質問 # 226
How does the 'managing product delivery' process achieve its purpose?

  • A. By requiring the project manager to produce and monitor team plans
  • B. By agreeing requirements for how project work should be undertaken
  • C. By producing highlight reports to enable the project board to oversee the work
  • D. By escalating issues and risks that cannot be resolved within stage tolerance

正解:B


質問 # 227
In what process is the authorization to deliver the project's products given?

  • A. Directing a Project
  • B. Managing a Stage Boundary
  • C. Starting up a Project
  • D. Initiating a Project

正解:A


質問 # 228
Which is a PRINCE2 time-driven control?

  • A. End Stage Report
  • B. Checkpoint Report
  • C. Project Initiation Documentation
  • D. Project Brief

正解:B


質問 # 229
Why does the project board review the PID during an end stage assessment?

  • A. To notify the commissioning organization that the project has been authorized
  • B. To confirm that project controls are adequate for the remainder of the project
  • C. To ensure that post-project reviews of operational performance are planned
  • D. To review summarized progress to date and decide what to do next with the project

正解:D

解説:
The project board reviews the Project Initiation Documentation (PID) during an end stage assessment primarily to review summarized progress to date and to decide the future course of action for the project. This review helps determine whether the project is still viable and if the project should continue into its next stage based on performance against the plan and the business case.References: PRINCE2 Foundation Manual


質問 # 230
Which are benefits of using PRINCE2?
1. It removes the need for activity-based planning
2. It promotes learning and continuous improvement
3. It can be applied to any type of project
4. It defines specific leadership and other interpersonal skills required

  • A. 1 and 2
  • B. 3 and 4
  • C. 1 and 4
  • D. 2 and 3

正解:D

解説:
Explanation/Reference:
Reference https://www.axelos.com/best-practice-solutions/prince2/key-benefits-of-prince2


質問 # 231
Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?

  • A. To identify uncertainties that may impact on the delivery of the project objectives
  • B. To identify responses to risks documented in the business case
  • C. To identify the roles to be involved in risk management activities
  • D. To identify information about the project environment and objectives

正解:A

解説:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Risk#The_Risk_Management_Procedure


質問 # 232
Which is part of quality control?

  • A. Define the quality responsibilities of those involved in the production of the products
  • B. Produce quality records to show that the planned quality activities have been carried out
  • C. Document the project's acceptance criteria in the Project Product Description
  • D. Maintain the corporate organization's quality management system

正解:B


質問 # 233
Which theme provides all management levels within the project management team with mechanisms for monitoring and control?

  • A. Quality
  • B. Organization
  • C. Change
  • D. Progress

正解:D

解説:
Section: Volume B
Explanation/Reference: https://www.whatisprince2.net/prince2-theme-progress.php


質問 # 234
Which is a minimum requirement for applying the risk theme?

  • A. Threats must be assessed for their impact on the viability of the project
  • B. Team managers must maintain their own risk registers
  • C. The PRINCE2 risk management procedure must be followed
  • D. A single role that is responsible for all risks must be defined

正解:C

解説:
A minimum requirement for applying the Risk Theme in PRINCE2 is to follow the PRINCE2 risk management procedure. This procedure includes the systematic process of identifying, assessing, and controlling project risks, ensuring that risks are managed proactively throughout the project. References:
PRINCE2 7 Foundation Handbook and official training materials.


質問 # 235
What process aims to ensure accurate progress information is provided to the Project
Manager?

  • A. Managing Product Delivery
  • B. Directing a Project
  • C. Managing a Stage Boundary
  • D. Starting up a Project

正解:A


質問 # 236
Which is a purpose of the Managing a Stage Boundary process?

  • A. Provide the Project Board with sufficient information for approving the next stage
  • B. Review and close any risks and issues identified during the previous stage
  • C. Control the link between the Project Manager and the Team Manager(s)
  • D. Approve the next Stage Plan

正解:A

解説:
Section: Volume B


質問 # 237
Which are reasons for a benefits management approach?
1. To state how improvements will be measured
2. To confirm that the benefits are realized
3. To estimate the costs of improvement
4. To define the reason for delivering the improvement

  • A. 3 and 4
  • B. 1 and 4
  • C. 1 and 2
  • D. 2 and 3

正解:C、D


質問 # 238
What product is used to maintain a record of those who have an interest in the project and their information requirements?

  • A. Project Product Description
  • B. Project Plan
  • C. Communication Management Strategy
  • D. Project Brief

正解:C


質問 # 239
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

  • A. Directing a Project
  • B. Managing a Stage Boundary
  • C. Controlling a Stage
  • D. Starting up a Project

正解:C


質問 # 240
Which is an objective of the 'starting up a project' process?

  • A. To approve the initiation stage
  • B. To select the project mandate
  • C. To appoint the project management team
  • D. To define the project quality management approach

正解:A

解説:
Reference http://prince2.wiki/Starting_Up_a_Project#Purpose


質問 # 241
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?

  • A. When a change is raised
  • B. At the start of the project
  • C. Throughout each stage
  • D. In exception situations

正解:C

解説:
Section: Volume B
Explanation/Reference: https://www.prince2.com/blog/the-7-principles-themes-and-processes-of-prince2/


質問 # 242
What is a temporary organization that is treated for the purpose of delivering Business Products according an-agrees business casa?

  • A. The project scope
  • B. A project
  • C. The business
  • D. A baselined product

正解:B

解説:
A project is defined as a temporary organization that is created for the purpose of delivering business products according to an agreed business case. This definition emphasizes the temporary and purpose-driven nature of a project, which is organized to achieve specific business objectives and then disbanded upon achieving its goals. References: PRINCE2 7 Foundation manual and basic project management concepts.


質問 # 243
......


Prince2-Foundation認定試験は、Prince2の方法論に関する個人の知識と理解をテストするように設計されています。この試験では、プロジェクト計画、リスク管理、変更制御、プロジェクトの監視と制御、プロジェクトの閉鎖など、プロジェクト管理に関連するさまざまなトピックをカバーしています。認定試験を受けることを求めている個人は、プロジェクト管理の原則と概念を基本的に理解する必要があります。


Prince2 Foundation試験に合格するには、候補者はPrince2の原則を実際のシナリオに適用する能力を実証する必要があります。この試験では、プロジェクト管理用語、Prince2フレームワーク、Prince2の7つの原則、Prince2の7つのテーマ、Prince2の7つのプロセス、さまざまなプロジェクト環境に合わせてPrince2の調整など、幅広いトピックをカバーしています。 Prince2 Foundation試験は、プロジェクト管理のキャリアを追求したり、プロジェクト管理スキルを向上させたりしたい個人にとって優れた出発点です。

 

あなたを合格させるEXIN試験にはPR2F試験問題集:https://www.goshiken.com/EXIN/PR2F-mondaishu.html

検証済みPR2F豪華お試しセットリアル試験問題集PDF:https://drive.google.com/open?id=1ENwnePB1H3JvRYkTBfpOBq8Lzff8iNIT