
[2023年12月]に更新されたPRINCE2 Agile PRINCE2-Agile-Foundation試験練習問題集お試しセット
2023年最新のPRINCE2-Agile-Foundationプレミアム資料テストPDF無料問題集お試しセット
質問 # 19
Which statement about the waterfall methodology definition is CORRECT?
- A. It is a behavior that involves making things transparent
- B. It has distinct goals for each stage of development
- C. It promotes the use of experiments carried out in a scientific way
- D. It states that deadlines should not be moved
正解:B
質問 # 20
Which statement about the 'keep teams stable' target is CORRECT?
- A. It prevents compromising the overall quality level of the product
- B. It results in the early delivery of a minimum viable product
- C. It is the primary reason why the tolerance for cost is set to zero
- D. It applies primarily to the long term, such as a project or a program
正解:C
質問 # 21
Which describes the Scrum Master role in Scrum?
- A. It is empowered to organize and manage its own work to create a valuable, useful increment every sprint
- B. It is servant-leadership to help everyone change their interactions to maximize the value created by the team
- C. It is responsible for ensuring that product backlog items are clearly expressed on the product backlog
- D. It is authorized to run the project on a day-to-day basis on behalf of the project board
正解:C
質問 # 22
What is the definition of a timebox?
- A. A description of the rate of progress a team is making
- B. A period where work is carried out to achieve a goal
- C. A regular event that looks at how processes can be improved
- D. A tool to write a requirement in the form of who, what and why
正解:B
質問 # 23
Which PRINCE2 principle should be followed in order to engage the business, user and supplier stakeholder interests?
- A. Learn from experience
- B. Continued business justification
- C. Tailor to suit the project
- D. Defined roles and responsibilities
正解:D
質問 # 24
What should the business case state about the minimum viable product (MVP)?
- A. What the MVP is
- B. That the MVP is the same as project viability
- C. When the MVP will be defined
- D. That the MVP must go into operational use
正解:D
質問 # 25
What term is used to describe boards that display what work needs to be completed for people working on a project?
- A. Work in progress limit
- B. Highlight report
- C. Glad! Sad! Mad!
- D. Information radiator
正解:B
質問 # 26
What is typically displayed on a board to show progress to people working on a project?
- A. Agilometer assessment
- B. User story
- C. Information radiator
- D. Product backlog
正解:C
質問 # 27
Which process can take place during a release review workshop?
- A. Controlling a stage
- B. Managing product delivery
- C. Directing a project
- D. Managing a stage boundary
正解:B
質問 # 28
What BEST defines embryonic customer requirements?
- A. Sub-products
- B. 'Fine-grained' user stories
- C. Technical stories
- D. Epics
正解:D
質問 # 29
Which is a reason for releasing a product into a staging area?
- A. It supports regulatory compliance checking
- B. It supports management by exception
- C. It enables the faster delivery of changes
- D. It enables a phased Waterfall approach
正解:A
解説:
Reference:
%20and%20verification%20process
質問 # 30
In Scrum, what answers the question 'what can be done this sprint?'
- A. Increment
- B. Sprint planning
- C. Sprint review
- D. Daily scrum
正解:D
質問 # 31
Which BEST describes the senior user role when tailoring the organization theme?
- A. A 'coach'
- B. A 'super product owner'
- C. An 'executive sponsor'
- D. An 'agile sponsor'
正解:B
質問 # 32
What should be emphasized when tailoring the PRINCE2 Progress theme?
- A. Tracking time and cost
- B. Planning resources
- C. Assessing the impact of risks
- D. Monitoring what is being delivered
正解:D
質問 # 33
Which TWO project board responsibilities are specifically assigned to the senior user?
1) Demonstrating the achievement of benefits.
2) Specifying the needs of those impacted by the outputs.
3) Balancing business, user and supplier demands.
4) Ensuring that the project delivers value for money.
- A. 2 and 3
- B. 1 and 2
- C. 3 and 4
- D. 1 and 4
正解:B
質問 # 34
Which statement about the 'directing a project' process is CORRECT?
- A. The project board may pull reports from the information radiator
- B. As a minimum, the project board should receive oral reports from the project manager
- C. The project board should attend the delivery team's daily stand up meeting
- D. The project board should receive regular reports focusing on cost and time overruns
正解:A
質問 # 35
Which TWO statements describe a purpose of the business case?
1) To define the acceptance criteria for what the project must deliver.
2) To transfer responsibility for the work to the appropriate delivery team.
3) To document how significant risks will affect the expected project benefits.
4) To outline how and when the anticipated benefits can be measured.
- A. 2 and 3
- B. 1 and 2
- C. 3 and 4
- D. 1 and 4
正解:C
質問 # 36
How should product-based planning be used as part of PRINCE2 Agile?
- A. To track progress against the team plan
- B. To create the project plan using empiricism
- C. To enable team planning to be predictive
- D. To plan by focusing on the features required
正解:D
質問 # 37
Which statement about the 'embrace change' target is CORRECT?
- A. It trades user stories for those of a similar size
- B. It results in the late delivery of the minimum viable product
- C. It degrades the performance of the features that are delivered
- D. It re-establishes team dynamics when a new member joins the team
正解:C
質問 # 38
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?
- A. Using visualization to display information
- B. Using social media to reach more people
- C. Using meeting minutes to share decisions
- D. Using email to document discussions
正解:A
質問 # 39
Which is typically used in agile when estimating detailed requirements during sprint planning?
- A. Visioning
- B. Trading
- C. Rationalism
- D. T-shirt sizing
正解:C
質問 # 40
......
今すぐ弊社のPRINCE2 Agile試験パッケージ使って試験準備してPRINCE2-Agile-Foundationをパスせよ:https://www.goshiken.com/PRINCE2/PRINCE2-Agile-Foundation-mondaishu.html
全幅的な更新されたトレーニング専門問題を使って2023年最新のPRINCE2-Agile-Foundation試験問題集テスト合格:https://drive.google.com/open?id=124hg1mEuPL3DM83UgnRhDzDuFIZ-R6EO