質問 # 16
Which statement about timeboxes is CORRECT?
- A. A project cannot be referred to as a timebox
- B. Timeboxes should be avoided in business as usual environments
- C. A timebox can contain another timebox
- D. Flow based working partitions work into timeboxes
正解:C
質問 # 17
How is the 'learn from experience' principle applied in an agile context?
- A. By continual customer involvement to obtain feedback during the project
- B. By using the Agilometer to assess risks associated with the agile way of working
- C. By ensuring control through lots of short stages during innovative projects
- D. By prioritizing quality criteria to focus the project on the delivery of value
正解:A
質問 # 18
Which TWO statements about the typical tailoring of a checkpoint report in an agile environment are CORRECT?
1) It should be replaced by the project manager attending a daily stand-up.
2) It should be displayed in the form of an information radiator in a team room.
3) It should be produced when the amount to be delivered will result in tolerance being exceeded.
4) It should be produced in a product backlog in the form of prioritized user stories.
- A. 1 and 2
- B. 2 and 3
- C. 1 and 4
- D. 3 and 4
正解:B
質問 # 19
Which statement about the PRINCE2 Agile behaviour 'collaboration' is CORRECT?
- A. It allows many small learnings to accumulate over time
- B. It uses the most effective channel to communicate
- C. It creates a shared ownership of goals
- D. It allows the delivery team to decide how best to get the job done
正解:C
質問 # 20
Which statement about the 'initiating a project' process is CORRECT?
- A. The project solution should be documented in detail in the project product description
- B. The process should take more time than usual for disruptive projects
- C. The impact of frequent releases on quality management should be assessed
- D. The initiation stage plan should form part of the project plan
正解:C
質問 # 21
To help with prioritization, what is MOST important when understanding the difference between scope and quality?
- A. Differentiating functional from non-functional requirements
- B. Combining functional and non-functional requirements
- C. Creating non-functional requirements with user stories
- D. Defining non-functional requirements before functional requirements
正解:A
質問 # 22
Which statement about the 'be on time and hit deadlines' target is CORRECT?
- A. It ensures that the level of quality is protected
- B. It is achieved by keeping the delivery teams stable
- C. It allows change to be handled dynamically
- D. It helps with planning dependencies within a project
正解:D
質問 # 23
What information is NOT typically displayed on a burn chart?
- A. Actual amount of work done
- B. Team working agreements
- C. Amount of time elapsed
- D. Effort remaining
正解:B
質問 # 24
What needs to happen when new detailed requirements are added to a timebox?
- A. The delivery milestones should be reviewed and re-planned
- B. Requirements of a similar level of effort should be removed
- C. More people should be added to the delivery team
- D. Formal change control should be applied
正解:B
質問 # 25
How does the change theme regard change in PRINCE2 Agile?
- A. As disruptive
- B. As inevitable
- C. As something to be avoided
- D. As a necessity
正解:B
質問 # 26
What should be emphasized when tailoring the PRINCE2 Progress theme?
- A. Assessing the impact of risks
- B. Tracking time and cost
- C. Planning resources
- D. Monitoring what is being delivered
正解:D
質問 # 27
Which statement describes how the PRINCE2 'starting up a project' process can be applied in an agile environment?
- A. PRINCE2 requires a lengthy start to a project
- B. PRINCE2 is predictive, but not emergent
- C. PRINCE2 is predictive and can be emergent
- D. PRINCE2 requires a disruptive start to a project
正解:C
質問 # 28
Which is often used during a retrospective to capture lessons?
- A. A Glad! Sad! Mad! board
- B. A burn chart
- C. A Gantt chart
- D. A Kanban board
正解:A
質問 # 29
Which is a key objective of running a workshop?
- A. To make daily progress visible to the delivery team and key stakeholders
- B. To encourage collaboration and create the defined outputs from the event
- C. To communicate decisions to the wider stakeholder community
- D. To make day-to-day decisions on behalf of the delivery team within a sprint
正解:B
質問 # 30
When should PRINCE2 Agile be used?
- A. When a team is created to deliver a specific product
- B. When simple requests to update a product are implemented
- C. When delivering an ongoing service to a customer
- D. When an established team performs product maintenance
正解:D
質問 # 31
What is the MOST LIKELY benefit from frequent releases into operational use?
- A. The risks associated with agile ways of working are assessed
- B. The need for customer involvement is increased
- C. The need for configuration management is reduced
- D. Feedback is obtained from real customers
正解:D
質問 # 32
Which is a purpose of the quality theme?
- A. To evaluate whether the project continues to be achievable
- B. To assess any potential improvements to a product
- C. To determine how the means of delivering products is communicated
- D. To define the specific conditions that enable a product to be usable
正解:A
質問 # 33
Which statement about the 'directing a project' process is CORRECT?
- A. The project board should increase the stage-level time tolerance
- B. A project board member should fulfill the product owner role within a delivery team
- C. The project board should attend regular project progress meetings
- D. The project board should make decisions based on the Agilometer risks
正解:B
質問 # 34
What term is used to describe boards that display what work needs to be completed for people working on a project?
- A. Highlight report
- B. Information radiator
- C. Work in progress limit
- D. Glad! Sad! Mad!
正解:A
質問 # 35
......