質問 # 47
Identify the missing words in the following sentence.
PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.
- A. the project board
- B. the project manager
- C. the change authority
- D. corporate, programme management or the customer
正解:A
解説:
Section: Volume B
Explanation/Reference:
質問 # 48
Which role is responsible for ensuring the project is justified in terms of cost?
- A. Senior supplier
- B. Executive
- C. Senior user
- D. Project manager
正解:B
質問 # 49
Which is a minimum requirement for applying the change theme?
- A. To tailor all changes to improve the quality of the project
- B. To identify whether an issue affects the continuation of the project
- C. To produce a breakdown of the products to be produced
- D. To ensure each change is managed as an exception
正解:D
解説:
Section: Volume B
質問 # 50
Which is one of the six aspects of project performance to be managed?
- A. Estimate
- B. Efficiency
- C. Work
- D. Timescales
正解:D
解説:
Reference http://prince2.wiki/Introduction:_The_PRINCE2_Foundation_Training_Manual#Six_variables_.2F_six_performance_targets
質問 # 51
What product is used to maintain a record of those who have an interest in the project and their information requirements?
- A. Project Plan
- B. Project Brief
- C. Project Product Description
- D. Communication Management Strategy
正解:D
解説:
Section: Volume A
質問 # 52
Which statement about stages is true?
- A. The use of technical stages is mandatory
- B. Management stages are driven by specialist teams
- C. Management stages should be of the same duration
- D. The use of management stages is mandatory
正解:D
解説:
Section: Volume B
質問 # 53
Which is an objective of the quality review technique?
- A. To assess that a product conforms to set criteria
- B. To provide assurance that the project is being conducted properly
- C. To ensure that staff are properly trained in the quality methods
- D. To identify a product's quality criteria
正解:A
質問 # 54
Which is NOT obtained from a product's Product Description?
- A. The product's quality criteria
- B. The quality method to be used
- C. Who will approve the product
- D. The development method to be used
正解:D
質問 # 55
Why is it necessary to apply the 'defined roles and responsibilities' principle?
- A. Because the people involved in a project should know what is expected of them
- B. Because the project manager should represent all the stakeholders of the project
- C. Because the project management team should be cross-functional
- D. Because the user and supplier interests should be involved on a need-to-know basis
正解:A
解説:
The 'defined roles and responsibilities' principle in PRINCE2 is essential because it ensures clarity and efficiency in project management. By clearly defining roles and responsibilities, everyone involved in the project understands their tasks, responsibilities, and reporting relationships. This clarity helps in reducing confusion and improving communication and accountability among project team members.References:
PRINCE2 Foundation Manual
質問 # 56
Within which integrated element does PRINCE2 set minimum requirements?
- A. Principles
- B. Themes
- C. Processes
- D. Project environment
正解:B
解説:
PRINCE2 sets minimum requirements within its themes. Themes support the principles and are aspects of project management that must be addressed continually and in parallel throughout the project. The themes provide knowledge areas necessary for the effective management of a project. References: PRINCE2 Foundation Handbook, Themes section.
質問 # 57
Which is one of the three levels of plan in PRINCE2?
- A. Project Brief
- B. Benefits Review Plan
- C. Programme Plan
- D. Team Plan
正解:D
解説:
Section: Volume B
質問 # 58
Which project characteristic suggests that projects should have a defined start and a defined end?
- A. Temporary
- B. Cross-functional
- C. Change
- D. Risk
正解:A
質問 # 59
Which is a purpose of the Directing a Project process?
- A. Control the day-to-day running of the project
- B. Delegate day-to-day management of the project to the Project Manager
- C. Ensure that work on products allocated to the team is authorized and agreed
- D. Create and authorize the project mandate
正解:B
質問 # 60
What information should be recorded in the quality register?
- A. Planned activities to determine whether the products are fit for purpose
- B. Off-specifications that will occur during the project
- C. Lessons that the project will capture and use during the project
- D. Potential threats to the project's objectives and how they will be managed
正解:C
解説:
Section: Volume B
Explanation/Reference: https://mplaza.pm/prince2-quality-register-template/
質問 # 61
Which is a minimum requirement for applying the risk theme?
- A. Threats must be assessed for their impact on the viability of the project
- B. Team managers must maintain their own risk registers
- C. A single role that is responsible for all risks must be defined
- D. The PRINCE2 risk management procedure must be followed
正解:A
解説:
Section: Volume B
Explanation/Reference: https://www.prince2primer.com/prince2-2017-risk-theme-changes/
質問 # 62
Which term is defined as a product that will not meet is quality specifications?
- A. Problem
- B. Request for change
- C. Concern
- D. Off-specification
正解:D
解説:
The term 'off-specification' is defined as a product that will not meet its quality specifications. This indicates a variance from what was agreed upon in the product description, requiring attention and potentially corrective action to ensure the project's outputs meet the required standards. References: PRINCE2 Foundation glossary and project documentation guidelines.
質問 # 63
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?
- A. Throughout each stage
- B. In exception situations
- C. At the start of the project
- D. When a change is raised
正解:A
解説:
Section: Volume B
Explanation/Reference: https://www.prince2.com/blog/the-7-principles-themes-and-processes-of-prince2/
質問 # 64
Which is a FALSE statement about technical stages?
- A. Include the Managing a Stage Boundary process activities
- B. Can overlap with other technical stages
- C. Can span more than one management stage
- D. Typified by the use a particular set of specialist skills
正解:A
解説:
Section: Volume B
質問 # 65
When should the level of tailoring be defined?
- A. As a response to issues and risks experienced
- B. During the initiation stage
- C. When reviewing what has been learned to date
- D. Before the project is triggered by the project mandate
正解:B
解説:
The level of tailoring in PRINCE2 should be defined during the initiation stage of the project. This stage involves setting up the proper foundation for the project by adapting the method to suit the project's environment, including deciding how much and which parts of the methodology to apply. References:
PRINCE2 Foundation Handbook, Tailoring PRINCE2 section.
質問 # 66
What is a risk actionee responsible for?
- A. Managing, monitoring and controlling of all aspects of an assigned risk
- B. Identifying risks to the project that might occur in their department
- C. Carrying out a risk response action to respond to a particular risk
- D. Owning and authorizing the use of the risk budget to fund risk responses
正解:C
質問 # 67
What product should be used to confirm the version number of ail products in a particular stage?
- A. Configuration Item Record
- B. Issue Register
- C. Product Status Account
- D. Product Description
正解:C
質問 # 68
Which statement is CORRECT about the customer and suppliers of a project in a commercial environment?
- A. The risk appetite should be collaboratively set before the project starts
- B. Each party may have their own business case for undertaking the project
- C. Management systems need to be unified for successful project delivery
- D. Both parties must apply the same external governance to the project
正解:B
解説:
Section: Volume B
質問 # 69
Which is a purpose of a Product Description?
- A. Document the level of quality required of a product
- B. Record the quality checks completed for the End Stage Report
- C. Define reporting frequency
- D. Provide the cost tolerance available for individual products
正解:A
質問 # 70
Which PRINCE2 principle ensures that members of the project management team know what they are expected to contribute?
- A. Learn from experience
- B. Manage by exception
- C. Defined roles and responsibilities
- D. Tailor to suit the project environment
正解:C
解説:
Section: Volume B
Explanation/Reference:
Reference https://www.wrike.com/blog/project-management-basics-prince2-explained/
質問 # 71
During the 'initiating a project' process, who specifies the required level of management control?
- A. Corporate, programme management or customer
- B. Project assurance
- C. Project board
- D. Project manager
正解:C
解説:
During the 'Initiating a Project' process in PRINCE2, it is the responsibility of the project board to specify the required level of management control. This includes defining how the project will be managed, monitored, and controlled throughout its lifecycle. The project board ensures that the project remains viable and that management decisions are made with the appropriate level of oversight.References: = PRINCE2 7 Foundation handbook and online resources
質問 # 72
......
PRINCE2-Foundation試験は、プロジェクト管理の経験がほとんどない人々を対象に設計された入門レベルの認定です。この試験は、PRINCE2メソッドの基礎、原則、テーマ、プロセス、および管理製品についてカバーしており、プロジェクトチームの役割と責任、プロジェクト管理で使用される各種テクニックとツールについても説明しています。試験は複数選択形式で実施され、候補者のPRINCE2メソッドに対する理解をテストすることを目的としています。
PRINCE2-Foundation試験は、全世界で認められ、プロジェクト管理業界の雇用主に高く評価されています。この認定は、候補者がPRINCE2メソッドを熟知していること、そしてこの枠組みを使用してプロジェクトを管理することができる能力を持っていることを示しています。また、個人のキャリアの可能性を高め、プロジェクト管理の分野でキャリアを進めるための優れた方法でもあります。この認定は、より長いプロジェクト管理経験を持つ個人を対象とした上級レベルのPRINCE2プラクティショナー認定の前提条件でもあります。
PRINCE2-Foundation問題集PDFとテストエンジン試験問題:https://www.goshiken.com/PRINCE2/PRINCE2-Foundation-mondaishu.html
無料提供中で最新のPRINCE2-Foundation認定有効な試験問題集はこれ:https://drive.google.com/open?id=1cCRIcfgGFAOtSPLTbhqbAjpoHjb3oxF_