質問 # 241
Which statement about the length of management stages in a project is CORRECT?

  • A. Stage length is influenced by project board availability
  • B. A higher level of major risk will require a stage to be longer
  • C. Use of management stages represents a time driven control
  • D. A higher level of major risk will require a stage to be shorter

正解:A

解説:
The length of management stages in a PRINCE2 project can be influenced by the availability of the project board to review and approve key decisions at stage boundaries. This ensures that stages are planned around when decision-makers can participate and provide necessary guidance or approvals.References: = PRINCE2 7 Foundation handbook and online resources


質問 # 242
Which process is triggered towards the end of the final stage when all the assigned work has been completed?

  • A. Managing a Stage Boundary
  • B. Managing Product Delivery
  • C. Closing a Project
  • D. Controlling a Stage

正解:C


質問 # 243
Which level of management sets the project level tolerances?

  • A. Project board
  • B. Corporate, programme management or the customer
  • C. Team manager
  • D. Project manager

正解:B

解説:
The level of management that sets the project level tolerances in PRINCE2 is corporate, programme management, or the customer. These project-level tolerances are defined to set the allowable limits of variation for the project's objectives, which the Project Manager must work within. This helps ensure that the project remains aligned with strategic goals and customer or corporate standards.References: PRINCE2 7 Foundation resources and materials.


質問 # 244
Which of the following statements about lines of authority and reporting are true?
1, The Project Manager has day-to-day control for a management stage within the limits laid,
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.

  • A. Only 2 is true
  • B. Both 1 and 2 are true
  • C. Only 1 is true
  • D. Neither 1 or 2 are true

正解:B


質問 # 245
Which describes a risk event?

  • A. The derivation or sources of a potential risk to the project
  • B. The area of uncertainty in terms of the threat or opportunity
  • C. The achievement of a milestone on the Project Plan
  • D. The sequence of events and actions that will be put in place if a risk occurs

正解:B


質問 # 246
Which describes the 'Identify Risks' step within the recommended risk management procedure?

  • A. Identify the roles to be involved in risk management activities
  • B. Gather information about the project environment and objectives
  • C. Identify uncertainties that may impact on the delivery of the project objectives
  • D. Identify responses to risks documented in the Business Case

正解:C


質問 # 247
Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?

  • A. Manage by exception
  • B. Manage by stages
  • C. Continued business justification
  • D. Learn from experience

正解:B

解説:
Explanation
Reference https://www.whatisprince2.net/prince2-theme-plans.php


質問 # 248
What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?

  • A. No specific documents related to benefits are necessary
  • B. The senior user's responsibilities for realizing benefits
  • C. The management actions needed to ensure benefits are realized
  • D. Statements of actual versus forecast benefits at reviews

正解:B

解説:
Section: Volume B


質問 # 249
What is performed as part of the recommended risk management procedure?

  • A. Conflicts between the project and the programme board are resolved
  • B. Risk management practices are reviewed to ensure that they are performed effectively
  • C. A budget to investigate issues is allocated
  • D. Information about risks to the projects is sent to project stakeholders

正解:C

解説:
Section: Volume B
Explanation/Reference:
Reference https://www.greycampus.com/opencampus/prince-2-foundation/prince2-risk-management- procedure


質問 # 250
Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.

  • A. define a coding system to provide a unique identifier for the products within
  • B. provide a framework to design, develop and maintain
  • C. define the project benefits to be achieved by each of
  • D. summarize the results of the quality activities performed on

正解:B


質問 # 251
According to the 'tailor to suit the project' principle, what is the basis for effective project management?

  • A. That the project method relates to the project's environment
  • B. That the appropriate information is provided to make decisions
  • C. That the project is divided into an appropriate number of stages
  • D. That the appropriate number and type of meetings are held

正解:A

解説:
Reference http://prince2.wiki/Tailor_to_suit_the_project_environment


質問 # 252
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

  • A. Only corporate or programme management
  • B. All levels of management
  • C. Only the Project Board
  • D. Only the Project Manager

正解:B

解説:
The mechanisms established by the Progress theme in PRINCE2 are used by all levels of management to control any unacceptable deviations. This includes the Project Board, Project Manager, and higher management levels, ensuring that everyone involved in the project management team can effectively monitor and control the project's progress and address issues as they arise. References: PRINCE2 Foundation manual, PRINCE2 official resources


質問 # 253
What is a goal of the 'implement' step within the recommended risk management procedure?

  • A. To estimate the risk to the project in terms of probability and impact
  • B. To communicate information related to the risks faced by the project
  • C. To prepare specific management responses to identified risks
  • D. To monitor the effectiveness of actioned risk responses

正解:A


質問 # 254
Which is a purpose of the quality theme?

  • A. To ensure that the project outputs are agreed
  • B. To enable the project to be managed according to plan
  • C. To check that the project is viable and achievable
  • D. To ensure that formal issues are recorded

正解:C

解説:
Section: Volume B
Explanation/Reference:


質問 # 255
Identify the missing words in the following sentence.
The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

  • A. the project board has agreed the project strategies
  • B. the 'starting up a project' process is completed
  • C. corporate, programme management or the customer have authorized a project
  • D. the project mandate has been approved by the project board

正解:B

解説:
Section: Volume B
Explanation/Reference:
Reference https://www.siliconbeachtraining.co.uk/blog/prince2-directing-project-process-dp


質問 # 256
Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

  • A. Controlling a stage
  • B. Managing a stage boundary
  • C. Starting up a project
  • D. Directing a project

正解:A

解説:
Section: Volume B
Explanation/Reference:
Reference https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-controlling-a-stage- process-in-prince2


質問 # 257
Which is an objective of the 'controlling a stage' process?

  • A. To produce a learn plan for the work package
  • B. To replan the current stage when directed
  • C. To develop products to defined quality criteria
  • D. To review the business justification for the project

正解:B

解説:
An objective of the 'Controlling a Stage' process in PRINCE2 is to replan the current stage when directed.
This process handles day-to-day management of the project, and includes responding to issues that might impact the stage plan, requiring replanning to ensure project objectives can still be met.References:
PRINCE2 Foundation Manual


質問 # 258
Identify the missing word(s) in the following sentence.
The 'controlling a stage' process is used to manage and control each [ ? ] of a project.

  • A. team plan
  • B. delivery step
  • C. benefit
  • D. delivery stage

正解:D

解説:
The 'Controlling a Stage' process in PRINCE2 is used to manage and control each 'delivery stage' of a project. This process focuses on the day-to-day management of the project stages, ensuring that the project remains within its agreed tolerances and effectively addressing issues as they arise.References: PRINCE2 Foundation Manual


質問 # 259
Which describes an off-specification?

  • A. The production of more than the defined quantity of a specialist product
  • B. A prototype demonstrating a possible design solution
  • C. An interdependency between products that was previously unidentified
  • D. That the right people are involved in appropriate roles
  • E. The addition of an improvement to a product description

正解:C

解説:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-change-control/


質問 # 260
Which is a type of issue?

  • A. An off-specification
  • B. A project outcome
  • C. A scope tolerance
  • D. An expected dis-benefit

正解:A


質問 # 261
Which may be funded from a risk budget?

  • A. Producing risk summaries for inclusion in Highlight Reports
  • B. Specific management responses to a project's threats and opportunities
  • C. Any remaining open risks after the project has been closed
  • D. Capturing identified threats and opportunities in the Risk Register

正解:B


質問 # 262
Which is an objective of the Starting up a Project process?

  • A. Authorize the Project Manager to proceed with the initiation stage
  • B. Agree how the project will be monitored and controlled after initiation
  • C. Agree how issues and changes will be identified, assessed and controlled
  • D. Identify who will be responsible for creating the Project Plan

正解:D


質問 # 263
Which is a benefit of applying the 'tailor to suit the project' principle?

  • A. The number of outputs is reduced
  • B. The project environment complexity is reduced
  • C. The capability of leadership is strengthened
  • D. Project management becomes less bureaucratic

正解:D

解説:
Applying the 'tailor to suit the project' principle in PRINCE2 helps make project management less bureaucratic by allowing for adaptations based on the project's size, complexity, environment, and stakeholders' needs. This flexibility reduces unnecessary overhead and ensures that the project management approach is both effective and efficient, enhancing overall project delivery without being overly constrained by rigid processes.References: PRINCE2 Foundation Manual


質問 # 264
Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.

  • A. an issue should be created for
  • B. a solution should be designed for
  • C. the chair will approve the solution to
  • D. the agreed actions should be recorded for

正解:D

解説:
Section: Volume B


質問 # 265
Identify the missing word in the following sentence, A purpose of the [?] theme is to control any unacceptable deviations from the project's objectives.

  • A. Change
  • B. Plans
  • C. Progress
  • D. Risk

正解:C


質問 # 266
......