質問 13
Why should stakeholders' influence and interests be compared?
- A. To ensure communication channels are exploited effectively
- B. To identify the various stakeholders from their interests
- C. To define the areas of the programme that affect each stakeholder
- D. To understand how the programme will affect their working environment Section: (none) Explanation
正解: D
質問 14
Which role facilitates assessments of the impact of changes on the target operating model?
- A. Programme office
- B. Business change manager
- C. Senior responsible owner
- D. Programme manager
正解: A
質問 15
Which transformational flow process provides the basis for deciding whether the programme can proceed?
- A. Delivering the Capability
- B. Defining a Programme
- C. Identifying a Programme
- D. Managing the Tranches
正解: C
質問 16
Which describes an impact of a risk?
- A. Possibility that something will go wrong
- B. The amount of risk that will be tolerated
- C. An event that might increase a programme's outcome
- D. Effect on the programme if something goes wrong
正解: D
質問 17
Which is a programme management principle?
- A. Vision
- B. Adding value
- C. Corporate strategy
- D. Identifying a programme
正解: B
質問 18
Which of the following statements about business change and transition costs in the business case are true?
1. Include the costs of any interim operational resources required to embed the change.
2. Include the costs of a contingency budget for dealing with risk.
- A. Only 2 is true
- B. Both 1 and 2 are true
- C. Neither 1 and 2 are true
- D. Only 1 is true
正解: D
質問 19
What role has a focus on designing benefit measures within a programme to track business performance against targets?
- A. Senior Responsible Owner
- B. Programme Manager
- C. Benefits Realization Manager
- D. Business Change Manager
正解: C
質問 20
Which is MOST LIKELY to trigger premature closure of a programme?
- A. The scope of one of the key projects has been changed
- B. The last tranche has been completed as per the programme plan
- C. The programme is no longer aligned with corporate strategy
- D. There is a change of senior responsible owner
正解: C
質問 21
Which is a description of a programme resource?
- A. A process to control a programme
- B. A logical grouping of projects within a programme
- C. The objective of a programme
- D. An input required by a programme
正解: D
質問 22
Which role would be MOST LIKELY to initiate assurance reviews of project performance?
- A. Business change manager
- B. Senior responsible owner
- C. Programme manager
- D. Programme office
正解: C
質問 23
Which of the following statements about successful stakeholder engagement are true?
1. It is more active and embracing than communication.
2. It includes stakeholders in decision making and implementation.
- A. Only 2 is true
- B. Only 1 is true
- C. Neither 1 or 2 is true
- D. Both 1 and 2 are true
正解: D
質問 24
Which is the BEST description of the purpose of the Projects Dossier?
- A. Describes the context when starting up projects
- B. Provides detailed requirements for each project
- C. Specifies a thorough brief for starting each project
- D. Lists the projects involved in the delivery of the Blueprint
正解: D
解説:
Projects dossier provides a list of projects required to deliver the blueprint, with high-level information and estimates.
質問 25
What can programme leaders do to influence key stakeholders?
- A. Analyze stakeholder influence and interest
- B. Create a programme communications plan
- C. Hold visioning workshops to draft the vision statement
- D. Produce a stakeholder map to show areas of interest
正解: B
質問 26
Which is NOT a governance theme?
- A. Vision
- B. Blueprint design and delivery
- C. The business case
- D. Benefit profile
正解: D
質問 27
Which response pays a third party to accept a risk?
- A. Avoid
- B. Prepare contingent plans
- C. Accept
- D. Transfer
正解: D
質問 28
Which role is responsible for delivering the capability?
- A. Programme board
- B. Business change manager
- C. Programme manager
- D. Senior responsible owner
正解: D
質問 29
What role is responsible for tracking the progress of risk responses?
- A. Risk Manager
- B. Risk owner
- C. Design Authority
- D. Risk actionee
正解: B
質問 30
Which transformational flow process results in the achievement of outcomes?
- A. Delivering the Capability
- B. Closing a Programme
- C. Managing the Tranches
- D. Realizing the Benefits
正解: D
質問 31
Which is a characteristic of a programme?
- A. It co-ordinates, directs and oversees the implementation of a set of related projects and activities
- B. It defines an organization's approach to achieving its corporate objectives in a given area of business
- C. It manages the planning, monitoring and control of projects
- D. It delivers one or more outputs in accordance with an agreed business case
正解: A
質問 32
Which document should be used to provide guidance on the standards that should be followed when producing outputs?
- A. Project Brief
- B. Programme Brief
- C. Programme Blueprint
- D. Projects Dossier
正解: A
質問 33
In which situation should benefits management continue after programme closure?
- A. Transition is still being undertaken
- B. The benefits still need to be aligned to corporate strategy
- C. Business change managers are still facilitating change
- D. Unexpected benefits are still being captured
正解: C
質問 34
......