質問 # 87
Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?

  • A. Manage by exception
  • B. Continued business justification
  • C. Learn from experience
  • D. Manage by stages

正解:D

解説:
Explanation/Reference:
Reference https://www.whatisprince2.net/prince2-theme-plans.php


質問 # 88
Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?

  • A. Manage by exception
  • B. Continued business justification
  • C. Learn from experience
  • D. Manage by stages

正解:D

解説:
Section: Volume B
Explanation/Reference:
Reference https://www.whatisprince2.net/prince2-theme-plans.php


質問 # 89
In what process is the authorization to deliver the project's products given?

  • A. Starting up a Project
  • B. Directing a Project
  • C. Initiating a Project
  • D. Managing a Stage Boundary

正解:B


質問 # 90
Identify the missing words in the following sentence.
A problem/concern, a request for change and [ ? ] are the three types of issue.

  • A. a threat
  • B. an off-specification
  • C. a constraint
  • D. a deviation from tolerance

正解:B


質問 # 91
Which of the following is NOT an event-driven control?

  • A. End of a stage
  • B. Checkpoint Report
  • C. Project mandate
  • D. Exception Report

正解:B


質問 # 92
Which is an objective of the Managing Product Delivery process?

  • A. Ensure that work on products is authorized and agreed with the team
  • B. Report progress to the Project Board
  • C. Sign-off completed Work Packages
  • D. Ensure the Business Case is kept under review

正解:A

解説:
Section: Volume A


質問 # 93
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?

  • A. When a change is raised
  • B. At the start of the project
  • C. Throughout each stage
  • D. In exception situations

正解:C

解説:
Explanation/Reference:
Reference https://www.prince2.com/blog/the-7-principles-themes-and-processes-of-prince2/


質問 # 94
Which is a purpose of the 'directing a project' process?

  • A. To control the day-to-day running of the project
  • B. To create and authorize the project mandate
  • C. To ensure that work on products allocated to the team is authorized and agreed
  • D. To delegate day-to-day management of the project to the project manager

正解:D


質問 # 95
Which is a type of issue?

  • A. An expected dis-benefit
  • B. An off-specification
  • C. A scope tolerance
  • D. A project outcome

正解:B


質問 # 96
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

  • A. Risk response
  • B. Risk description
  • C. Risk status
  • D. Risk category

正解:A


質問 # 97
Which is a purpose of quality planning?

  • A. Document approval records for those project products that have met their quality criteria
  • B. Detail the acceptance criteria, in order for the Project Board to agree the level of quality expected of the project's product
  • C. Define the structure of the project management team
  • D. Produce the Project Plan with resource and schedule information

正解:B


質問 # 98
What should the benefits management approach define?

  • A. How the project has progressed against its plans
  • B. The suitability of the project management team structure
  • C. What actions will be taken to ensure the project's outcomes are achieved
  • D. What will be used to record the effectiveness of the project's approaches

正解:A

解説:
Section: Volume B
Explanation/Reference:


質問 # 99
Which is a benefit of using PRINCE2?

  • A. Prevents any changes once the scope of a project has been agreed
  • B. Includes techniquesfor critical path analysis and earned value analysis
  • C. Provides a defined structure of accountability, delegation, authority and communication
  • D. Enables a Project Manager to be accountable for the success of a project

正解:C


質問 # 100
From whom does a Team Manager obtain approval for a completed product?

  • A. The authority defined in the Product Description
  • B. Senior Supplier
  • C. Project Support
  • D. Project Manager

正解:A


質問 # 101
What do customer's quality expectations identify?

  • A. Standards that must be used in order to meet the level of quality needed
  • B. Skills required to develop the project product
  • C. Reviewer names for each product
  • D. Measurable definitions of the attributes required for a set of products to be acceptable to the customer

正解:A


質問 # 102
Which theme provides all management levels within the project management team with mechanisms for monitoring and control?

  • A. Quality
  • B. Organization
  • C. Change
  • D. Progress

正解:D

解説:
Reference https://www.whatisprince2.net/prince2-theme-progress.php


質問 # 103
Upon what environment is PRINCE2 based?

  • A. Programme
  • B. Operational
  • C. Customer/supplier
  • D. Configuration

正解:C


質問 # 104
Which statements about quality assurance and project assurance are CORRECT?
1. They are both independent of the project manager
2. They are both the responsibility of the project board
3. They are both independent from the project management team
4. They both assure that applicable standards are being used

  • A. 2 and 3
  • B. 1 and 4
  • C. 3 and 4
  • D. 1 and 2

正解:C


質問 # 105
Which of the following are true statements about a Project Brief?
1 . Used to provide a foundation for the Initiating a Project process
2 . Created in the Starting up a Project process
3 . Used by the Project Board to make an assessment of a project's progress
4 . Used as the basis of the Project Initiation Documentation

  • A. 1, 2, 4
  • B. 1, 2, 3
  • C. 1, 3, 4
  • D. 2, 3, 4

正解:A


質問 # 106
What must be produced to meet the minimum requirements for applying the change theme?

  • A. Details of the status of all products being produced
  • B. Documentation on the corrective action for an issue
  • C. Documentation on the version of each product
  • D. Details of the decisions taken on all issues

正解:D

解説:
Reference http://prince2.wiki/Themes#Change_Theme