質問 # 30
Which is a purpose of the Directing a Project process?

  • A. Create and authorize the project mandate
  • B. Ensure that work on products allocated to the team is authorized and agreed
  • C. Control the day-to-day running of the project
  • D. Delegate day-to-day management of the project to the Project Manager

正解:D


質問 # 31
How does the 'managing product delivery' process ensure that the team manager's perspective is provided in a work package?

  • A. The stage plan covering the work packages is created with input from the team manager
  • B. The work packages are defined by the team manager and supported by a team plan
  • C. the work packages provided by the project manager are agreed by the team manager
  • D. The team plans are checked by project assurance against the work packages

正解:C

解説:
In the 'Managing Product Delivery' process of PRINCE2, the team manager's perspective is considered by ensuring that work packages provided by the Project Manager are agreed upon by the Team Manager. This agreement includes understanding the requirements, scope, and criteria of the work packages, thus ensuring that the team manager is fully informed and agrees with what needs to be delivered.References: PRINCE2 Foundation Manual


質問 # 32
Which statement defines a risk?

  • A. An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response
  • B. An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives
  • C. A certain event occurring in the future that will have a negative impact on the project's objectives
  • D. An event that has already occurred that the Project Manager must deal with immediately

正解:B


質問 # 33
From whom does a Team Manager obtain approval for a completed product?

  • A. Project Manager
  • B. The authority defined in the Product Description
  • C. Senior Supplier
  • D. Project Support

正解:B


質問 # 34
Which describes a characteristic of a project?

  • A. It enables established and proven best practices
  • B. It involves a team with different skills
  • C. It provides a quality service to customers
  • D. It maintains business as usual profitability

正解:A

解説:
Reference https://www.projectsmart.co.uk/what-is-prince2.php


質問 # 35
In what product should the quality criteria for a specialist product be recorded?

  • A. Quality Management Strategy
  • B. Project Product Description
  • C. Product Description
  • D. Quality Register

正解:C


質問 # 36
Which enables the project's products and all interdependencies to be clearly identified and documented?

  • A. Quality Management Strategy
  • B. Product breakdown structure
  • C. Quality review technique
  • D. Product-based planning technique

正解:D


質問 # 37
Identify the missing word in the following sentence relating to one of the principles:
A PRINCE2 project should have [?] defined for each project objective.

  • A. themes
  • B. tolerances
  • C. processes
  • D. principles

正解:B


質問 # 38
Which of the following statements about stakeholders are true?
1. Someone who thinks they will be affected by a project is a stakeholder on that project.
2. Stakeholders may be internal or external to the corporate organization.

  • A. Only 1 is true
  • B. Both 1 and 2 are true
  • C. Neither 1 or 2 are true
  • D. Only 2 is true

正解:B


質問 # 39
In what process is the authorization to deliver the project's products given?

  • A. Managing a Stage Boundary
  • B. Directing a Project
  • C. Starting up a Project
  • D. Initiating a Project

正解:B


質問 # 40
What product is used to maintain a record of those who have an interest in the project and their information requirements?

  • A. Project Product Description
  • B. Project Brief
  • C. Project Plan
  • D. Communication Management Strategy

正解:D


質問 # 41
According to PRINCE2, which characteristic is necessary for an effective project board?

  • A. A calm management style
  • B. A 'problem-solving' approach
  • C. An attention to detail
  • D. An ability to delegate

正解:D

解説:
Explanation
Reference https://www.prince2primer.com/project-board/


質問 # 42
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

  • A. Issue Register
  • B. Risk Register
  • C. Follow-on action recommendations
  • D. Off-specifications

正解:C


質問 # 43
Which is an objective of the Starting up a Project process?

  • A. Agree how issues and changes will be identified, assessed and controlled
  • B. Identify who will be responsible for creating the Project Plan
  • C. Agree how the project will be monitored and controlled after initiation
  • D. Authorize the Project Manager to proceed with the initiation stage

正解:B


質問 # 44
Which statement about project roles is CORRECT?

  • A. The project board roles defined in PRINCE2 must be used, but other roles can be defined as required
  • B. The project organization must be defined using the roles and responsibilities in PRINCE2
  • C. The project team structure defined in PRINCE2 must be used, but other roles may be added
  • D. Any role can be defined as required the responsibilities defined in PRINCE2 are fulfilled

正解:A


質問 # 45
Which statement describes a purpose of the 'starting up a project' process?

  • A. To appoint people ta the major rales in the project management team
  • B. To provide Information so that the business can understand the cost of delivering the project
  • C. To provide management control Listen the project manager and the team managers
  • D. Ta agree how a team manager will report progress

正解:A

解説:
The purpose of the 'Starting up a Project' process is primarily to appoint people to the major roles within the project management team. This process ensures that the right people are in place with clear responsibilities before the project kicks off, facilitating effective planning and execution from the outset. References:
PRINCE2 7 Foundation manual and the 'Starting up a Project' process documentation.


質問 # 46
What is the result of the change derived from using the project's product?

  • A. Output
  • B. Dis-benefit
  • C. Benefit
  • D. Outcome

正解:D


質問 # 47
Which is a purpose of the 'initiating a project' process?

  • A. To identify the number of work packages required
  • B. To decide on the project approach
  • C. To establish solid foundations for a project
  • D. To decide if it is worthwhile to initiate a project

正解:C

解説:
Explanation
Reference http://prince2.wiki/Initiating_a_Project#Objective


質問 # 48
......


PRINCE2-Foundation試験は、プロジェクトマネジメントに新しく取り組む人やPRINCE2方法論についてより学びたい経験者向けのエントリーレベルの認定資格です。この試験では、PRINCE2の原則、テーマ、プロセス、プロジェクトチームメンバーの役割と責任などのトピックをカバーし、プロジェクト計画、リスク管理、品質管理についても取り上げます。


EXIN PR2F(PRINCE2 Foundation written)試験は、PRINCE2プロジェクト管理手法の基本的な知識と理解力を評価するために設計されています。PRINCE2は、PRojects IN Controlled Environmentsの略で、プロジェクト管理のための広く使用されているフレームワークであり、プロジェクトを予算内、期限内、および所望の品質で提供するための構造化されたアプローチを提供します。PRINCE2手法は、最も効果的なプロジェクト管理フレームワークの一つとして広く認められており、PR2F試験はプロジェクト管理の分野でキャリアを進めたい専門家にとって貴重な認証資格です。

 

PRINCE2 PRINCE2-Foundation問題集でカバー率リアル試験問題:https://www.goshiken.com/PRINCE2/PRINCE2-Foundation-mondaishu.html

問題集お試しセットPRINCE2-Foundationテストエンジン問題集トレーニングには465問あります:https://drive.google.com/open?id=1cCRIcfgGFAOtSPLTbhqbAjpoHjb3oxF_