質問 # 173
Which role is responsible for appointing the senior user in a project that is independent from a program?

  • A. The project manager
  • B. Project assurance
  • C. The executive
  • D. Corporate, program management or the customer

正解:D

解説:
Explanation
Reference https://www.prince2primer.com/prince2-roles-and-responsibilities/


質問 # 174
Whose approval is needed to replace a Stage Plan with an Exception Plan?

  • A. Project Manager
  • B. Team Manager
  • C. Project Board
  • D. Corporate or programme management

正解:C


質問 # 175
Which risk response type is appropriate to respond to an opportunity?

  • A. Accept
  • B. Fallback
  • C. Exploit
  • D. Transfer

正解:C


質問 # 176
Why is a Project Brief produced?

  • A. To be used by the Project Board as a basis for reviewing the progress of a project
  • B. To act as a trigger for the Starting up a Project process
  • C. To record the strategies and management controls to be used by a project
  • D. To provide a full and firm foundation for the initiation of a project

正解:D

解説:
Section: Volume B
Explanation/Reference:


質問 # 177
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

  • A. Quality
  • B. Benefits
  • C. Scope
  • D. Risk

正解:A

解説:
Quality is the aspect of project performance that must be managed to ensure the project's products are fit for purpose. PRINCE2 emphasizes that quality management is essential to ensure that the project outputs meet the necessary requirements and standards to achieve the desired outcomes. References: PRINCE2 Foundation official documentation and study materials.
These responses are based on the latest materials and guidelines from the PRINCE2 Foundation, ensuring accurate and up-to-date answers as per your request.


質問 # 178
What problem may occur if projects are not aligned with corporate business strategy?

  • A. The objectives of different projects may overlap
  • B. The project management approaches used may differ
  • C. The outputs may be of poor quality
  • D. The control of projects may be poor

正解:B


質問 # 179
Which describes a risk effect?

  • A. The issue which is affecting the project and has resulted in a risk
  • B. The impact(s) on the project objectives should the threat or opportunity occur
  • C. The uncertainty expressed as a negative or favourable occurrence
  • D. The change in the statusof a risk in response to actions taken to control it

正解:B


質問 # 180
What information should be recorded in the quality register?

  • A. Potential threats to the project's objectives and how they will be managed
  • B. Lessons that the project will capture and use during the project
  • C. Off-specifications that will occur during the project
  • D. Planned activities to determine whether the products are fit for purpose

正解:D

解説:
The quality register in PRINCE2 is used to record all planned quality activities, such as quality checks and audits, which determine whether the project's products are fit for purpose. It serves as a log of the quality activities conducted and their outcomes, ensuring quality control throughout the project. References:
PRINCE2 Foundation Handbook, Quality Register section.


質問 # 181
Which common project context relates to the need to engage with external suppliers to deliver part of the project?

  • A. Scale
  • B. Delivery method
  • C. Organizational
  • D. Commercial

正解:D

解説:
The need to engage with external suppliers for delivering parts of the project is commonly related to the
'Commercial' project context in PRINCE2. This context involves considerations around contractual arrangements, procurement, and the management of supplier relationships which are crucial for projects relying on external vendors for key components or services.References: (PRINCE2 7 Foundation Handbook, AXELOS)


質問 # 182
Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?

  • A. Continued business justification
  • B. Defined roles and responsibilities
  • C. Manage by stages
  • D. Manage by exception

正解:D

解説:
Explanation
Reference http://prince2.wiki/Manage_by_exception


質問 # 183
Which is NOT considered when defining risk tolerance?

  • A. A Project Board's attitude towards risk taking
  • B. The amount of risk a Project Board considers acceptable
  • C. The allocated risk budget
  • D. An organization's risk appetite

正解:C


質問 # 184
Which is one of the three levels of plan in PRINCE2?

  • A. Team Plan
  • B. Benefits Review Plan
  • C. Programme Plan
  • D. Project Brief

正解:A


質問 # 185
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

  • A. Follow-on action recommendations
  • B. Risk Register
  • C. Issue Register
  • D. Off-specifications

正解:A


質問 # 186
Which document should record the agreed amount of risk budget for a project?

  • A. Project Plan
  • B. Risk Register
  • C. Project Brief
  • D. Risk Management Strategy

正解:D

解説:
The agreed amount of risk budget for a project is recorded in the Risk Management Strategy document. This document outlines how risks will be managed throughout the project, including the budget set aside specifically for implementing risk responses. It provides a structured approach to managing risks, including their identification, assessment, planning responses, and the funds allocated for these activities.References:
PRINCE2 7 Foundation handbook and documents.


質問 # 187
Which is an objective of the 'initiating a project' process?

  • A. To ensure that the planned products are delivered within tolerances
  • B. To ensure that the business case is kept under review
  • C. To ensure that user acceptance of the products is confirmed
  • D. To ensure that baselines are established and controlled

正解:A

解説:
Explanation
Reference http://prince2.wiki/Initiating_a_Project#Objective


質問 # 188
Which describes risk appetite?

  • A. The budget set aside for potential changes to the scope of the project
  • B. A common set of risk categories, risk scales and evaluation techniques
  • C. An organization's unique attitude towards risk-taking
  • D. The risks to the expected benefits

正解:C


質問 # 189
Who represents the three project interests on a project?

  • A. Project support
  • B. External project stakeholders
  • C. Project manager
  • D. Project board

正解:D

解説:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Organization#Three_Project_Interests


質問 # 190
Which of the following are objectives of the Directing a Project process?
1 . Ensure corporate or programme management has an interface to a project
2 . Ensure that work on products allocated to a team is authorized
3 . Ensure there is authority to initiate a project
4 . Ensure that a project remains viable

  • A. 1, 2, 3
  • B. 1, 3, 4
  • C. 2, 3, 4
  • D. 1, 2, 4

正解:B


質問 # 191
Which is an objective of the Closing a Project process?

  • A. Review the performance of the project against its baseline
  • B. Create a Benefits Review Plan
  • C. Perform any post-project reviews
  • D. Review and approve the plan for project closure

正解:A


質問 # 192
What information should be recorded in the quality register?

  • A. Potential threats to the project's objectives and how they will be managed
  • B. Off-specifications that will occur during the project
  • C. Planned activities to determine whether the products are fit for purpose
  • D. Lessons that the project will capture and use during the project

正解:D

解説:
Explanation
Reference https://mplaza.pm/prince2-quality-register-template/


質問 # 193
Which statement about the Directing a Project process is true?

  • A. Begins on completion of the Initiating a Project process
  • B. Covers the day-to-day activities of the Project Manager
  • C. Provides a mechanism for the Project Board to assure that there is continued business justification
  • D. Ensures there are regular progress meetings

正解:C


質問 # 194
Which is a purpose of the Plans theme?

  • A. Identify, assess and control any potential changes to the baseline
  • B. Assess and control uncertainty
  • C. Understand whether the targets are achievable
  • D. Establish the project's structure of accountability

正解:C


質問 # 195
Which PRINCE2 principle ensures that members of the project management team know what they are expected to contribute?

  • A. Learn from experience
  • B. Tailor to suit the project environment
  • C. Defined roles and responsibilities
  • D. Manage by exception

正解:C

解説:
Section: Volume B
Explanation/Reference:
Reference https://www.wrike.com/blog/project-management-basics-prince2-explained/


質問 # 196
Who are considered as the stakeholders in a project?

  • A. Everyone involved in or affected by the project
  • B. Only those benefitting the project
  • C. Only those who are users of the products
  • D. Everyone in the corporate organization

正解:A


質問 # 197
Which is a purpose of the change theme?

  • A. To establish mechanisms to monitor and compare actual achievements against those planned
  • B. To assess and control uncertainty
  • C. To prevent change to baselined products
  • D. To identify, assess and control any potential and approved changes to baselined products

正解:D

解説:
Section: Volume B
Explanation/Reference: https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-prince2-change- theme


質問 # 198
......


EXIN PR2F(PRINCE2 Foundation written)試験は、PRINCE2プロジェクト管理手法の基本的な知識と理解力を評価するために設計されています。PRINCE2は、PRojects IN Controlled Environmentsの略で、プロジェクト管理のための広く使用されているフレームワークであり、プロジェクトを予算内、期限内、および所望の品質で提供するための構造化されたアプローチを提供します。PRINCE2手法は、最も効果的なプロジェクト管理フレームワークの一つとして広く認められており、PR2F試験はプロジェクト管理の分野でキャリアを進めたい専門家にとって貴重な認証資格です。


PRINCE2 PRINCE2-Foundation(PRINCE2 Foundation written)認定試験は、PRINCE2プロジェクト管理手法の知識と理解を検証する、国際的に認められた資格です。PRINCE2(Projects IN Controlled Environments)は、プロジェクト管理のためのプロセスベースのアプローチで、構造化されたフレームワークを提供します。PRINCE2は、英国で広く使用され、他の国々でも人気が高まっています。


PRINCE2(PRojects IN Controlled Environments)フレームワークは、英国および他の国々でプロジェクトを効果的に管理するため広く使用されています。PR2F 資格試験は、プロジェクト管理プロセス、原則、テーマ、およびガバナンスなどの主要な領域における候補者の知識を評価します。また、この資格は、PRINCE2 フレームワークを特定のプロジェクト環境に適合させることの重要性も強調しています。PR2F 資格は、プロジェクト管理のベストプラクティスを理解し、キャリアアップを目指すプロフェッショナルにとって強固な基盤を提供します。

 

あなたを合格させるPRINCE2 PRINCE2-Foundation試験専門問題集はここにある:https://www.goshiken.com/PRINCE2/PRINCE2-Foundation-mondaishu.html

最新PRINCE2 Certification PRINCE2-Foundation練習テストに最速準備問題をゲットせよ:https://drive.google.com/open?id=1wItHIvaNjx8wh0j1w2vgUNxpcU_9mzNO