質問 # 148
What information should be recorded in the quality register?
- A. Planned activities to determine whether the products are fit for purpose
- B. Off-specifications that will occur during the project
- C. Lessons that the project will capture and use during the project
- D. Potential threats to the project's objectives and how they will be managed
正解:C
解説:
Explanation/Reference:
Reference https://mplaza.pm/prince2-quality-register-template/
質問 # 149
Which is a purpose of the Managing Product Delivery process?
- A. Enable the Project Board to requestupdates to the current Team Plan
- B. Provide a controlled link between the Project Manager and the Team Manager(s)
- C. Establish solid foundations for the project
- D. Enable the Senior Supplier to be provided with sufficient information by the Project
Manager so that they can review the success of the current Work Package
正解:B
質問 # 150
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?
- A. Project Board
- B. Executive
- C. Project Assurance
- D. Corporate group
正解:D
質問 # 151
Which statement about the quality review technique is FALSE?
- A. It is used to gain wider acceptance of a product by involving key interested parties
- B. It enables a check to be made on a product's fitness for purpose
- C. It supports the management of future changes by providing a baseline for a product
- D. It defines the quality responsibilities of the project team
正解:D
解説:
Section: Volume B
質問 # 152
Why is a project brief produced?
- A. To be used by the project board as a basis for reviewing the progress of a project
- B. To provide a full and firm foundation for the initiation of a project
- C. To act as a trigger for the 'starting up a project' process
- D. To record the how the project will communicate with its stakeholders
正解:B
質問 # 153
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
- A. Manage by stages
- B. Continued business justification
- C. Manage by exception
- D. Learn from experience
正解:C
解説:
Topic 3, Volume C
質問 # 154
Which product documents the information needed to demonstrate continued business justification?
- A. Communication Management Strategy
- B. Quality Management Strategy
- C. Business Case
- D. Project Product Description
正解:C
質問 # 155
Which is NOT one of the levels of plan recommended by PRINCE2?
- A. Benefits Review Plan
- B. Stage Plan
- C. Team Plan
- D. Project Plan
正解:A
質問 # 156
Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved. Packages for the work performed in the final stage.
- A. Both 1 and 2 are true
- B. Neither 1 or 2 are true
- C. Only 1 is true
- D. Only 2 is true
正解:D
質問 # 157
Which is a purpose of the Managing a Stage Boundary process?
- A. Provide the Project Board with sufficient information for approving the next stage
- B. Control the link between the Project Manager and the Team Manager(s)
- C. Approve the next Stage Plan
- D. Review and close any risks and issues identified during the previous stage
正解:A
解説:
Section: Volume B
質問 # 158
Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
- A. Starting up a project
- B. Directing a project
- C. Managing a stage boundary
- D. Controlling a stage
正解:D
解説:
Reference https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-controlling-a-stage-process-in-prince2
質問 # 159
Identify the missing words in the following sentence. A Change Authority may be given a [?] to enable it to finance new requirements.
- A. scope tolerance
- B. cost tolerance
- C. change budget
- D. risk budget
正解:C
質問 # 160
Which is an objective of the 'starting up a project' process?
- A. To approve the initiation stage
- B. To appoint the project management team
- C. To select the project mandate
- D. To define the project quality management approach
正解:A
解説:
Explanation/Reference:
Reference http://prince2.wiki/Starting_Up_a_Project#Purpose
質問 # 161
If an informal issue is defined as a problem or concern, where should it first be recorded?
- A. Daily Log
- B. Risk Register
- C. Issue Register
- D. Exception Report
正解:A
質問 # 162
Which of the following statements about stakeholders are true?
1.Someone who thinks they will be affected by a project is a stakeholder on that project.
2.Stakeholders may be internal or external to the corporate organization.
- A. Neither 1 or 2 are true
- B. Both 1 and 2 are true
- C. Only 1 is true
- D. Only 2 is true
正解:B
質問 # 163
Identify the missing words in the following sentence, The six aspects of project performance to be managed are [?] costs, timescales and scope,
- A. benefits, customers, quality,
- B. change, quality, progress,
- C. benefits, quality, risk,
- D. benefits, progress, risk,
正解:C
質問 # 164
Which PRINCE2 principle ensures that members of the project management team know what they are expected to contribute?
- A. Tailor to suit the project environment
- B. Defined roles and responsibilities
- C. Learn from experience
- D. Manage by exception
正解:B
解説:
Section: Volume B
Explanation/Reference:
Reference https://www.wrike.com/blog/project-management-basics-prince2-explained/