. Create an exception plan tor project board approval
  • D. Determine the initial priority of the issue that has been raised

正解: D

 

質問 137
Which are characteristics of stakeholders?
1. They are often affected by the project
2. They agree with every project objective
3. They are only/always external to the corporate organization
4. They typically interact with the project

  • A. 3 and 4
  • B. 1 and 4
  • C. 2 and 3
  • D. 1 and 2

正解: B

解説:
Section: Volume B
Explanation/Reference: https://www.prince2.com/blog/how-to-identify-stakeholders/

 

質問 138
Which is a purpose of the Business Case theme?

  • A. Establish the controls to manage changes that may impact the project benefits
  • B. Identify which role is responsible for producing the Business Case
  • C. Establish a viable investment proposition
  • D. Identify the project'soutputs

正解: C

 

質問 139
Where should a Team Manager look for information on the quality required for a product?

  • A. Quality Management Strategy
  • B. Product Description
  • C. Project Initiation Documentation
  • D. Team Plan

正解: B

 

質問 140
Which is a purpose of the Risk theme?

  • A. Establish mechanisms to control any unacceptable deviations from plan
  • B. Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
  • C. Establish a cost-effective procedure to identify, assess and control uncertainty
  • D. Establish mechanisms to manage risks at the corporate or programme level of an organization

正解: C

 

質問 141
How many tasks does the product-based planning technique describe?

  • A. Four
  • B. One
  • C. Three
  • D. Two

正解: A

解説:
Section: Volume B

 

質問 142
Which role is responsible for the quality of the specialist products delivered in the project?

  • A. Executive
  • B. Project assurance
  • C. Senior user
  • D. Senior supplier

正解: D

解説:
Section: Volume B
Explanation/Reference: http://www.fmdconsultants.co.uk/p2_roles_and_responsibilities_v01.docx

 

質問 143
Identify the missing words in the following sentence.
A problem/concern, a request for change and [ ? ] are the three types of issue.

  • A. an off-specification
  • B. a threat
  • C. a deviation from tolerance
  • D. a constraint

正解: A

 

質問 144
Which is a purpose of the Closing a Project process?

  • A. Delegate day-to-day management of the end of the project to the Project Manager
  • B. Recognize whether objectives set out in the original Project Initiation Documentation have been achieved
  • C. Authorize the final stage of the project
  • D. Confirm that all benefits defined in the Business Case have been achieved

正解: B

 

質問 145
Which are characteristics of stakeholders?
1. They are often affected by the project
2. They agree with every project objective
3. They are only/always external to the corporate organization
4. They typically interact with the project

  • A. 3 and 4
  • B. 1 and 4
  • C. 2 and 3
  • D. 1 and 2

正解: B

解説:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2.com/blog/how-to-identify-stakeholders/

 

質問 146
Which of the following is NOT part of quality planning?

  • A. Gain acceptance of the project product
  • B. Set quality tolerances
  • C. Define quality responsibilities
  • D. Agree acceptance criteria

正解: A

 

質問 147
Which is a purpose of the Directing a Project process?

  • A. Control the day-to-day running of the project
  • B. Create and authorize the project mandate
  • C. Delegate day-to-day management of the project to the Project Manager
  • D. Ensure that work on products allocated to the team is authorized and agreed

正解: C

 

質問 148
Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.

  • A. Quality Management Strategy
  • B. Follow-on action recommendations
  • C. Stage Plan
  • D. Communication Management Strategy

正解: D

 

質問 149
Which is a purpose of the 'initiating a project' process?

  • A. To provide a fixed point at which acceptance for the project product is confirmed
  • B. To produce a stage plan for each stage of a multi-stage project
  • C. To enable an organization to understand the work needed to deliver the project's products
  • D. To enable the project board to decide whether it is worthwhile to initiate a project

正解: D

解説:
Explanation/Reference:
Reference http://prince2.wiki/Initiating_a_Project#Objective

 

質問 150
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

  • A. Only 2 is true
  • B. Only 1 is true
  • C. Both 1 and 2 are true
  • D. Neither 1 or 2 are true

正解: C

解説:
Section: Volume B

 

質問 151
When should the Project Board refer to corporate or programme management for a decision?

  • A. It is forecast that project level tolerance will be exceeded
  • B. The Senior Supplier or Senior User needs to be changed
  • C. The stage requires resources
  • D. Any request for change needs to be approved

正解: A

 

質問 152
How should the Team Manager report that tolerances are forecast to be exceeded?

  • A. Raise an issue
  • B. Grant a concession
  • C. Create a Highlight Report
  • D. Create an Exception Report

正解: A

 

質問 153
Which is NOT a purpose of the Initiating a Project process?

  • A. Enable the Project Board to decide whether it is worthwhile to initiate a project
  • B. Enable a Project Board decision about the commitment of resources to a project
  • C. Establish solid foundations for a project
  • D. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved

正解: A

 

質問 154
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

  • A. Create user and supplier groups
  • B. Create a separate Project Board to manage the supplier elements of the project
  • C. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board
  • D. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.

正解: A

 

質問 155
When is the 'managing a stage boundary' process used?

  • A. Immediately alter the project board has authorized the previous stage
  • B. Near the end of each stage
  • C. Immediately after the project board has authorized the next stage
  • D. Near the end of delivery stages

正解: D

 

質問 156
Which is an assumption about the PRINCE2 customer/supplier environment?

  • A. The supplier will tailor the project's application of PRINCE2
  • B. The customer will provide the resources to deliver the products
  • C. The customer will specify the desired result
  • D. The supplier will pay for the project

正解: C

解説:
Section: Volume B

 

質問 157
Which statement describes the responsibilities of a risk actionee?

  • A. Identifying risks to the project that might occur in their department
  • B. Carrying out a risk response action to respond to a particular risk
  • C. Owning and authorizing the use of the risk budget to fund risk responses
  • D. Managing, monitoring and controlling of all aspects of an assigned risk

正解: B

 

質問 158
When considering risks, which describes an opportunity in a project?

  • A. An uncertain event that could have a negative impact on objectives
  • B. An uncertain event that could have a favourable impact on objectives
  • C. An event that has occurred resulting in a favourable impact on objectives
  • D. An event that has occurred resulting in a negative impact on objectives

正解: B

 

質問 159
......

結果を保証するには最新2023年04月無料:https://www.goshiken.com/PRINCE2/PRINCE2Foundation-mondaishu.html

有効な問題最新版を無料で試そうPRINCE2Foundation試験問題集解答:https://drive.google.com/open?id=106_cGCbGBpkgZ9B7ynXAUt8-hMMsAxRb