PRINCE2 PRINCE2-Foundation 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • どの管理製品が入力されているかを述べる| そして7つのプロセスからの出力|主な目的を述べる| と主要な内容| そのうちの
トピック 2
  • すべての役割の目的と主な内容を説明してください| 7つの原則| 7つのテーマと7つのプロセス

 

質問 137
Which is a purpose of a Project Product Description?

  • A. Form part of the Work Package for the project product
  • B. Provide the initial project budget to be refined in the Business Case
  • C. Document the project mandate and gain approval for the project from the Project Board
  • D. Define the quality required of the project's product

正解: D

 

質問 138
Which is a true statement about PRINCE2 event-driven controls?

  • A. Checkpoint Reports are event-driven controls
  • B. Event-driven controls are produced at the frequency defined in a Work Package
  • C. Event-driven controls are used for decision making
  • D. Event-driven controls take place at predefined periodic intervals

正解: C

解説:
Section: Volume B

 

質問 139
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

  • A. Risk response
  • B. Risk category
  • C. Risk status
  • D. Risk description

正解: A

 

質問 140
Which is a task of product-based planning?

  • A. Identify activities and dependencies
  • B. Produce Product Status Accounts
  • C. Prepare the Work Packages
  • D. Write the Project Product Description

正解: D

 

質問 141
In which product would you find a product's quality tolerance defined?

  • A. Product Description
  • B. Quality Management Strategy
  • C. Quality Register
  • D. Configuration Item Record

正解: A

 

質問 142
Which is an objective of the 'directing a project' process?

  • A. To define how risks, issues and changes will be managed
  • B. To ensure corporate or programme management has an interface to the project
  • C. To obtain approval for completed products
  • D. To review and approve a project mandate

正解: B

解説:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Directing_a_Project#Objective

 

質問 143
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

  • A. Directing a Project
  • B. Controlling a Stage
  • C. Managing a Stage Boundary
  • D. Starting up a Project

正解: B

 

質問 144
Which describes the 'Identify Risks' step within the recommended risk management procedure?

  • A. Identify the roles to be involved in risk management activities
  • B. Gather information about the project environment and objectives
  • C. Identify uncertainties that may impact on the delivery of the project objectives
  • D. Identify responses to risks documented in the Business Case

正解: C

 

質問 145
Which product defines how the project board should approve the management products produced during the 'initiating a project' process?

  • A. Quality management approach
  • B. Initiation stage plan
  • C. Project plan
  • D. Communication management approach

正解: C

 

質問 146
Who is responsible for documenting any tailoring of the business case theme?

  • A. Business project assurance
  • B. Executive
  • C. Project manager
  • D. Corporate management

正解: C

解説:
Section: Volume B

 

質問 147
Which are characteristics of stakeholders?
1. They are often affected by the project
2. They agree with every project objective
3. They are only/always external to the corporate organization
4. They typically interact with the project

  • A. 2 and 3
  • B. 1 and 4
  • C. 1 and 2
  • D. 3 and 4

正解: B

解説:
Section: Volume B
Explanation/Reference: https://www.prince2.com/blog/how-to-identify-stakeholders/

 

質問 148
Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

  • A. Develop a project's products
  • B. Ensure the technical integrity of a project
  • C. Specify the desired result
  • D. Provide the resources and skills to deliver the desired result

正解: C

 

質問 149
Which is NOT a recommended quality review team role?

  • A. Administrator
  • B. Producer
  • C. Reviewer
  • D. Chair

正解: B

 

質問 150
Which is part of quality control?

  • A. Undertake quality reviews
  • B. Provide assurance that the project is being conducted properly
  • C. Write Product Descriptions
  • D. Document the customer's quality expectations

正解: A

解説:
Section: Volume B

 

質問 151
Identify the missing words in the following sentence.
At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.

  • A. Quality Management Strategy
  • B. Communication Management Strategy
  • C. Stage Plan
  • D. Follow-on action recommendations

正解: B

 

質問 152
Which product is created in the 'starting up a project' process to define and confirm the scope of the project?

  • A. Project initiation documentation
  • B. Project mandate
  • C. Initiation stage plan
  • D. Project brief

正解: C

 

質問 153
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?

  • A. Throughout each stage
  • B. In exception situations
  • C. At the start of the project
  • D. When a change is raised

正解: A

解説:
Explanation/Reference:
Reference https://www.prince2.com/blog/the-7-principles-themes-and-processes-of-prince2/

 

質問 154
Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity

  • A. Reduce
  • B. Avoid
  • C. Transfer
  • D. Share

正解: D

 

質問 155
Which process provides the Project Board with the information it requires in order to commit resources to the project?

  • A. Managing Product Delivery
  • B. Directinga Project
  • C. Initiating a Project
  • D. Controlling a Stage

正解: C

 

質問 156
Identify the missing words in the following sentence.
The role of [ ? ] is assigned to the project manager if it is not allocated to another person.

  • A. senior user
  • B. project assurance
  • C. change authority
  • D. project support

正解: D

解説:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Roles_and_responsibilities

 

質問 157
Which is a typical core activity within configuration management?

  • A. Quality control
  • B. Status accounting
  • C. Assessment
  • D. Communication

正解: B

 

質問 158
......

PRINCE2-Foundation問題集が合格させる、一日でPRINCE2 Certification試験合格:https://www.goshiken.com/PRINCE2/PRINCE2-Foundation-mondaishu.html

最新でリアルなPRINCE2 PRINCE2-Foundation試験問題集解答:https://drive.google.com/open?id=1Bjx_0-49SmBi9ZCYsP3XfSK7exa2B5VZ