[2023年11月] 練習で合格させる問題学習ガイドは PRINCE2-Foundation 試験問題集 [Q148-Q165]

Share

[2023年11月] 問題集練習試験問題学習ガイドはPRINCE2-Foundation試験合格させます

PRINCE2-Foundation問題集には練習試験問題解答


PRINCE2-Foundation認定は、PRINCE2方法論の理解を示すグローバルに認められた資格です。この認定は、プロジェクトマネジメントのキャリアをスタートさせたい人や、プロジェクトマネジメントのスキルを向上させたい人にとって特に価値があります。また、PRINCE2方法論をプロジェクトマネジメントの標準として採用したい組織にとっても有益であり、プロジェクトマネージャーが方法論の共通理解を持っていることを保証します。

 

質問 # 148
What information should be recorded in the quality register?

  • A. Planned activities to determine whether the products are fit for purpose
  • B. Off-specifications that will occur during the project
  • C. Lessons that the project will capture and use during the project
  • D. Potential threats to the project's objectives and how they will be managed

正解:C

解説:
Explanation/Reference:
Reference https://mplaza.pm/prince2-quality-register-template/


質問 # 149
Which is a purpose of the Managing Product Delivery process?

  • A. Enable the Project Board to requestupdates to the current Team Plan
  • B. Provide a controlled link between the Project Manager and the Team Manager(s)
  • C. Establish solid foundations for the project
  • D. Enable the Senior Supplier to be provided with sufficient information by the Project
    Manager so that they can review the success of the current Work Package

正解:B


質問 # 150
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

  • A. Project Board
  • B. Executive
  • C. Project Assurance
  • D. Corporate group

正解:D


質問 # 151
Which statement about the quality review technique is FALSE?

  • A. It is used to gain wider acceptance of a product by involving key interested parties
  • B. It enables a check to be made on a product's fitness for purpose
  • C. It supports the management of future changes by providing a baseline for a product
  • D. It defines the quality responsibilities of the project team

正解:D

解説:
Section: Volume B


質問 # 152
Why is a project brief produced?

  • A. To be used by the project board as a basis for reviewing the progress of a project
  • B. To provide a full and firm foundation for the initiation of a project
  • C. To act as a trigger for the 'starting up a project' process
  • D. To record the how the project will communicate with its stakeholders

正解:B


質問 # 153
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

  • A. Manage by stages
  • B. Continued business justification
  • C. Manage by exception
  • D. Learn from experience

正解:C

解説:
Topic 3, Volume C


質問 # 154
Which product documents the information needed to demonstrate continued business justification?

  • A. Communication Management Strategy
  • B. Quality Management Strategy
  • C. Business Case
  • D. Project Product Description

正解:C


質問 # 155
Which is NOT one of the levels of plan recommended by PRINCE2?

  • A. Benefits Review Plan
  • B. Stage Plan
  • C. Team Plan
  • D. Project Plan

正解:A


質問 # 156
Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved. Packages for the work performed in the final stage.

  • A. Both 1 and 2 are true
  • B. Neither 1 or 2 are true
  • C. Only 1 is true
  • D. Only 2 is true

正解:D


質問 # 157
Which is a purpose of the Managing a Stage Boundary process?

  • A. Provide the Project Board with sufficient information for approving the next stage
  • B. Control the link between the Project Manager and the Team Manager(s)
  • C. Approve the next Stage Plan
  • D. Review and close any risks and issues identified during the previous stage

正解:A

解説:
Section: Volume B


質問 # 158
Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

  • A. Starting up a project
  • B. Directing a project
  • C. Managing a stage boundary
  • D. Controlling a stage

正解:D

解説:
Reference https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-controlling-a-stage-process-in-prince2


質問 # 159
Identify the missing words in the following sentence. A Change Authority may be given a [?] to enable it to finance new requirements.

  • A. scope tolerance
  • B. cost tolerance
  • C. change budget
  • D. risk budget

正解:C


質問 # 160
Which is an objective of the 'starting up a project' process?

  • A. To approve the initiation stage
  • B. To appoint the project management team
  • C. To select the project mandate
  • D. To define the project quality management approach

正解:A

解説:
Explanation/Reference:
Reference http://prince2.wiki/Starting_Up_a_Project#Purpose


質問 # 161
If an informal issue is defined as a problem or concern, where should it first be recorded?

  • A. Daily Log
  • B. Risk Register
  • C. Issue Register
  • D. Exception Report

正解:A


質問 # 162
Which of the following statements about stakeholders are true?
1.Someone who thinks they will be affected by a project is a stakeholder on that project.
2.Stakeholders may be internal or external to the corporate organization.

  • A. Neither 1 or 2 are true
  • B. Both 1 and 2 are true
  • C. Only 1 is true
  • D. Only 2 is true

正解:B


質問 # 163
Identify the missing words in the following sentence, The six aspects of project performance to be managed are [?] costs, timescales and scope,

  • A. benefits, customers, quality,
  • B. change, quality, progress,
  • C. benefits, quality, risk,
  • D. benefits, progress, risk,

正解:C


質問 # 164
Which PRINCE2 principle ensures that members of the project management team know what they are expected to contribute?

  • A. Tailor to suit the project environment
  • B. Defined roles and responsibilities
  • C. Learn from experience
  • D. Manage by exception

正解:B

解説:
Section: Volume B
Explanation/Reference:
Reference https://www.wrike.com/blog/project-management-basics-prince2-explained/


質問 # 165
......

無料PRINCE2 Certification PRINCE2-Foundation試験問題:https://www.goshiken.com/PRINCE2/PRINCE2-Foundation-mondaishu.html

PRINCE2-FoundationはPRINCE2 Certification実際の無料試験練習テスト:https://drive.google.com/open?id=1Bjx_0-49SmBi9ZCYsP3XfSK7exa2B5VZ