質問 # 18
The sum of all budgets for work scheduled to be accomplished within a given time period is the
____________.

  • A. Budgeted cost of work performed (BCWP)
  • B. Budgeted cost of work scheduled (BCWS)
  • C. Budget at completion (BAC)
  • D. Estimate at completion (EAC)

正解:C


質問 # 19
What method offers the best chance of the schedule being used effectively to implement the project in the field?

  • A. Allow large time contingencies on milestones and completion deadlines.
  • B. Include detailed and stringent set of scheduling specifications in the contract.
  • C. Issue detailed schedule updates as frequently as possible.
  • D. Obtain consent and agreement to the schedule from the key project personnel.

正解:D


質問 # 20
Total float is defined as the amount of time an activity can be delayed without impacting

  • A. The buoyancy of a successor activity
  • B. The overall project completion
  • C. The next activity
  • D. The end of that activity

正解:B


質問 # 21
By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:

  • A. Productivity efficiency.
  • B. Production output.
  • C. Productivity loss.
  • D. Acceleration.

正解:C


質問 # 22
What owner action could have mitigated the late completion of the project?

  • A. Hire a more senior project manager.
  • B. Use a procurement agent to monitor and expedite equipment deliveries.
  • C. Prepare better structural steel drawings.
  • D. Self-perform more of the work.

正解:B


質問 # 23
Determine the correct formula and date for the late start for Activity 9001.

  • A. LF.9001 Dur.9001 -> 11-20-02.
  • B. There is insufficient data provided to calculate the answer.
  • C. LS.6001 Dur.6001 -> 11-20-02.
  • D. The early finish is required in order to determine the answer.

正解:A


質問 # 24
Which of the following is NOT input data to the construction planning process?

  • A. Input from the owner
  • B. Bonding capacity of subcontractors
  • C. Input from the contractor
  • D. The contract

正解:B


質問 # 25
When resource leveling craft labor for a critical path schedule, the scheduler

  • A. Need not consider its effects, as it is a theoretical concept with limited application to construction projects.
  • B. Need only consider the non-union crafts persons.
  • C. Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.
  • D. Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.

正解:D


質問 # 26
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

  • A. Multiple calendars.
  • B. Front end loading.
  • C. Preferential logic.
  • D. Start and finish constraints.

正解:B


質問 # 27
Which statement is true?

  • A. Where compensability can be established, excusability is assumed.
  • B. Where compensability cannot be established, excusability is a given.
  • C. Where compensability can be established, excusabltity cannot be assumed.
  • D. Where compensability cannot be established, excusability is assumed.

正解:D


質問 # 28
Which of the following will always describe the critical path? The path with

  • A. Zero float.
  • B. The longest duration through the network.
  • C. The shortest duration and negative float.
  • D. Negative float.

正解:A


質問 # 29
What is a key first step in developing a critical path method schedule?

  • A. Drawing a bar chart of the key phrases of the work.
  • B. Defining the execution plan to meet the required scope of work.
  • C. Setting out the resource to be used and its limitations.
  • D. Drawing the logic diagram.

正解:D


質問 # 30
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?

  • A. S.
  • B. W.
  • C. C.
  • D. B.

正解:A


質問 # 31
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

  • A. 10 days.
  • B. 5 days.
  • C. 15 days.
  • D. 0 days.

正解:D


質問 # 32
Which of the following is NOT required when performing weekly or monthly schedule updates?

  • A. Original duration of activities.
  • B. Actual finish of activities.
  • C. Remaining duration of activities.
  • D. Percent complete.

正解:C


質問 # 33
What is the remaining work duration of Active D?

  • A. 0
  • B. 4.
  • C. 8.
  • D. 3.

正解:B


質問 # 34
How many work days does it take to move the product from testing to sale?

  • A. 70.
  • B. 100.
  • C. 60.
  • D. 90.

正解:B


質問 # 35
Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT

  • A. Use gross building square footages. The pluses and minuses all average out.
  • B. Look at each activity independently and don't follow specific logic paths when assigning activity durations.
  • C. Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.
  • D. Use the people responsible for performing the work as a resource to assign activity durations.

正解:A


質問 # 36
When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

  • A. Assigned party responsibility for each work task
  • B. Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID
  • C. Detailed listing of working days for each calendar used
  • D. Tabular listing of activities showing duration, calendar ID, early and late dates

正解:A


質問 # 37
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

  • A. 10 days.
  • B. 0 days.
  • C. 5 days.
  • D. 15 days.

正解:C


質問 # 38
If no time extensions are granted and all actual delays are as described above, what will the total float calculation be at the end of the project?

  • A. 0 calendar days.
  • B. -14 calendar days.
  • C. 10 calendar days.
  • D. -20 calendar days.

正解:B


質問 # 39
A driving relationship is _____________________.

  • A. The link between a predecessor and the activity whose dates it controls.
  • B. The link between two related activities.
  • C. A finish-to-start relationship.
  • D. A critical relationship.

正解:A


質問 # 40
In its simplest form, what is the main drawback of critical path method scheduling?

  • A. It doesn't account for interdependent between activities.
  • B. It requires a backward pass to calculate late dates.
  • C. It assumes that resources are unlimited.
  • D. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.

正解:C


質問 # 41
Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?

  • A. 50 lifts
  • B. 80 lifts
  • C. 20 lifts
  • D. 5 lifts

正解:A


質問 # 42
......