質問 68
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

  • A. Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.
  • B. Use the forward-looking critical path of the most current updates.
  • C. Use the progressed portion of the critical path of all the updates previous to the current update.
  • D. Use the progressed portion of the critical path of the baseline schedule.

正解: B

 

質問 69
Which is NOT an industry-recognized methodology for quantifying critical delay?

  • A. Gantt Chart.
  • B. Periodic Windows.
  • C. Collapsed As-Built.
  • D. Time Impact.

正解: A

 

質問 70
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:

  • A. Predecessor is activity 9001, successor is activity 9002
  • B. Predecessor is activity 5001, successor is activity 8002
  • C. Predecessor is activity 4001, successor is activity 8001
  • D. Predecessor is activity 5001, successor is activity 8001

正解: D

 

質問 71
Time-scaled logic diagrams are

  • A. Only calculated using a computer.
  • B. Logic networks that are drawn to match the calendar.
  • C. Used to calculate the most probable activity duration.
  • D. The same as a pure-logic diagram.

正解: B

 

質問 72
The activity with the most total float is:

  • A. Activity I.
  • B. Activity C.
  • C. Activity F.
  • D. Activity D.

正解: A

 

質問 73
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

  • A. Preferential logic.
  • B. Start and finish constraints.
  • C. Multiple calendars.
  • D. Front end loading.

正解: D

 

質問 74
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?

  • A. 2003 and 7001.
  • B. 2004.
  • C. 4001, 5001 and 6001.
  • D. 4001 and 5001.

正解: D

 

質問 75
Which of the following is NOT required when performing weekly or monthly schedule updates?

  • A. Remaining duration of activities.
  • B. Actual finish of activities.
  • C. Percent complete.
  • D. Original duration of activities.

正解: A

 

質問 76
If no time extensions are granted and all actual delays are as described above, what will the total float calculation be at the end of the project?

  • A. 10 calendar days.
  • B. -14 calendar days.
  • C. -20 calendar days.
  • D. 0 calendar days.

正解: B

 

質問 77
What is a key first step in developing a critical path method schedule?

  • A. Defining the execution plan to meet the required scope of work.
  • B. Setting out the resource to be used and its limitations.
  • C. Drawing the logic diagram.
  • D. Drawing a bar chart of the key phrases of the work.

正解: C

 

質問 78
What owner action could have mitigated the late completion of the project?

  • A. Self-perform more of the work.
  • B. Hire a more senior project manager.
  • C. Prepare better structural steel drawings.
  • D. Use a procurement agent to monitor and expedite equipment deliveries.

正解: D

 

質問 79
Which of the following is NOT required when initially planning a project?

  • A. Logical relationships between the tasks.
  • B. Resource Identification and leveling.
  • C. A schedule that identifies tasks required on a project.
  • D. The duration of each task.

正解: D

 

質問 80
What is the result of a forward pass calculation?

  • A. Early start and early finish date for individual activities
  • B. Value of total float for individual activities
  • C. Critical path
  • D. Value of free float for individual activities

正解: A

 

質問 81
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

  • A. The schedule has too much detail to reflect an accurate critical path.
  • B. Different calendars are assigned to certain activities in the logical chain.
  • C. The schedule is projecting an "early completion".
  • D. Certain activities in the critical path have no successors.

正解: D

 

質問 82
Resource planning must take all of the following into account except for

  • A. Earned value techniques established for the project.
  • B. Cash flow (expenditure) limitations for completing work on the project.
  • C. Time available to complete the project.
  • D. Types of materials, equipment and labor skills required to complete the project.

正解: A

 

質問 83
Which of the following is NOT a tool or technique used to perform scope planning?

  • A. Benefit cost analysis.
  • B. Expert Judgment.
  • C. Alternatives identification.
  • D. Schedule performance indexing.

正解: D

 

質問 84
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

  • A. The activities occur in series with a 15-day lag.
  • B. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
  • C. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
  • D. The activities run concurrently.

正解: A

 