質問 # 12
Which is a reason for releasing a product into a staging area?
- A. It supports regulatory compliance checking
- B. It enables a phased Waterfall approach
- C. It supports management by exception
- D. It enables the faster delivery of changes
正解:A
解説:
Reference:
%20and%20verification%20process
質問 # 13
Which statement about the 'protect the level of quality' target is CORRECT?
- A. It is achieved by using the same team members
- B. It delivers the early realization of benefits
- C. It gives confidence on the progress of the project
- D. It is achieved by allowing enough time for testing
正解:B
解説:
Reference:
%20level%20is%20met
質問 # 14
Which is a key objective of running a workshop?
- A. To make daily progress visible to the delivery team and key stakeholders
- B. To encourage collaboration and create the defined outputs from the event
- C. To communicate decisions to the wider stakeholder community
- D. To make day-to-day decisions on behalf of the delivery team within a sprint
正解:B
質問 # 15
Which is typically used in agile when estimating detailed requirements during sprint planning?
- A. Visioning
- B. T-shirt sizing
- C. Trading
- D. Rationalism
正解:D
質問 # 16
What should the business case state about the minimum viable product (MVP)?
- A. What the MVP is
- B. That the MVP is the same as project viability
- C. That the MVP must go into operational use
- D. When the MVP will be defined
正解:C
質問 # 17
Which TWO statements about the typical tailoring of a checkpoint report in an agile environment are CORRECT?
1) It should be replaced by the project manager attending a daily stand-up.
2) It should be displayed in the form of an information radiator in a team room.
3) It should be produced when the amount to be delivered will result in tolerance being exceeded.
4) It should be produced in a product backlog in the form of prioritized user stories.
- A. 1 and 2
- B. 3 and 4
- C. 2 and 3
- D. 1 and 4
正解:C
質問 # 18
How is the 'learn from experience' principle applied in an agile context?
- A. By using the Agilometer to assess risks associated with the agile way of working
- B. By continual customer involvement to obtain feedback during the project
- C. By prioritizing quality criteria to focus the project on the delivery of value
- D. By ensuring control through lots of short stages during innovative projects
正解:B
質問 # 19
Which statement about the 'keep teams stable' target is CORRECT?
- A. It will lead to a lower cost of ownership
- B. It is required in order to allow the team to self-organize
- C. It results in the earth delivery of a minimum viable product
- D. It ensures that the level of quality is protected
正解:B
質問 # 20
Which is a purpose of the quality theme?
- A. To define the specific conditions that enable a product to be usable
- B. To evaluate whether the project continues to be achievable
- C. To determine how the means of delivering products is communicated
- D. To assess any potential improvements to a product
正解:B
質問 # 21
Which statement about the PRINCE2 Agile behaviour 'collaboration' is CORRECT?
- A. It uses the most effective channel to communicate
- B. It allows the delivery team to decide how best to get the job done
- C. It creates a shared ownership of goals
- D. It allows many small learnings to accumulate over time
正解:C
質問 # 22
Which is a purpose of the plans theme?
- A. To control any approved changes to the baseline
- B. To monitor actual achievements against those planned
- C. To identify any deviations from the project's objectives
- D. To communicate the approach for delivering products
正解:D
質問 # 23
How does PRINCE2 Agile describe Scrum?
- A. Scrum is an IT method
- B. Scrum is a project management framework
- C. Scrum is the most well-known agile framework
- D. Scrum is agile and agile is Scrum
正解:C
質問 # 24
What information is NOT typically displayed on a burn chart?
- A. Actual amount of work done
- B. Effort remaining
- C. Team working agreements
- D. Amount of time elapsed
正解:C
質問 # 25
Which statement about the 'accept that the customer doesn't need everything' target is CORRECT?
- A. It is achieved by testing only a few features to deliver on time
- B. It enables a more accurate final product to be produced
- C. It is achieved by ensuring that the operational product has complete documentation
- D. It is based on the concept that people generally use a limited number of product features
正解:D
質問 # 26
What should be emphasized when tailoring the PRINCE2 Progress theme?
- A. Assessing the impact of risks
- B. Planning resources
- C. Tracking time and cost
- D. Monitoring what is being delivered
正解:D
質問 # 27
Which is the BEST method of communication to gather feedback?
- A. Discussing over the telephone to gather feedback quickly from stakeholders
- B. Receiving emailed diagrams to encourage discussion
- C. Conducting online surveys to obtain a range of opinions
- D. Meeting face-to-face to encourage an exchange of views
正解:D
質問 # 28
......
PRINCE2-Agile-Foundation試験問題集でPDF問題とテストエンジン:https://www.goshiken.com/PRINCE2/PRINCE2-Agile-Foundation-mondaishu.html