[2022年02月15日]PRINCE2-Agile-Foundation試験問題集で100%合格率PRINCE2-Agile-Foundation試験! [Q17-Q36]

Share

[2022年02月15日]PRINCE2-Agile-Foundation試験問題集で100%合格率PRINCE2-Agile-Foundation試験!

試験問題集リアルPRINCE2 Agile問題集52解答を試そう!


PRINCE2 PRINCE2-Agile-Foundation 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • Understand key concepts relating to projects and PRINCE2 Agile
トピック 2
  • Understand the agile ways of working, key terms and techniques
トピック 3
  • Understand how PRINCE2 principles, themes, processes and management products are tailored and
  • or applied in an agile context
トピック 4
  • Understand the focus areas in an agile contex
  • Understand key concepts relating to PRINCE2

 

質問 17
Which PRINCE2 principle should be followed in order to engage the business, user and supplier stakeholder interests?

  • A. Learn from experience
  • B. Defined roles and responsibilities
  • C. Tailor to suit the project
  • D. Continued business justification

正解: B

 

質問 18
During which process should release planning be done for the FIRST time?

  • A. Initiating a project
  • B. Controlling a stage
  • C. Managing product delivery
  • D. Managing a stage boundary

正解: D

 

質問 19
Which statement about the 'embrace change' target is CORRECT?

  • A. It reduces testing in order to meet deadlines
  • B. It minimizes the time needed to train a new team member
  • C. It encourages the customer to raise new ideas
  • D. It reduces the planning of dependencies between projects

正解: C

 

質問 20
Which statement explains the setting of the cost tolerance for a project in an agile context?

  • A. Cost tolerance can be fixed and flexed
  • B. Cost tolerance can be fixed or flexed
  • C. Cost tolerance is fixed
  • D. Cost tolerance is flexed

正解: D

 

質問 21
Why are team working agreement produced?

  • A. To evolve the effectiveness and behaviors of the self-organizing team by agreeing values
  • B. To create structure so that the team manager can assess individual performance
  • C. To ensure that the delivery team members comply with company policy
  • D. To make the team rules visible to the project manager for monitoring purposes

正解: A

解説:
Reference https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126&showNav=true&expandNav=true

 

質問 22
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.

  • A. 2 and 3
  • B. 1 and 4
  • C. 1 and 2
  • D. 3 and 4

正解: B

 

質問 23
What is the definition of a timebox?

  • A. A tool to write a requirement in the form of who, what and why
  • B. A regular event that looks at how processes can be improved
  • C. A description of the rate of progress a team is making
  • D. A period where work is carried out to achieve a goal

正解: D

 

質問 24
Which statement about the 'accept that the customer doesn't need everything' target is correct?

  • A. It can result in the early delivery of a minimum viable product
  • B. It gives confidence on the progress of the project
  • C. It allows misunderstandings to be dealt with appropriately
  • D. It is achieved by managing the culture of the team carefully

正解: C

 

質問 25
Whose interests are specifically represented by the senior supplier?
1. Those ensuring the project is value for money.
2. Those who will use the project's products.
3. Those who will be developing the project's products.
4. Those responsible for the project's technical integrity.

  • A. 1 and 4
  • B. 2 and 3
  • C. 3 and 4
  • D. 1 and 2

正解: C

 

質問 26
To help with prioritization, what is MOST important when understanding the difference between scope and quality?

  • A. Combining functional and non-functional requirements
  • B. Differentiating functional from non-functional requirements
  • C. Creating non-functional requirements with user stories
  • D. Defining non-functional requirements before functional requirements

正解: B

 

質問 27
Which statement explains how the 'learn from experience' principle is applied in an agile context?

  • A. It integrates releases within management stages
  • B. It provides guidance on mapping PRINCE2 roles to an agile environment
  • C. It is supported by the 'inspect and adapt' concept
  • D. It focuses on the prioritization and decomposition of requirements

正解: C

 

質問 28
How should product-based planning be used as part of PRINCE2 Agile?

  • A. To plan by focusing on the features required
  • B. To enable team planning to be predictive
  • C. To create the project plan using empiricism
  • D. To track progress against the team plan

正解: A

 

質問 29
Which TWO are the purposes of a highlight report?
1. To describe the MoSCoW priority of user stories.
2. To summarize the status of a work package.
3. To summarize the stage status.
4. To report any potential issues and risks

  • A. 1 and 4
  • B. 2 and 3
  • C. 3 and 4
  • D. 1 and 2

正解: C

解説:
Reference:
%20by%20them.&text=The%20project%20manager%20also%20uses,the%20project%20board%20could%20help

 

質問 30
In Scrum, what answers the question 'what can be done this sprint?'

  • A. Increment
  • B. Sprint planning
  • C. Sprint review
  • D. Daily scrum

正解: D

 

質問 31
What information is NOT typically displayed on a burn chart?

  • A. Actual amount of work done
  • B. Definition of 'ready'
  • C. Effort remaining
  • D. Amount of time elapsed

正解: B

 

質問 32
When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?

  • A. Effective
  • B. Preferable
  • C. Typical

正解: A

 

質問 33
What needs to happen when new detailed requirements are added to a timebox?

  • A. More people should be added to the delivery team
  • B. Requirements of a similar level of effort should be removed
  • C. Formal change control should be applied
  • D. The delivery milestones should be reviewed and re-planned

正解: B

 

質問 34
Which statement about the 'protect the level of quality' target is CORRECT?

  • A. It gives confidence on the progress of the project
  • B. It is achieved by allowing enough time for testing
  • C. It is achieved by using the same team members
  • D. It delivers the early realization of benefits

正解: D

解説:
Reference:
%20level%20is%20met

 

質問 35
Which is typically used in agile when estimating detailed requirements during sprint planning?

  • A. T-shirt sizing
  • B. Trading
  • C. Visioning
  • D. Rationalism

正解: D

 

質問 36
......