質問 # 23
How can trust be gained between the business and development?

  • A. Deliver predictability
  • B. Automate the delivery pipeline
  • C. Release new value to production every day
  • D. Maintain Iterations as a safe zone for the team

正解:A


質問 # 24
What is one way Lean-Agile leaders lead by example?

  • A. By using the SAFe Implementation Roadmap to script the way for change
  • B. By applying empathic design and focusing on Customer Centricity
  • C. By mastering the Seven Core Competencies of the Lean Enterprise
  • D. By modeling SAFe's Lean-Agile Mindset, values, principles, and practices

正解:D


質問 # 25
What is one key purpose of DevOps?

  • A. DevOps joins development and operations to enable continuous delivery
  • B. DevOps focuses on automating the delivery pipeline to reduce transaction cost
  • C. DevOps focuses on a set of practices applied to large systems
  • D. DevOps enables continuous release by building a scalable Continuous Delivery Pipeline

正解:A


質問 # 26
The primary need for SAFe is to scale the idea of what?

  • A. Organizational and Functional Alignment
  • B. Lean Portfolio Management
  • C. Business Agility
  • D. Technical Solution Delivery

正解:C


質問 # 27
Who is responsible for managing the Portfolio Kanban?

  • A. Release Train Engineer
  • B. Solution Management
  • C. Product Management
  • D. Lean Portfolio Management

正解:D


質問 # 28
An Enterprise has just adopted the SAFe Implementation Roadmap and is in the process of training executives,
managers, and leaders. What is their next step?

  • A. Train the leaders in Portfolio and Product Management to solve problems before fixing symptoms
  • B. Perform process mapping on the current state
  • C. Identify Value Streams and Agile Release Trains to start alignment of the organization
  • D. Train Lean-Agile change agents to push out the roadmap and build consensus

正解:C


質問 # 29
Which team type is 'organized to assist other teams with specialized capabilities and help them become more
proficient in new technologies'?

  • A. Enabling team
  • B. Stream-aligned team
  • C. Complicated subsystem team
  • D. Platform team

正解:A


質問 # 30
During the PI Planning event, when are planning adjustments agreed upon?

  • A. During the draft plan review
  • B. During the management review and problem-solving
  • C. During Scrum of scrums
  • D. During breakout sessions

正解:B


質問 # 31
Which statement is true when continuously deploying using a DevOps model?

  • A. It ensures that changes deployed to production are always immediately available to end-users
  • B. It lessens the severity and frequency of release failures
  • C. It increases the transaction cost
  • D. It alleviates the reliance on the skill sets of Agile Teams

正解:A


質問 # 32
Optimizing flow means identifying what?

  • A. Key performance indicators
  • B. Activities that lack innovation
  • C. Delays
  • D. Predictability issues of the train

正解:C


質問 # 33
SAFe's first Lean-Agile Principle includes "Deliver early and often" and what else?

  • A. Apply systems thinking
  • B. Apply cadence
  • C. Decentralize decision-making
  • D. Deliver value incrementally

正解:D


質問 # 34
How does SAFe describe Customer Centricity?

  • A. As a set of practices employed to make products focused on the Customer
  • B. As a way of working to include the Customer in daily work processes and planning
  • C. As a strategy to meet the needs of an ever-changing Customer market
  • D. As a mindset focused on Customer behaviors that produce the best innovations

正解:D


質問 # 35
Which two types of decisions should remain centralized even in a decentralized decision-making
environment? (Choose two.)

  • A. Decisions that are made frequently
  • B. Decisions that deliver large and broad economic benefits
  • C. Decisions unlikely to change in the short term
  • D. Decisions that require local information
  • E. Decisions that come with a high cost of delay

正解:B、C


質問 # 36
According to SAFe Principle #10, what should the Enterprise do when markets and customers demand
change?

  • A. Create a reliable decision-making framework to empower employees and ensure a fast flow of value
  • B. Apply development cadence and synchronization to operate effectively and manage uncertainty
  • C. Reorganize the network around the new value flow
  • D. Create an Agile Release Train to focus on value

正解:C


質問 # 37
The analyzing step of the Portfolio Kanban system has a new Epic with a completed Lean business case. What
best describes the next step for the Epic?

  • A. It will be moved to the Portfolio Backlog if it receives a 'go' decision from Lean Portfolio Management
  • B. It will remain in the analyzing step until one or more Agile Release Trains have the capacity to
    implement it
  • C. It will be implemented if it has the highest weighted shortest job first (WSJF) ranking
  • D. It will be implemented once the Lean business case is approved by the Epic Owner

正解:A


質問 # 38
What does the Continuous Delivery Pipeline enable?

  • A. Ongoing learning
  • B. Increased technical debt
  • C. Delivery of large batches
  • D. Continuous refactoring

正解:A


質問 # 39
Which statement is true about a Value Stream that successfully uses DevOps?

  • A. It has objective measurements with automation
  • B. It has a lower threshold of defects approved to production
  • C. It has a closed loop process of learning
  • D. It has a technology stack without legacy code

正解:C


質問 # 40
Which pillar in the House of Lean focuses on the Customer being the consumer of the work?

  • A. Value
  • B. Flow
  • C. Innovation
  • D. Respect for People and Culture

正解:D