[2022年02月11日] 最新のAACE-PSP試験の的確なPlanning & Scheduling Professional (PSP) ExamのPDF問題
AACE-PSP試験問題を練習するならGoShiken顕著なPlanning & Scheduling Professional (PSP) Exam試験練習問題集
質問 68
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?
- A. Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.
- B. Use the forward-looking critical path of the most current updates.
- C. Use the progressed portion of the critical path of all the updates previous to the current update.
- D. Use the progressed portion of the critical path of the baseline schedule.
正解: B
質問 69
Which is NOT an industry-recognized methodology for quantifying critical delay?
- A. Gantt Chart.
- B. Periodic Windows.
- C. Collapsed As-Built.
- D. Time Impact.
正解: A
質問 70
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:
- A. Predecessor is activity 9001, successor is activity 9002
- B. Predecessor is activity 5001, successor is activity 8002
- C. Predecessor is activity 4001, successor is activity 8001
- D. Predecessor is activity 5001, successor is activity 8001
正解: D
質問 71
Time-scaled logic diagrams are
- A. Only calculated using a computer.
- B. Logic networks that are drawn to match the calendar.
- C. Used to calculate the most probable activity duration.
- D. The same as a pure-logic diagram.
正解: B
質問 72
The activity with the most total float is:
- A. Activity I.
- B. Activity C.
- C. Activity F.
- D. Activity D.
正解: A
質問 73
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
- A. Preferential logic.
- B. Start and finish constraints.
- C. Multiple calendars.
- D. Front end loading.
正解: D
質問 74
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?
- A. 2003 and 7001.
- B. 2004.
- C. 4001, 5001 and 6001.
- D. 4001 and 5001.
正解: D
質問 75
Which of the following is NOT required when performing weekly or monthly schedule updates?
- A. Remaining duration of activities.
- B. Actual finish of activities.
- C. Percent complete.
- D. Original duration of activities.
正解: A
質問 76
If no time extensions are granted and all actual delays are as described above, what will the total float calculation be at the end of the project?
- A. 10 calendar days.
- B. -14 calendar days.
- C. -20 calendar days.
- D. 0 calendar days.
正解: B
質問 77
What is a key first step in developing a critical path method schedule?
- A. Defining the execution plan to meet the required scope of work.
- B. Setting out the resource to be used and its limitations.
- C. Drawing the logic diagram.
- D. Drawing a bar chart of the key phrases of the work.
正解: C
質問 78
What owner action could have mitigated the late completion of the project?
- A. Self-perform more of the work.
- B. Hire a more senior project manager.
- C. Prepare better structural steel drawings.
- D. Use a procurement agent to monitor and expedite equipment deliveries.
正解: D
質問 79
Which of the following is NOT required when initially planning a project?
- A. Logical relationships between the tasks.
- B. Resource Identification and leveling.
- C. A schedule that identifies tasks required on a project.
- D. The duration of each task.
正解: D
質問 80
What is the result of a forward pass calculation?
- A. Early start and early finish date for individual activities
- B. Value of total float for individual activities
- C. Critical path
- D. Value of free float for individual activities
正解: A
質問 81
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
- A. The schedule has too much detail to reflect an accurate critical path.
- B. Different calendars are assigned to certain activities in the logical chain.
- C. The schedule is projecting an "early completion".
- D. Certain activities in the critical path have no successors.
正解: D
質問 82
Resource planning must take all of the following into account except for
- A. Earned value techniques established for the project.
- B. Cash flow (expenditure) limitations for completing work on the project.
- C. Time available to complete the project.
- D. Types of materials, equipment and labor skills required to complete the project.
正解: A
質問 83
Which of the following is NOT a tool or technique used to perform scope planning?
- A. Benefit cost analysis.
- B. Expert Judgment.
- C. Alternatives identification.
- D. Schedule performance indexing.
正解: D
質問 84
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?
- A. The activities occur in series with a 15-day lag.
- B. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
- C. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
- D. The activities run concurrently.
正解: A
質問 85
......
試験問題と解答はAACE-PSP学習ガイド問題解答:https://www.goshiken.com/AACE-International/AACE-PSP-mondaishu.html
練習用AACE-PSPにはGoShiken顕著な問題集はあなたをPlanning & Scheduling Professional (PSP) Exam試験合格させます合格させる:https://drive.google.com/open?id=1heuyPrT2zdoax8Y_gl8rK6uSclfYq-Co