質問 # 179
Which are benefits of using PRINCE2?
1. It removes the need for activity-based planning
2. It promotes learning and continuous improvement
3. It can be applied to any type of project
4. It defines specific leadership and other interpersonal skills required
- A. 1 and 2
- B. 2 and 3
- C. 3 and 4
- D. 1 and 4
正解:B
解説:
Section: Volume B
Explanation/Reference: https://www.axelos.com/best-practice-solutions/prince2/key-benefits-of-prince2
質問 # 180
Which process provides information for the project board to review an updated project plan?
- A. Managing a stage boundary
- B. Directing a project
- C. Controlling a stage
- D. Initiating a project
正解:A
解説:
The process that provides information for the project board to review an updated project plan is 'Managing a Stage Boundary'. This process involves preparing the information needed for the project board to review the current stage's performance, reassess the project viability, and make decisions regarding the next stage, including updates to the project plan if necessary.References: PRINCE2 Foundation Manual
質問 # 181
Who represents the three project interests on a project?
- A. External project stakeholders
- B. Project support
- C. Project board
- D. Project manager
正解:C
解説:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Organization#Three_Project_Interests
質問 # 182
What is an advantage of applying the 'manage by stages' principle?
- A. The project has decision points so that it does not run on in an uncontrolled manner
- B. The PRINCE2 method can be used for any type of project
- C. Tolerances can be defined for delegated authority
- D. The project delivers benefits that are aligned with strategic objectives
正解:A
解説:
One advantage of applying the 'manage by stages' principle in PRINCE2 is that the project is broken down into manageable stages, providing decision points (stage boundaries). This helps in maintaining control by providing opportunities to review and, if necessary, adjust the project's direction and ensure it does not run on in an uncontrolled manner.References: PRINCE2 Foundation Manual
質問 # 183
What action is taken as part of the 'controlling a stage' process?
1. Create an exception plan
2. Authorize work to be done
3. Take corrective action
4. Obtain approvals for completed products
- A. 1 and 2
- B. 2 and 3
- C. 3 and 4
- D. 1 and 4
正解:B
解説:
As part of the 'controlling a stage' process, the actions taken include authorizing work to be done (2) and taking corrective action (3) as necessary to manage the stage effectively and keep the project on track.
References: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.
質問 # 184
Which is a valid statement about the Project Support role?
- A. Can be performed by the Project Manager
- B. Produces Checkpoint Reports for the Project Manager
- C. Can be combined with the Project Assurance role
- D. Is an optional role for a PRINCE2 project
正解:A
質問 # 185
Which statement about risks is FALSE?
- A. A risk is an uncertain event that, should it occur, will have an effect on a project's objectives
- B. A risk that could have a positive impact on a project's objectives is known as an opportunity
- C. A risk that a project's product is incomplete is known as an off-specification
- D. A risk that could have a negative impact on a project's objectives is known as a threat
正解:C
質問 # 186
According to the 'exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?
- A. Senior supplier AND team manager
- B. Project executive AND project manager
- C. Project executive AND senior user
- D. Project manager AND team manager
正解:B
解説:
Under the 'exception management technique' in PRINCE2, the roles most likely to identify issues that exceed stage tolerances are the Project Executive and the Project Manager. The Project Manager monitors the project's progress against its plans and will identify any deviations that might breach the set tolerances. The Project Executive, being accountable for the project's overall success, also plays a crucial role in overseeing tolerance thresholds and taking appropriate actions when these are exceeded.References: (PRINCE2 7 Foundation Handbook, AXELOS)
質問 # 187
Which is an objective of the 'directing a project' process?
- A. To review and approve a project mandate
- B. To obtain approval for completed products
- C. To define how risks, issues and changes will be managed
- D. To ensure corporate or programme management has an interface to the project
正解:D
解説:
Reference http://prince2.wiki/Directing_a_Project#Objective
質問 # 188
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?
- A. Project mandate
- B. Project Brief
- C. Benefits Review Plan
- D. Project Initiation Documentation
正解:D
質問 # 189
Which is a minimum requirement for applying the quality theme?
- A. To use lessons to inform quality planning
- B. To use the prescribed approach to quality management
- C. To use external quality standards for quality control
- D. To use user stories to inform the project product description
正解:B
解説:
Reference http://prince2.wiki/Quality
質問 # 190
Identify the missing words in the following sentence.
The project manager [ ? ] for day-to-day management of the project.
- A. and the team manager(s) are accountable
- B. has responsibility
- C. decides who is responsible
- D. and the project board are responsible
正解:B
解説:
The correct phrase that completes the sentence is "The project manager has responsibility for day-to-day management of the project." This highlights the project manager's role in overseeing the project's daily operations, ensuring that project activities align with the overall plan and objectives. References: PRINCE2
7 Foundation Handbook and official training materials.
質問 # 191
According to PRINCE2, which characteristic is necessary for an effective project board?
- A. An ability to delegate
- B. A 'problem-solving' approach
- C. A calm management style
- D. An attention to detail
正解:A
解説:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/project-board/
質問 # 192
Which is an objective of the quality review technique?
- A. To assess that a product conforms to set criteria
- B. To ensure that staff are properly trained in the quality methods
- C. To provide assurance that the project is being conducted properly
- D. To identify a product's quality criteria
正解:A
質問 # 193
Which are characteristics of stakeholders?
1. They are often affected by the project
2. They agree with every project objective
3. They are only/always external to the corporate organization
4. They typically interact with the project
- A. 1 and 4
- B. 1 and 2
- C. 3 and 4
- D. 2 and 3
正解:A
解説:
Reference https://www.prince2.com/blog/how-to-identify-stakeholders/
質問 # 194
Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?
- A. Writing a project product description
- B. Creating a product flow diagram
- C. Documenting the plan
- D. Writing the product description
正解:A
解説:
The first task in PRINCE2's recommended approach to 'defining and analyzing the products' is writing the Project Product Description. This document outlines what the project must deliver in order to gain acceptance. It serves as the basis for defining and analyzing more detailed product descriptions later in the process. References: PRINCE2 7 Foundation Handbook and official training materials.
質問 # 195
......
Prince2-Foundation試験は、Prince2プロジェクト管理方法論の知識と理解を評価するために設計された認定試験です。 Prince2は、あらゆる規模と業界の組織がグローバルに使用する広く採用されているプロジェクト管理フレームワークです。この試験は、Prince2の方法論とプロジェクト管理におけるその応用についての理解を実証したい候補者向けに設計されています。
PR2F認定試験は、Prince2方法論の基本的な理解を得ようとしている専門家を特に標的にしています。この認定は、プロジェクト管理分野に慣れていない個人や、既存のプロジェクト管理知識を強化しようとしている人に最適です。 PR2F認定試験では、プロジェクト管理の原則、Prince2プロセス、テーマ、テクニック、プロジェクトの組織、計画、および制御など、幅広いトピックをカバーしています。
PRINCE2Foundation認定ガイドPDFは100%カバー率でリアル試験問題:https://www.goshiken.com/PRINCE2/PRINCE2Foundation-mondaishu.html
合格させるPRINCE2Foundationレビューガイド、信頼され続けるPRINCE2Foundationテストエンジン:https://drive.google.com/open?id=106_cGCbGBpkgZ9B7ynXAUt8-hMMsAxRb