PDF問題(2025年最新)実際のAACE International AACE-PSP試験問題 [Q39-Q57]

Share

PDF問題(2025年最新)実際のAACE International AACE-PSP試験問題

問題集返金保証付きのAACE-PSP問題集には90%オフされます


AACE-PSP認定試験は、プロジェクトマネジメント業界の専門家にとって、卓越性の証としてグローバルに認められています。この認定を取得することは、個人の職業への献身と最新の業界標準やベストプラクティスに対する取り組みを示すものです。この認定は、新しいキャリアの機会を開き、高い給与とより大きな雇用安定性につながることもあります。全体的に、AACE-PSP認定試験は、プロジェクトマネジメント、コストエンジニアリング、総コスト管理のキャリアを進めたい専門家にとって貴重な投資となります。

 

質問 # 39
If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using

  • A. Finish-no-earlier constraint on the last activity
  • B. Finish-no-earlier constraint on the first activity
  • C. Finish-no-later constraint on the last activity
  • D. Start-no-later constraint on the first activity

正解:C


質問 # 40
Budgeted cost of work scheduled is _______________________.

  • A. The expected total cost of an activity, group of activities or the project
  • B. The sum of all budgets for work scheduled to be accomplished within a given time period
  • C. The value of the completed work expressed in terms of the budget assigned to that work
  • D. The total authorized budget for accomplishing the project scope

正解:A


質問 # 41
Estimate to complete (ETC) is __________________.

  • A. The expected remaining cost needed to complete an activity, group of activities or the project
  • B. The expected total cost of an activity, group of activities or the project
  • C. The value of the completed work expressed in terms of the budget assigned to that work
  • D. The costs actually incurred in accomplishing the work performed

正解:A


質問 # 42
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

  • A. Not suitable for projects with long durations.
  • B. Not suitable for complicated projects with multiple planned critical paths.
  • C. Less accurate as the analysis advances through the project.
  • D. Accuracy is increased by inserting delaying events into the as-planned schedule.

正解:D


質問 # 43
Which of the following is NOT true?

  • A. Multiple calendars can affect the total float calculation.
  • B. Remaining durations can exceed original durations.
  • C. A network must contain only one Critical Path.
  • D. Constraints can interfere with the longest path calculation.

正解:B


質問 # 44
Which is NOT an industry-recognized methodology for quantifying critical delay?

  • A. Gantt Chart.
  • B. Time Impact.
  • C. Periodic Windows.
  • D. Collapsed As-Built.

正解:A


質問 # 45
The addition of which of the following relationships would cause a logic loop?

  • A. O H - D
  • B. O l-C
  • C. O F-I
  • D. O C - J

正解:B


質問 # 46
A driving relationship is _____________________.

  • A. The link between two related activities.
  • B. The link between a predecessor and the activity whose dates it controls.
  • C. A finish-to-start relationship.
  • D. A critical relationship.

正解:B


質問 # 47
Which of the following project planning situations is the most frequent contributor to cost overruns?

  • A. Inappropriate definition of work breakdown structure
  • B. Inadequate definition of scope at the estimate (budget) stage
  • C. lack of detailed planning for operational start-up
  • D. Insufficient planning for change management

正解:B


質問 # 48
Which of these letters, symbols or words best approximates the graphical shape of a project's cumulative BCWS?

  • A. _
  • B. Bell curve
  • C. S
  • D. /

正解:C


質問 # 49
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

  • A. 09-28-01.
  • B. 09-15-01.
  • C. 09-18-01.
  • D. 09-08-01.

正解:D


質問 # 50
Budgeted cost of work scheduled is _______________________.

  • A. The expected total cost of an activity, group of activities or the project
  • B. The sum of all budgets for work scheduled to be accomplished within a given time period
  • C. The value of the completed work expressed in terms of the budget assigned to that work
  • D. The total authorized budget for accomplishing the project scope

正解:B


質問 # 51
Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?

  • A. 24 lifts
  • B. 30 lifts
  • C. 48 lifts
  • D. 36 lifts

正解:D


質問 # 52
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

  • A. 3 cranes
  • B. 4 cranes
  • C. 2 cranes
  • D. 1 crane

正解:C


質問 # 53
Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?

  • A. After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
  • B. After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
  • C. After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.

正解:A


質問 # 54
Determine the correct formula and date for the late finish for Activity 2002.

  • A. LS.2003 - 1 day -> 10-05-01.
  • B. LS.2003 + 1 day -> 10-07-01.
  • C. LS.2003 - 1 day -> 11.06.01.
  • D. LS.2003 - 1 day -> 10-06-01.

正解:A


質問 # 55
At a minimum, periodic reporting must be done at what interval?

  • A. As requested by the project manager.
  • B. As requested by the owner.
  • C. Monthly.
  • D. As specified in the contract documents.

正解:D


質問 # 56
Determine the correct formula and date for the late finish for Activity 6002.

  • A. LS of 6003 less 1 day equaling 09 Mar 2023
  • B. LS of 6003 less 1 day equaling 09 Mar 2022
  • C. LS of 6003 plus 1 day equaling 09 Mar 2023
  • D. LS of 6003 plus 1 day equaling 09 Mar 2022

正解:C


質問 # 57
......


AACE-PSP認定試験では、プロジェクトの計画、スケジューリング、リソース割り当て、コスト管理、リスク管理など、プロジェクトの計画とスケジューリングに関連する幅広いトピックをカバーしています。この試験は、実世界のシナリオでこれらの概念の候補者の理解と適用をテストするように設計されています。この試験は、複数の選択の質問で構成され、安全で提案された環境で管理されています。

 

更新された2025年04月合格させるAACE-PSP試験リアル練習テスト問題:https://www.goshiken.com/AACE-International/AACE-PSP-mondaishu.html

あなたを合格させる試験には100%確認済みAACE-PSP試験問題:https://drive.google.com/open?id=1EtOEX-xeYHJc2Q6A43P_9iTOBIwu1rmd