Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
- A. Those who will specify the desired outputs of the project
- B. Those with a financial interest in the project
- C. Those who will manage the project on a day-to-day basis
- D. Those who will create the project's outputs
正解: C
解説:
Section: Volume A
Explanation/Reference:
質問 120
Which is a purpose of quality planning?
- A. Produce the Project Plan with resource and schedule information
- B. Detail the acceptance criteria, in order for the Project Board to agree the level of quality expected of the project's product
- C. Document approval records for those project products that have met their quality criteria
- D. Define the structure of the project management team
正解: B
質問 121
Which is a minimum requirement for applying the risk theme?
- A. A single role that is responsible for all risks must be defined
- B. The PRINCE2 risk management procedure must be followed
- C. Threats must be assessed for their impact on the viability of the project
- D. Team managers must maintain their own risk registers
正解: C
解説:
Reference https://www.prince2primer.com/prince2-2017-risk-theme-changes/
質問 122
Which is a recommended quality review team role?
- A. Administrator
- B. Project Support
- C. Project Manager
- D. Assurance
正解: A
質問 123
Which is an objective of the 'managing a product delivery' process?
- A. To request authorization to start the next stage
- B. To ensure the business case is regularly reviewed
- C. To assess whether the stage products have been approved
- D. To deliver the planned specialist products within tolerance
正解: D
解説:
Reference http://prince2.wiki/Managing_Product_Delivery#Objective
質問 124
Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?
- A. Writing the product description
- B. Writing a project product description
- C. Creating a product flow diagram
- D. Documenting the plan
正解: C
質問 125
Which product defines how the project board should approve the management products produced during the
'initiating a project' process?
- A. Project plan
- B. Initiation stage plan
- C. Communication management approach
- D. Quality management approach
正解: A
解説:
Section: Volume B
質問 126
Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.
- A. Stage Plan
- B. Follow-on action recommendations
- C. Communication Management Strategy
- D. Quality Management Strategy
正解: C
質問 127
Which should be funded by a change budget?
- A. Initiation stage
- B. Handover activities
- C. Change Authority
- D. Increase in agreed scope
正解: D
質問 128
Which statement defines a risk?
- A. An event that has already occurred that the Project Manager must deal with immediately
- B. An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response
- C. A certain event occurring in the future that will have a negative impact on the project's objectives
- D. An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives
正解: D
質問 129
Who is the key project decision-maker in the project management team?
- A. Corporate management
- B. Change Authority
- C. Project Manager
- D. Executive
正解: D
質問 130
What should the 'managing product delivery' process ensure?
1. That the planned products meet their quality criteria
2. That the stage plan is kept up to date
3. That the project board is provided with progress information
4. That the planned products are delivered within tolerance
- A. 2 and 3
- B. 1 and 2
- C. 1 and 4
- D. 3 and 4
正解: D
解説:
Explanation
Reference http://prince2.wiki/Managing_Product_Delivery
質問 131
Which is a purpose of the 'managing a stage boundary' process?
- A. To exercise overall control over the project while delegating day-to-day management
- B. To assign work to be controlled by the team manager
- C. To enable the project board to approve the continuation of the project
- D. To define the work that needs to be done to deliver the project product
正解: C
解説:
Reference http://prince2.wiki/Managing_a_Stage_Boundary#Objective
質問 132
Which is a purpose of the Directing a Project process?
- A. Delegate day-to-day management of the project to the Project Manager
- B. Ensure that work on products allocated to the team is authorized and agreed
- C. Create and authorize the project mandate
- D. Control the day-to-day running of the project
正解: A
質問 133
According to PRINCE2, which characteristic is necessary for an effective project board?
- A. A 'problem-solving' approach
- B. A calm management style
- C. An ability to delegate
- D. An attention to detail
正解: C
解説:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/project-board/
質問 134
Which is a task of product-based planning?
- A. Write the Project Product Description
- B. Identify activities and dependencies
- C. Prepare the Work Packages
- D. Produce Product Status Accounts
正解: A
質問 135
Which is NOT included in the PRINCE2 definition of a project?
- A. A project is a temporary organization
- B. A project's purpose is to deliver one or more business products
- C. A project is part of 'business as usual'
- D. A project is based on an agreed Business Case
正解: C
質問 136
During the Managing a Stage Boundary process, what is reviewed and updated to provide the information needed by the Project Board for assessing the continuing viability of the project?
- A. Product Status Account
- B. Project Plan
- C. Business Case
- D. Benefits Review Plan
正解: C
質問 137
Which is a task of product-based planning?
- A. Analyze the risks
- B. Create the product flow diagram
- C. Design the plan
- D. Prepare the schedule
正解: B
質問 138
Why is a Project Brief produced?
- A. To provide a full and firm foundation for the initiation of a project
- B. To act as a trigger for the Starting up a Project process
- C. To be used by the Project Board as a basis for reviewing the progress of a project
- D. To record the strategies and management controls to be used by a project
正解: A
質問 139
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?
- A. Raise an off-specification
- B. Write an Exception Report
- C. Raise a request for change
- D. Amend the Work Package
正解: A
質問 140
Which is a purpose of an End Project Report?
- A. Ensure that key project information is archived and made secure
- B. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
- C. Review how well the project performed against the Project Initiation Documentation used to authorize it
- D. Identify individuals or groups that need to be told that the project is coming to an end