質問 # 221
What must be done for a project to be a PRINCE2 project?
- A. The project must use the recommended approach to planning
- B. The project must meet the minimum requirements for applying the themes
- C. The project roles must be combined wherever possible
- D. The project must form part of a programme or portfolio
正解:B
解説:
For a project to be considered a PRINCE2 project, it must meet the minimum requirements for applying the seven PRINCE2 themes. These themes (Business Case, Organization, Quality, Plans, Risk, Change, and Progress) provide a framework for managing the project and ensuring that it is conducted in a systematic, consistent manner that is aligned with PRINCE2 principles.References: = PRINCE2 7 Foundation handbook and online resources
質問 # 222
In what product should the quality criteria for a specialist product be recorded?
- A. Quality Management Strategy
- B. Quality Register
- C. Project Product Description
- D. Product Description
正解:D
質問 # 223
Identify the missing words in the following sentence. The purpose of the Starting up a
Project process is as much about [?] as it is about requesting authorization to initiate viable projects,
- A. obtaining approval from all stakeholders
- B. producing an achievable Project Plan
- C. preventing poorly-conceived projects from ever being initiated
- D. setting up the required project controls
正解:C
質問 # 224
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?
- A. Risk
- B. Benefits
- C. Quality
- D. Scope
正解:C
質問 # 225
Which statements about quality assurance and project assurance are CORRECT?
1. They are both independent of the project manager
2. They are both the responsibility of the project board
3. They are both independent from the project management team
4. They both assure that applicable standards are being used
- A. 1 and 2
- B. 3 and 4
- C. 2 and 3
- D. 1 and 4
正解:B
質問 # 226
Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?
- A. To identify information about the project environment and objectives
- B. To identify uncertainties that may impact on the delivery of the project objectives
- C. To identify the roles to be involved in risk management activities
- D. To identify responses to risks documented in the business case
正解:B
解説:
Explanation/Reference:
Reference http://prince2.wiki/Risk#The_Risk_Management_Procedure
質問 # 227
According to the 'continued business justification' principle, what must project benefits be aligned to?
- A. The direction of the project board
- B. Regular deliveries throughout the project
- C. The technology available
- D. The business objectives
正解:D
解説:
Section: Volume B
Explanation/Reference:
Reference https://www.whatisprince2.net/prince2-principle-continued-business-justification.php
質問 # 228
Which is shown in a product breakdown structure?
- A. Management stages, major products and control points
- B. In which order the products should be created
- C. The major products that are to be developed in a plan
- D. What resources are required to develop the products
正解:C
質問 # 229
Identify the missing word(s) in the following sentence.
Following initiation, the Controlling a Stage process is used to manage and control each [ ?
] of a project.
- A. Team Plan
- B. management stage
- C. benefit
- D. technical stage
正解:B
質問 # 230
Which is a purpose of a project brief?
- A. To provide a sound basis for project initiation
- B. To provide a description of the means and frequency of communication
- C. To define how the achievement of the project's benefits can be measured
- D. To act as a base document which enables the project board to assess progress
正解:A
解説:
Section: Volume B
Explanation/Reference:http://www.prince2how2.com/2014/12/prince2-project-brief-template.html
質問 # 231
Which are benefits of using PRINCE2?
1. It removes the need for activity-based planning
2. It promotes learning and continuous improvement
3. It can be applied to any type of project
4. It defines specific leadership and other interpersonal skills required
- A. 1 and 2
- B. 1 and 4
- C. 3 and 4
- D. 2 and 3
正解:D
解説:
Reference https://www.axelos.com/best-practice-solutions/prince2/key-benefits-of-prince2
質問 # 232
Which is definition of culture?
- A. The process when people from across the project ecosystem work together
- B. The set of shared attitudes, values, goals, and ways of working that characterize a group of people
- C. The tailoring required to take into account the complexity or simplicity of a project
- D. An essential aspect of project management that needs to be continually addressed
正解:B
解説:
The definition of 'culture' in the context of PRINCE2 and project management is the set of shared attitudes, values, goals, and ways of working that characterize a group of people. Culture impacts how project teams operate and interact, influencing decision-making, teamwork, and the overall success of a project.
References: PRINCE2 training materials and project management culture insights.
質問 # 233
Which is a purpose of the Risk theme?
- A. Establish a method for the implementation of continuous improvement during the project
- B. Identify, assess and control problems that have occurred
- C. Establish a cost-effective procedure to identify, assess and control risks
- D. Provide the Project Board with a time-driven control to capture all project risks
正解:C
解説:
Section: Volume B
質問 # 234
What is performed as part of the recommended risk management procedure?
- A. Conflicts between the project and the programme board are resolved
- B. Information about risks to the projects is sent to project stakeholders
- C. Risk management practices are reviewed to ensure that they are performed effectively
- D. A budget to investigate issues is allocated
正解:D
解説:
Explanation/Reference:
Reference https://www.greycampus.com/opencampus/prince-2-foundation/prince2-risk-management- procedure
質問 # 235
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
- A. Configuration Item Record
- B. Highlight Report
- C. Quality Register
- D. Checkpoint Report
正解:D
質問 # 236
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?
- A. Provide the resources and skills to deliver the desired result
- B. Pay for the project
- C. Specify the desired result
- D. Specify the benefits of the project
正解:A
質問 # 237
Which is a purpose of the quality theme?
- A. To establish how the project will ensure that all products created meet their requirements
- B. To establish baselines against which any changes to products can be assessed
- C. To identify all the products of the project to ensure the scope has been adequately defined
- D. To determine the communication needs of the organization's quality assurance function
正解:A
質問 # 238
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
- A. Managing a Stage Boundary
- B. Directing a Project
- C. Starting up a Project
- D. Controlling a Stage
正解:D
質問 # 239
Which is a recommended quality review team role?
- A. Project Manager
- B. Chair
- C. Assurance
- D. Producer
正解:B
質問 # 240
Which statement describes the context of the 'initiating a project" process?
- A. The 'controlling a stage' process will start immediately after this process
- B. This process is triggered by the assembly of the project brief
- C. This process should result in key stakeholders being committed to the project
- D. The project is viewed from the perspective of the project board in this process
正解:C
質問 # 241
Which role is responsible for the quality of the specialist products delivered in the project?
- A. Senior supplier
- B. Executive
- C. Project assurance
- D. Senior user
正解:A
解説:
Section: Volume B
Explanation/Reference:
Reference http://www.fmdconsultants.co.uk/p2_roles_and_responsibilities_v01.docx
質問 # 242
......
PRINCE2 Foundationの筆記試験は、プロジェクト管理におけるキャリアアップを目指す個人にとって不可欠な認定資格です。この試験では、プロジェクト管理に広く認識され、採用されているフレームワークであるPRINCE2方法論に関する知識がテストされます。この認定は高く評価されており、プロジェクト管理に初めて取り組む個人だけでなく、スキルや知識を向上させたい経験豊富なプロジェクトマネージャーにも適しています。