AACE-PSP問題集120問でAACE Certificationを確実実践 [Q21-Q38]

Share

AACE-PSP問題集120問でAACE Certificationを確実実践

リアル最新AACE-PSP試験問題AACE-PSP問題集


AACE Internationalは、コストエンジニアリング、プロジェクト管理、計画およびスケジューリングの専門家の専門協会です。協会は、AACE-PSP(計画&スケジューリング専門家)認定を含む、メンバーにさまざまな認定を提供しています。 AACE-PSP認定は、プロジェクトやプログラムの活動の計画とスケジューリングに関与している個人向けに設計されています。この認定プログラムは世界中で認識されており、専門家の計画とスケジューリングのベンチマークと見なされています。

 

質問 # 21
What was the original planned duration for Activity A through Activity G?

  • A. 25.
  • B. 26.
  • C. 28.
  • D. 24.

正解:C


質問 # 22
If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?

  • A. The Eichleay formula
  • B. Black-Scholes model
  • C. Time impact analysis
  • D. Historical production rates

正解:D


質問 # 23
When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

  • A. Detailed listing of working days for each calendar used
  • B. Tabular listing of activities showing duration, calendar ID, early and late dates
  • C. Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID
  • D. Assigned party responsibility for each work task

正解:D


質問 # 24
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

  • A. 4 cranes
  • B. 3 cranes
  • C. 2 cranes
  • D. 1 crane

正解:C


質問 # 25
How could the structural steel drawing delay have been prevented?

  • A. Allow adequate time for review and resubmittal in the baseline schedule.
  • B. Release the structural steel for fabrication concurrent with review of structural steel shop drawings.
  • C. Switch to post-tensioned concrete construction.
  • D. Add a time buffer at the end of structural steel activities.

正解:D


質問 # 26
If no time extensions are granted and all actual delays are as described above, what will the total float calculation be at the end of the project?

  • A. -14 calendar days.
  • B. 10 calendar days.
  • C. 0 calendar days.
  • D. -20 calendar days.

正解:A


質問 # 27
At a minimum, periodic reporting must be done at what interval?

  • A. As requested by the project manager.
  • B. As requested by the owner.
  • C. Monthly.
  • D. As specified in the contract documents.

正解:D


質問 # 28
Identify the late finish to develop plans and specs.

  • A. 9 months.
  • B. 7 months.
  • C. 10 months.
  • D. 8 months.

正解:A


質問 # 29
Determine the driving activity for Activity 10001.

  • A. Activity 11001.
  • B. Activity 9005.
  • C. There is no driving activity for Activity 10001 in the backward pass.
  • D. Activity 10002.

正解:D


質問 # 30
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

  • A. The delay must not cause monetary harm to the defendant.
  • B. The delay must be concurrent with the delay attributable to both parties.
  • C. The delay must affect the critical path.
  • D. The delay must affect the contractor's planned construction schedule.

正解:C


質問 # 31
Which of the following will always describe the critical path? The path with

  • A. Zero float.
  • B. Negative float.
  • C. The longest duration through the network.
  • D. The shortest duration and negative float.

正解:A


質問 # 32
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?

  • A. 14.
  • B. 12.
  • C. 13.
  • D. Cannot be determined.

正解:B


質問 # 33
Identify the minimum project duration.

  • A. 16 months.
  • B. 19 months.
  • C. 21 months.
  • D. 20 months.

正解:D


質問 # 34
Budgeted cost of work scheduled is _______________________.

  • A. The total authorized budget for accomplishing the project scope
  • B. The value of the completed work expressed in terms of the budget assigned to that work
  • C. The sum of all budgets for work scheduled to be accomplished within a given time period
  • D. The expected total cost of an activity, group of activities or the project

正解:D


質問 # 35
Total float is defined as the amount of time an activity can be delayed without impacting

  • A. The overall project completion
  • B. The end of that activity
  • C. The next activity
  • D. The buoyancy of a successor activity

正解:A


質問 # 36
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

  • A. 15 days.
  • B. 10 days.
  • C. 0 days.
  • D. 5 days.

正解:D


質問 # 37
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

  • A. Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.
  • B. Use the progressed portion of the critical path of all the updates previous to the current update.
  • C. Use the forward-looking critical path of the most current updates.
  • D. Use the progressed portion of the critical path of the baseline schedule.

正解:C


質問 # 38
......


AACE-PSP認定プログラムは、プロジェクト計画とスケジュールの専門知識を検証する機会を提供します。この認定プログラムは、職場での競争力を高め、プロの信頼性を向上させます。AACE-PSP認定を取得することにより、プロフェッショナルは継続的な学習と職業的発展に対する責任を示すことができます。

 