質問 # 12
Which is a reason for releasing a product into a staging area?

  • A. It supports regulatory compliance checking
  • B. It enables a phased Waterfall approach
  • C. It supports management by exception
  • D. It enables the faster delivery of changes

正解:A

解説:
Reference:
%20and%20verification%20process


質問 # 13
Which statement about the 'protect the level of quality' target is CORRECT?

  • A. It is achieved by using the same team members
  • B. It delivers the early realization of benefits
  • C. It gives confidence on the progress of the project
  • D. It is achieved by allowing enough time for testing

正解:B

解説:
Reference:
%20level%20is%20met


質問 # 14
Which is a key objective of running a workshop?

  • A. To make daily progress visible to the delivery team and key stakeholders
  • B. To encourage collaboration and create the defined outputs from the event
  • C. To communicate decisions to the wider stakeholder community
  • D. To make day-to-day decisions on behalf of the delivery team within a sprint

正解:B


質問 # 15
Which is typically used in agile when estimating detailed requirements during sprint planning?

  • A. Visioning
  • B. T-shirt sizing
  • C. Trading
  • D. Rationalism

正解:D


質問 # 16
What should the business case state about the minimum viable product (MVP)?

  • A. What the MVP is
  • B. That the MVP is the same as project viability
  • C. That the MVP must go into operational use
  • D. When the MVP will be defined

正解:C


質問 # 17
Which TWO statements about the typical tailoring of a checkpoint report in an agile environment are CORRECT?
1) It should be replaced by the project manager attending a daily stand-up.
2) It should be displayed in the form of an information radiator in a team room.
3) It should be produced when the amount to be delivered will result in tolerance being exceeded.
4) It should be produced in a product backlog in the form of prioritized user stories.

  • A. 1 and 2
  • B. 3 and 4
  • C. 2 and 3
  • D. 1 and 4

正解:C


質問 # 18
How is the 'learn from experience' principle applied in an agile context?

  • A. By using the Agilometer to assess risks associated with the agile way of working
  • B. By continual customer involvement to obtain feedback during the project
  • C. By prioritizing quality criteria to focus the project on the delivery of value
  • D. By ensuring control through lots of short stages during innovative projects

正解:B


質問 # 19
Which statement about the 'keep teams stable' target is CORRECT?

  • A. It will lead to a lower cost of ownership
  • B. It is required in order to allow the team to self-organize
  • C. It results in the earth delivery of a minimum viable product
  • D. It ensures that the level of quality is protected

正解:B


質問 # 20
Which is a purpose of the quality theme?

  • A. To define the specific conditions that enable a product to be usable
  • B. To evaluate whether the project continues to be achievable
  • C. To determine how the means of delivering products is communicated
  • D. To assess any potential improvements to a product

正解:B


質問 # 21
Which statement about the PRINCE2 Agile behaviour 'collaboration' is CORRECT?

  • A. It uses the most effective channel to communicate
  • B. It allows the delivery team to decide how best to get the job done
  • C. It creates a shared ownership of goals
  • D. It allows many small learnings to accumulate over time

正解:C


質問 # 22
Which is a purpose of the plans theme?

  • A. To control any approved changes to the baseline
  • B. To monitor actual achievements against those planned
  • C. To identify any deviations from the project's objectives
  • D. To communicate the approach for delivering products

正解:D


質問 # 23
How does PRINCE2 Agile describe Scrum?

  • A. Scrum is an IT method
  • B. Scrum is a project management framework
  • C. Scrum is the most well-known agile framework
  • D. Scrum is agile and agile is Scrum

正解:C


質問 # 24
What information is NOT typically displayed on a burn chart?

  • A. Actual amount of work done
  • B. Effort remaining
  • C. Team working agreements
  • D. Amount of time elapsed

正解:C


質問 # 25
Which statement about the 'accept that the customer doesn't need everything' target is CORRECT?

  • A. It is achieved by testing only a few features to deliver on time
  • B. It enables a more accurate final product to be produced
  • C. It is achieved by ensuring that the operational product has complete documentation
  • D. It is based on the concept that people generally use a limited number of product features

正解:D


質問 # 26
What should be emphasized when tailoring the PRINCE2 Progress theme?

  • A. Assessing the impact of risks
  • B. Planning resources
  • C. Tracking time and cost
  • D. Monitoring what is being delivered

正解:D


質問 # 27
Which is the BEST method of communication to gather feedback?

  • A. Discussing over the telephone to gather feedback quickly from stakeholders
  • B. Receiving emailed diagrams to encourage discussion
  • C. Conducting online surveys to obtain a range of opinions
  • D. Meeting face-to-face to encourage an exchange of views

正解:D


質問 # 28
......