質問 # 47
Using the additional information provided for this question in the Scenario Booklet, answer the following questions about the requirement for a fire exit from the upstairs of the building.
What is an appropriate reason to classify the need for a secondary exit from the upstairs of the building as a Must Have requirement?
- A. A secondary exit from the upstairs of the building would help ease congestion in busy periods during festivals.
- B. The requirement for a secondary exit from the upstairs of the building has to be made a higher priority in order to be moved to an earlier Timebox.
- C. A secondary exit from the upstairs of the building will provide a shorter and more direct route into the garden than the main stairway.
- D. Provision of a secondary exit from the upstairs of the building will ensure compliance with national fire safety regulations.
正解:D
解説:
A: Provision of a secondary exit from the upstairs of the building will ensure compliance with national fire safety regulations.
Rationale:
Compliance with national fire safety regulations is non-negotiable and would be a legal requirement for the operation of the hotel. Therefore, any features required to meet these regulations would automatically be classified as "Must Have" due to their mandatory nature for safety and legal operation.
質問 # 48
An external web developer is to be contracted to create the new coffee bar insurance area on the existing web site. The chosen web developer will only agree to work on a 'fixed price for a fixed specification' contract.
What action should the Project Manager take?
- A. Agree to a 'fixed price for a fixed specification' contract with a requirement for the web developer to provide daily progress reports.
- B. Refuse to employ the chosen web developer as this is not an Agile
approach to project management. - C. Divide the work into component parts to ensure the web developer is focused on, and is paid to deliver, only what is specified for each component.
- D. Ensure the later elements of the project reflect the most valuable features of the product being built by the contractor.
正解:C
解説:
Dividing the work into smaller, well-defined component parts is a strategic approach when dealing with fixed-price contracts within an Agile framework. This method allows for greater flexibility and adaptability, as each component can be specified in detail, making it clear what the external web developer is responsible for delivering. This approach aligns with Agile principles by enabling incremental development and delivery, allowing for adjustments and refinements to be made as the project progresses and more information becomes available.
References:
In Agile Project Management, particularly when incorporating external resources or contractors, breaking down the project into smaller, manageable parts is a common practice. This not only facilitates better control and tracking of progress but also ensures that the project remains adaptable, with the capacity to respond to changes in requirements or priorities. This approach is in line with Agile methodologies that emphasize iterative development, customer collaboration, and responding to change over following a fixed plan.
質問 # 49
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each question.
Which 2 statements describe the appropriate application of Agile Project Management when developing the Delivery Plan?
- A. The Project Manager should include any known constraints associated with planning permission.
- B. The Architecture Angels' Marketing Director should be involved in the development of the Delivery Plan.
- C. The approach to the project should be based on the Project Approach Questionnaire responses.
- D. The Earth Excavations' Head Gardener should be excluded from discussions related to deliverables since contracts are NOT yet signed.
- E. The Project Manager should NOT need to identify any risks this early in the project.
正解:A、B
解説:
In the context of Agile Project Management, when developing the Delivery Plan during the Feasibility phase, the two statements that best align with Agile principles are:
A: The Project Manager should include any known constraints associated with planning permission.
E: The Architecture Angels' Marketing Director should be involved in the development of the Delivery Plan.
Here's the rationale:
*A: Recognizing and accounting for known constraints such as planning permission is a key aspect of Agile. It allows for better adaptability and planning around these constraints. Including them early in the Delivery Plan helps ensure that they are considered throughout the project.
*E: Agile emphasizes cross-functional collaboration and stakeholder engagement. The Marketing Director would provide valuable insights into customer needs and market conditions, which are crucial for a successful delivery plan.
質問 # 50
What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?
- A. The Project Manager should extend the timescale of Timebox B and shorten Timebox C.
- B. The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities.
- C. The Solution Development Team should change a Must Have requirement into a Should Have in the Prioritised Requirements List.
- D. The Project Manager should move a Must Have requirement from Timebox B into Timebox C.
正解:B
解説:
C: The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities.
Rationale:
In Agile Project Management, priorities are often reassessed and reprioritized based on new information or changes in the project's context. The need for a secondary exit due to compliance with fire safety regulations would necessitate such a reassessment. The Business Visionary and Business Sponsor, who provide the vision and funding for the project, together with the Solution Development Team, who are responsible for implementing solutions, should collaboratively review the Prioritised Requirements List to reflect this new priority. This change must be agreed upon by these key stakeholders to ensure that it aligns with the business needs and project goals.
質問 # 51
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following question
about assigning the Agile Project Management team roles within this
project.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E. that applies. Each option can be used once, more than once or not at all.


正解:
解説:
Explanation:
The activities from Column 1 should be performed in the following steps from Column 2, according to the iterative development process:
* Create the data entry screen for entering coffee bar details needed for a quotation.Selection: B.
ActionExplanation: Creating the data entry screen is part of the 'Action' step in iterative development, where the actual product or a part of it is being constructed.
* Enter numbers into a text-only field to see how the web page behaves.Selection: A. Thought Explanation: Testing how the web page behaves by entering data is part of the 'Thought' step, which includes reviewing and evaluating the work done, testing, and reflecting on the outcomes.
* Discuss the requirements of the new coffee bar insurance web page and agree which data fields are important.Selection: C. ConversationExplanation: Discussing and agreeing on the requirements is part of the 'Conversation' step, which involves interactions between team members and stakeholders to understand and define what needs to be built.
質問 # 52
There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as it evolves.
Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2 can be used once, more than once or not at all.
Column 1
1) In order to get an objective
view, the financial transaction
function is to be tested by
someone from Finance who
has had no involvement in its
development.
2) Before the developer works on
the printing function for the
policy documents, the Sales
Manager will review a prototype
of the online application form
for the new coffee shop
insurance product with the
solution tester.
3) Security test scripts have been
provided by the company's
bank. These scripts will be used
to test the link from the
company's website to the
banking system, which is to be
developed specifically to achieve these tests
4.
The addition of the new coffee
shop insurance product may
threaten the stability of the
existing website. As a primary
route to market this is
unacceptable. The website's
capacity to run additional pages
is to be verified before any
other tests are performed.
5.
The Must Have and Should
Have requirements are to be
tested before the Could Have
requirements.
Column 2
* Collaborative Testing
* Repeatable Testing
* Independent Testing
* Prioritised Testing
* Test-Driven Development
正解:
解説:
Explanation:
* C. Independent Testing
* A. Collaborative Testing
* B. Repeatable Testing
* D. Prioritised Testing
* D. Prioritised Testing
Short Comprehensive Explanation:
* Independent Testing is appropriate when someone from a different department (Finance) with no involvement in the development process conducts the testing to ensure an objective view.
* Collaborative Testing involves various stakeholders, in this case, the Sales Manager and the solution tester, working together to review and test a prototype, promoting early feedback and shared understanding.
* Repeatable Testing is used for security testing where predefined test scripts (provided by the bank) are applied to ensure the system meets specific security standards and can be repeated as needed.
* Prioritised Testing is essential when the project's stability and core functionality, such as the website's capacity to handle new features, must be confirmed before other tests are conducted to ensure the most critical aspects are addressed first.
* Again, Prioritised Testing is used to ensure that the essential requirements (Must Haves and Should Haves) are tested and validated before moving on to less critical ones (Could Haves), aligning with prioritization in Agile methodologies.
References:The Agile Project Management (AgilePM) framework and principles, as detailed in the AgilePM Practitioner documents and learning resources, guide the application of these testing concepts within an Agile project environment. These resources emphasize the importance of iterative development, stakeholder collaboration, and prioritization of work to ensure project success and alignment with business needs. Specific references to testing approaches and their application within Agile projects can be found in the official AgilePM handbook and practitioner-level training materials available through APMG International and affiliated training providers.
質問 # 53
Which 2 statements represent appropriate entries for the plan for Post-Project activities?
- A. The Sales Manager will create a company-wide email showing the
number of policies sold weekly by each of the sales assistants. - B. Before the product is deployed, the Sales Manager will circulate a copy of the revised sales procedure for processing coffee shop insurance sales.
- C. Once the new system has been deployed, the time it takes to process sales online will be compared with the time it takes to process new policies sold through telephone sales.
- D. The Project Manager will attend Daily Stand-up meetings to observe
progress. - E. A report showing the number of application forms completed online
through the website for coffee shop insurance policies will be produced weekly.
正解:C、E
解説:
For the XAN Insurance Company Web Project, the plan for Post-Project activities should include actions and measures that will be undertaken after the project's deliverables have been implemented to ensure sustained benefits, monitor performance, and facilitate continuous improvement.
Selected Statements for the Plan for Post-Project Activities:
D: A report showing the number of application forms completed online through the website for coffee shop insurance policies will be produced weekly.
E: Once the new system has been deployed, the time it takes to process sales online will be compared with the time it takes to process new policies sold through telephone sales.
D: Producing a weekly report on the number of application forms completed online is a clear post-project activity. It provides ongoing monitoring of the project's impact and the effectiveness of the online system in attracting coffee shop insurance policies.
E; Comparing the processing times of online sales to telephone sales after the new system's deployment is an essential post-project activity. It evaluates the efficiency and effectiveness of the new online system, offering insights into improvements and adjustments that may be needed.
Why Other Statements Are Excluded:
A: Creating a company-wide email to show the number of policies sold by each sales assistant weekly is more related to internal sales performance monitoring and motivation rather than a specific post-project activity tied to the project's objectives.
B: Circulating a copy of the revised sales procedure before product deployment is a preparation step for the transition to the new system, rather than a post-project activity.
C: The Project Manager attending Daily Stand-up meetings is part of the ongoing project management and team coordination activities during the project, not a post-project activity.
Topic 2, Hoy Hall Hotel Refurbishment Project
Scenario:
Hoy Hall Hotel Refurbishment Project
(Note:
Hoy Hall, a historic, timber-framed building dating from the 17th century, was originally the residence of the Lords of the Manor of Hoytown. The building is registered as a Heritage Building of Special Interest and is subject to restrictions in terms of development. Used as a hotel for over a century, it has recently fallen into disrepair, and for two years it has been completely unused, accelerating its deterioration. The local community has formed the Action Group "Hoy for Hoy Hall" to save the building, and wants to be closely involved in its future success.
After much discussion Hoy Hall has been purchased by Architecture Angels (AA), a small company whose directors are experienced hoteliers. Five years ago they decided to move into the property renovation business and have recently restored two other similarly-endangered buildings for use as hotels.
Architecture Angels are keen to both support local businesses and to have local people run their hotels, giving them a significant amount of autonomy to do this.
To maintain core consistency, the hotels use Architecture Angels' Head Office services, such as IT operations, accounting, payroll, stocktaking, compliance, human resources and property management. The Head Office is based 80 miles from Hoy Hall.
Recently Architecture Angels commenced an Agile project to renovate Hoy Hall, which has a large downstairs hall and reception area, and 20 potential bedrooms upstairs. The roof requires extensive repairs and the electrical and plumbing installations require complete replacement. The 40 acres of land around the site are overgrown and need to be restored, and the driveway needs re-laying.
In the hotel industry, the trend for direct customer bookings via the internet has had a major impact on the growth of those hotels with this facility. Online booking now accounts for around 80% of room bookings, with only 20% being made via walk-in and telephone enquiries. Before Hoy Hall can open for business, a reservation system must be fully operational.
Architecture Angels use contractors to manage such work and have good
relationships with two local companies: Timber Tigers (TT) who will handle the internal works, and Earth Excavations (EE) who will handle the gardens.
A Project Manager, who has since left the company, started the Feasibility phase. This phase has been continued by the Senior Management Team, which consists of the Sales, Marketing, and Finance Directors and the Chief Executive.
This was scheduled to take a month and has almost been completed. A
Feasibility Assessment has been produced. An Outline Business Case has been completed which assessed the project as being viable.
The Architecture Angels Senior Management Team will be responsible for
Steering the project.
The table below shows the appointments planned for the project team and is subject to change.
Additional Information:
The project is approaching the end of Feasibility. The original Project Manager was involved in drafting a Delivery Plan for the project but not in the outline refurbishment options.
The Senior Management Team generated several options for the refurbishment.
All the options included a landscaping solution for the gardens and re-laying of the driveway, as the solution will not be acceptable without these. However, the best solution for the refurbishment is still under debate. The new Project Manager has suggested that a Feasibility Prototype could consist of paper-based drawings for each option. The "Hoy for Hoy Hall" Action Group thinks that a physically-built representation is mandatory for a prototype and wants a small-scale model of the recommendation for the building. The time available to produce this, however, is limited.
Contracts for resources have not yet been signed and will be postponed until the chosen outline solution has been agreed.
質問 # 54
Which 2 actions should the Workshop Facilitator take to implement the new Must Have requirement?
- A. Encourage all parties to contribute, irrespective of their views.
- B. Send a company-wide communication to explain the implications of the business change to all interested parties.
- C. Assess the impact of the additional development costs on the original Business Case.
- D. Add the tasks required to develop the new financial transaction
functionality to the Delivery Plan. - E. Consolidate and circulate an agenda for the workshop.
正解:A、E
質問 # 55
Column 1 is a list of individuals from within the Xan Insurance Company and their key responsibility within the Web project.
For each individual in Column 1, select from Column 2 the Agile Project Management team role they are fulfilling. Each selection from Column 2 can be used once, more than once or not at all.
Column 1
Manager of Web & Digital
Media - will oversee and report
progress on the delivery of the
overall system.
Finance Director - has
budgetary control and will
release finance for the project
subject to expected benefits.
Sales Manager - will formulate
design options for new
business processes that do not
adversely affect business as
usual.
Operations Manager - oversees
the design and integrity of the
technical aspects of the
solution.
Column 2
* Business Sponsor
* Business Analyst
* Business Ambassador
* Business Advisor
* Solution Developer
* Technical Coordinator
* DSDM Coach
* Project Manager
正解:
解説:
Explanation:
Based on the Agile Project Management roles and the responsibilities outlined for each individual in the XAN Insurance Company Web Project scenario, the following selections can be made:
* Manager of Web & Digital Media - will oversee and report progress on the delivery of the overall system.Selection: H. Project ManagerExplanation: The Manager of Web & Digital Media's role of overseeing and reporting on the project's progress aligns with the responsibilities of a Project Manager in an Agile setting, who is responsible for ensuring that the project meets its objectives and is delivered on time.
* Finance Director - has budgetary control and will release finance for the project subject to expected benefits.Selection: A. Business SponsorExplanation: The Finance Director's control over the budget and the decision to release funds based on the expected benefits align with the role of a Business Sponsor, who is typically responsible for the project's budget and ensuring that it delivers value to the business.
* Sales Manager - will formulate design options for new business processes that do not adversely affect business as usual.Selection: B. Business AnalystExplanation: The Sales Manager's responsibility for formulating design options for new business processes mirrors the role of a Business Analyst in Agile Project Management, who works to understand the business needs, assess the impact of changes, and ensure the solution meets business requirements.
* Operations Manager - oversees the design and integrity of the technical aspects of the solution.
Selection: F. Technical CoordinatorExplanation: The Operations Manager's focus on the technical design and integrity of the solution corresponds to the role of a Technical Coordinator in Agile projects, who ensures that the technical aspects of the project align with the business needs and technical standards.
質問 # 56
The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the agreement of the team.
Which Agile principle MOST influences this course of action?
- A. Develop iteratively.
- B. Build incrementally from firm foundations.
- C. Never compromise quality.
- D. Deliver on time.
正解:D
質問 # 57
Answer the following question about how risks will be reduced on the Hoy Hall Hotel project through successful application of the DSDM Principles.
Column 1 lists a selection of project risks identified on the Hoy Hall Hotel project. Column 2 is a list of the DSDM Principles. For each risk in Column 1, select from Column
2 the DSDM Principle which, if applied appropriately, would MOST help to reduce or mitigate that risk.
Each selection from Column 2 can be used once, more than once or not at all.

正解:
解説:
Explanation:
Here are the DSDM Principles that would most help to reduce or mitigate the listed risks:
* The 'Hoy for Hoy Hall' Action Group may cause delay to the project if they are not kept updated on how the finished rooms are going to look.
* G. Communicate continuously and clearly
* Timber Tigers will ensure that the front rooms are finished and approved by the end of Timebox A.
* E. Build incrementally from firm foundations
* The Architecture Angels IT support team may require more detail up front in order to approve the initial design for the new online reservation system.
* A. Focus on the business need
* The morale of the Solution Development Team may be adversely affected if the external web design specialist is not a team player.
* C. Collaborate
* Empowering the Solution Development Team to manage themselves on a day-to-day basis may result in the Project Manager losing sight of what activities are being carried out, by whom and when.
* H. Demonstrate control
質問 # 58
When preparing for the workshop, which 2 items should the Workshop Facilitator be provided with?
- A. Hints and tips on how to influence and persuade others.
- B. Empowerment to discuss any wider project issues that may arise during the workshop.
- C. Background to the disagreement and the reasons for this.
- D. An understanding of the decision-making process.
- E. A step-by-step guide to running an effective workshop.
正解:C、D
解説:
The two items that the Workshop Facilitator should be provided with when preparing for the workshop are:
*B. An understanding of the decision-making process. This will help the facilitator guide the discussion and help the group reach a consensus.
*C. Background to the disagreement and the reasons for this. This will help the facilitator understand the context of the disagreement and facilitate a more effective discussion.
Please note that while hints and tips on how to influence and persuade others (option A), empowerment to discuss any wider project issues that may arise during the workshop (option D), and a step-by-step guide to running an effective workshop (option E) could be helpful, they are not as crucial as understanding the decision-making process and the background to the disagreement for this specific workshop.
質問 # 59
Answer the following questions about actions to be taken by different
roles.
The Business Sponsor has decided that the new coffee shop insurance
product website pages will include the financial transaction functionality to support the end-to-end sales process. The Business Sponsor views this as a valuable sales tool, enabling customers to pay for insurance policies online. If successful, this new financial transaction functionality is to be made available across all other insurance products. This is a new Must Have requirement.
All parties are to be invited to a workshop to discuss the additional work required to deliver the required solution including the new Must Have requirement. The areas to be discussed include specialist skills required and possible legal, financial and technical standards to be adhered to.
Remember to limit your answers to the number of selections requested in each question.
Which 2 actions should the Business Sponsor take to implement the new Must Have requirement?
- A. Source and hire a web developer with experience in developing online financial transaction functionality.
- B. Send a company-wide communication to explain the implications of the business change to all interested parties.
- C. Check for any documented standards which need to be applied to the
development of online financial transaction functionality. - D. Check the viability of the project, following the inclusion of the new Must Have requirement.
- E. Assess the impact of the new Must Have requirement on the original Business Case.
正解:D、E
解説:
To implement the new Must Have requirement for the coffee shop insurance product website, which includes financial transaction functionality, the Business Sponsor should take the following actions:
Selected Actions for the Business Sponsor:
B; Check the viability of the project, following the inclusion of the new Must Have requirement.
E: Assess the impact of the new Must Have requirement on the original Business Case.
B: Evaluating the project's viability after adding a significant new requirement is crucial. This involves analyzing whether the project can still meet its objectives within the given constraints, such as time, budget, and resources, especially when the new requirement could potentially add complexity and cost.
E: Understanding how the new requirement affects the original Business Case is essential. This involves reassessing the project's expected benefits, costs, and risks in light of the new functionality. It ensures that the project remains aligned with business objectives and continues to offer a viable return on investment.
Why Other Actions Are Less Suitable:
A; While ensuring adherence to relevant standards is important, it is more of a task for the technical team or a specific role such as the Technical Coordinator, rather than the primary responsibility of the Business Sponsor.
C: Sourcing and hiring specific technical expertise, such as a web developer with experience in online financial transactions, is generally a responsibility delegated to the Project Manager or relevant technical leads, not the Business Sponsor directly.
D: While communicating business changes to all interested parties is important, the specific action of explaining the implications of the business change company-wide is more likely to be a collaborative effort involving several roles, including the Business Change Manager, rather than solely the Business Sponsor's responsibility.
質問 # 60
Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox Plan for Timebox B?
- A. Architecture Angels' Senior Management Team.
- B. Team Leader.
- C. Marketing Director, in the role of Business Visionary.
- D. Project Manager and Architect, in the role of Technical Co-ordinator.
正解:B
質問 # 61
Using the Project Scenario answer the following question about the technical quality of the solution to be delivered. An assessment of the maintenance requirement for the new reservation system was made during Feasibility.
Column 1 describes a list of different types of hotel reservation systems considered. Column 2 lists the three DSDM maintainability objectives. For each description in Column 1, select from Column 2 the maintainability objective it would support.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1. Off-the-shelf software with ready-to-use templates that will need to be customised to fully meet Hoy Hall requirements, after deployment.
2. Developing a fully functioning in-house system, developed and hosted by Architecture Angels IT Operations team.
3. All-in-one web-based reservation and accommodation management system built to Hoy Hall's specification.
4. All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group, until a suitable system can be implemented at the site.
5. A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.
Column 2
* Maintainability is a required attribute of the initial delivered solution
* Deliver first, re-engineer later
* Short-term, tactical solution
正解:
解説:
Explanation:
For each of the descriptions in Column 1, the maintainability objective from Column 2 that each would support is as follows:
* Off-the-shelf software with ready-to-use templates that will need to be customised to fully meet Hoy Hall requirements, after deployment.
* A. Maintainability is a required attribute of the initial delivered solution
* Rationale: Customizing off-the-shelf software indicates a need for the solution to be maintainable from the onset to allow for these adjustments.
* Developing a fully functioning in-house system, developed and hosted by Architecture Angels IT Operations team.
* A. Maintainability is a required attribute of the initial delivered solution
* Rationale: In-house developed systems need to be maintainable to facilitate future changes and enhancements by the team that created them.
* All-in-one web-based reservation and accommodation management system built to Hoy Hall's specification.
* A. Maintainability is a required attribute of the initial delivered solution
* Rationale: A system built to specific requirements will require the ability to maintain and adjust the system as needs evolve, making maintainability a key initial attribute.
* All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group, until a suitable system can be implemented at the site.
* C. Short-term, tactical solution
* Rationale: This is clearly a temporary measure until a proper system is in place, indicative of a tactical solution to address immediate needs.
* A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.
* C. Short-term, tactical solution
* Rationale: Using a spreadsheet is a stop-gap solution to manage information in the short term, emphasizing the tactical nature rather than long-term maintainability.
Option B is not selected for any of the descriptions as none of them imply an approach of delivering first with the intention to re-engineer later. They all suggest a need for immediate maintainability or a short-term fix, not a re-engineering approach.
質問 # 62
Which 2 actions should the Project Manager take to implement the new Must Have requirement?
- A. Consolidate and circulate an agenda for the workshop.
- B. Source and hire a web developer with experience in developing online financial transaction functionality.
- C. Check for any documented standards which need to be applied to the
development of online financial transaction functionality. - D. Update the Delivery Plan to show the new financial transaction functionality as a deliverable.
- E. Add the tasks required to develop the new financial transaction functionality to the Delivery Plan.
正解:D、E
解説:
To effectively implement the new Must Have requirement for financial transaction functionality on the coffee shop insurance product website, the Project Manager should focus on actions that align with their role in planning, execution, and team coordination. The following actions are most appropriate for the Project Manager:
Selected Actions for the Project Manager:
B; Add the tasks required to develop the new financial transaction functionality to the Delivery Plan.
C; Update the Delivery Plan to show the new financial transaction functionality as a deliverable.
B: Integrating the tasks necessary for developing the new functionality into the Delivery Plan is crucial. This ensures that all project activities are accounted for and scheduled, which helps in managing the project's timeline and resources effectively.
C: Reflecting the new financial transaction functionality as a deliverable in the Delivery Plan is important for clarity and focus. It signifies the inclusion of this functionality as a critical component of the project's scope, guiding the team's efforts and priorities.
Why Other Actions Are Less Suitable:
A: While ensuring adherence to documented standards is important, it is typically a collaborative effort involving the Technical Coordinator and Solution Development team, in addition to the Project Manager, to ensure technical compliance.
D: Sourcing and hiring specific expertise, such as a web developer skilled in online financial transactions, is indeed part of the Project Manager's responsibilities. However, the actions related to the Delivery Plan (options B and C) are more directly aligned with the immediate steps for implementing a new requirement in the project's scope.
E: Consolidating and circulating an agenda for the workshop is a logistical task that the Project Manager might oversee or delegate. However, the actions related to planning and updating the Delivery Plan are more critical to the successful implementation of the new requirement.
質問 # 63
Which 2 statements represent appropriate entries for the Prioritised
Requirements List?
- A. The Business Visionary will provide a formal acceptance of the coffee shop insurance product.
- B. An assessment will be made of the effectiveness of the techniques used on the project, in line with the principles of Agile Project Management.
- C. Creation of a new coffee shop insurance product on the existing website is expected to increase the insurance company's revenues by up to 10% per week.
- D. All correspondence sent to coffee shop owners by the new system should contain the XAN logo in the top left hand corner of the page.
- E. Further website developments to allow existing customers to access
services online are NOT to be included within the scope of this project.
正解:D、E
質問 # 64
Which 2 statements describe the appropriate application of Agile Project Management when developing the Prioritised Requirements List during Feasibility?
- A. Regulatory obligations associated with the redevelopment of Hoy Hall should be recorded as Must Have requirements.
- B. Details of which areas will require seeding in order to become lawn, and which are to become planted borders, should be captured.
- C. The re-laying of the driveway and a landscaping solution should be listed as Must Have requirements.
- D. The scope of the project should be agreed before moving into the Foundations phase.
- E. The responsibility for setting the priority of each of the requirements identified should be assigned to the Project Manager.
正解:A、C
解説:
In the context of Agile Project Management when developing the Prioritised Requirements List during Feasibility, the two statements that align with Agile principles are:
B; The re-laying of the driveway and a landscaping solution should be listed as Must Have requirements.
E: Regulatory obligations associated with the redevelopment of Hoy Hall should be recorded as Must Have requirements.
Here's the rationale:
*B: In Agile, requirements are often categorized by priority such as "Must Have", "Should Have", "Could Have", and "Won't Have for now" (the MoSCoW method). The re-laying of the driveway and a landscaping solution are essential for the project's success and thus should be classified as "Must Have".
*E: Regulatory requirements are non-negotiable constraints that the project must adhere to. These should always be prioritized in the requirements list to ensure compliance and to avoid legal issues, making them
"Must Have" items as well.
質問 # 65
Which 2 actions should the Workshop Facilitator take when preparing for the workshop?
- A. Invite the Marketing Director to create a summary of the content they believe the system should hold and why.
- B. Ask the IT Operations Manager to prepare the agenda for the workshop.
- C. Ask the Software Developer to provide an estimate of how much storage space would be required to hold photos and videos.
- D. Research other hotel reservation systems to form an opinion on what the content should be.
- E. Assign ownership of the workshop to the Software Developer.
正解:A、C
解説:
The two actions that the Workshop Facilitator should take when preparing for the workshop are:
*A. Ask the Software Developer to provide an estimate of how much storage space would be required to hold photos and videos. This will provide a factual basis for the discussion about the system's content and its storage requirements.
*B. Invite the Marketing Director to create a summary of the content they believe the system should hold and why. This will ensure that the Marketing Director's perspective and requirements are clearly understood by all participants in the workshop.
Please note that while the IT Operations Manager, Software Developer, and the Facilitator themselves (options C, D, and E) could contribute valuable input to the workshop, these actions are not necessarily part of the Facilitator's role in preparing for the workshop. The Facilitator's role is to guide the discussion, not to assign ownership of the workshop, prepare the agenda, or form opinions on the content.