質問 # 52
Which of the following components ensures that risks are examined for all new proposed change requests in the change control system?

  • A. Configuration management
  • B. Integrated change control
  • C. Risk monitoring and control
  • D. Scope change control

正解:B


質問 # 53
Which positive risk response best describes a teaming agreement?

  • A. Venture
  • B. Exploit
  • C. Enhance
  • D. Share

正解:D


質問 # 54
A race director is planning a marathon with US$80,000 in upfront costs that will be offset by race fees. The remainder of the funds will be donated to a national charity. State law mandates that all money paid by the participants must be refunded if the race is cancelled for any reason.
Which of the following is the best example of a risk mitigation response?

  • A. Purchase an insurance policy covering up to US$85,000 in losses, at a cost of US$5,000, in the event the race is cancelled.
  • B. Charge the runners an additional amount to cover the US$80,000.
  • C. Inform the charity that they will receive no funds should the race be cancelled.
  • D. Let the runners know the race will be cancelled only in the event of an emergency.

正解:A


質問 # 55
Kelly is the project manager of the BHH project for her organization. She is completing the risk identification process for this portion of her project. Which one of the following is the only thing that the risk identification process will create for Kelly?

  • A. Risk register updates
  • B. Project document updates
  • C. Risk register
  • D. Change requests

正解:C


質問 # 56
Sensitivity analysis is a technique for systematically changing parameters in a model to determine the effects of such changes and is useful for computer modelers for a range of purposes. Which of the following purposes does the sensitivity analysis include? Each correct answer represents a complete solution. Choose all that apply.

  • A. Increased understanding or quantification of the system
  • B. Estimating the average outcome
  • C. Model development
  • D. Decision making or the development of recommendations for decision makers

正解:A、C、D


質問 # 57
In what portion of a project are risk and opportunities greatest and require intense planning and anticipation of risk events?

  • A. Executing
  • B. Planning
  • C. Closing
  • D. Initiating

正解:D


質問 # 58
You are the project manager of a large, high-profile project in your organization. You have realized that politics within your company may affect the true identification of risk events within the project. You decide that you'd like to use a method to identify risk events through an anonymous process. Which one of the following risk events will allow you to collect and distribute risk information without the stakeholders knowing what other stakeholders are communicating about the project risk events?

  • A. Monte Carlo Technique
  • B. Delphi Technique
  • C. Checklist analysis
  • D. Surveys

正解:B


質問 # 59
A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors. What should the project manager do when engaging stakeholders?

  • A. Consider stakeholders' positions and opinions regarding the project's output.
  • B. Ignore any risks beyond stakeholders' tolerance.
  • C. Communicate response strategies to all stakeholders.
  • D. Include all stakeholders in the project's governance.

正解:A

解説:
Explanation
The project manager should consider stakeholders' positions and opinions regarding the project's output when engaging stakeholders. This approach helps to address stakeholders' concerns, expectations, and potential objections, and it can lead to better decision-making and more successful project outcomes. It is important for the project manager to maintain open communication with stakeholders and to be responsive to their needs and perspectives.


質問 # 60
Shelly is the project manager of the BUF project for her company. In this project Shelly needs to establish some rules to reduce the influence of risk bias during the qualitative risk analysis process. What method can Shelly take to best reduce the influence of risk bias?

  • A. Group stakeholders according to positive and negative stakeholders and then complete the risk analysis
  • B. Establish risk boundaries
  • C. Determine the risk root cause rather than the person identifying the risk events
  • D. Establish definitions of the level of probability and impact of risk event

正解:D


質問 # 61
The senior risk manager hears that critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. Which area should be reviewed, as an opportunity for the risk manager to coach the project manager responsible for the project?

  • A. Risk identification process and participation
  • B. Scope reduction to reduce SME reliance
  • C. Risk management plan and planned risks responses
  • D. Detailed review of the project schedule before approval

正解:B

解説:
Explanation/Reference:


質問 # 62
Mary is the project manager for the BLB project. She has instructed the project team to assemble, to review the risks. She has included the schedule management plan as an input for the quantitative risk analysis process. Why is the schedule management plan needed for quantitative risk analysis?

  • A. Mary will schedule when the identified risks are likely to happen and affect the project schedule.
  • B. Mary will utilize the schedule controls to determine how risks may be allowed to change the project schedule.
  • C. Mary will utilize the schedule controls and the nature of the schedule for the quantitative analysis of the schedule.
  • D. Mary will use the schedule management plan to schedule the risk identification meetings throughout the remaining project.

正解:C


質問 # 63
You work as a project manager for BlueWell Inc. You are working with Nancy, the COO of your company, on several risks within the project. Nancy understands that through qualitative analysis you have identified
80 risks that have a low probability and low impact as the project is currently planned. Nancy's concern, however, is that the impact and probability of these risk events may change as conditions within the project may change. She would like to know where will you document and record these 80 risks that have low probability and low impact for future reference. What should you tell Nancy?

  • A. Risks with low probability and low impact are recorded in a watchlist for future monitoring.
  • B. Risk identification is an iterative process so any changes to the low probability and low impact risks will be reassessed throughout the project life cycle.
  • C. All risks, regardless of their assessed impact and probability, are recorded in the risk log.
  • D. All risks are recorded in the risk management plan.

正解:A


質問 # 64
Harry is the project manager of the MMQ Construction Project. In this project, Harry has identified a supplier who can create stained glass windows for 1,000 window units in the construction project. The supplier is an artist who works by himself, but creates windows for several companies throughout the United States. Management reviews the proposal to use this supplier and while they agree that the supplier is talented, they do not think the artist can fulfill the 1,000 window units in time for the project's deadline. Management asked Harry to find a supplier who can fulfill the completion of the windows by the needed date in the schedule. What risk response has management asked Harry to implement?

  • A. Transference
  • B. Avoidance
  • C. Mitigation
  • D. Acceptance

正解:C


質問 # 65
You are the project manager of the NKQ project for your organization. You have completed the quantitative risk analysis process for this portion of the project. What is the only output of the quantitative risk analysis process?

  • A. Risk contingency reserve
  • B. Probability of reaching project objectives
  • C. Risk response
  • D. Risk register updates

正解:D


質問 # 66
You are the project manager of the GHY Project for your company. You have completed the risk response planning with your project team. You now need to update the WBS. Why would the project manager need to update the WBS after the risk response planning process? Choose the best answer.

  • A. Because of risk responses that are now activities
  • B. Because of risks associated with work packages
  • C. Because of work that was omitted during the WBS creation
  • D. Because of new work generated by the risk responses

正解:D


質問 # 67
Sammy is the project manager for her organization. She would like to rate each risk based on its probability and affect on time, cost, and scope. Harry, a project team member, has never done this before and thinks Sammy is wrong to attempt this approach. Harry says that an accumulative risk score should be created, not three separate risk scores. Who is correct in this scenario?

  • A. Harry is correct, because the risk probability and impact considers all objectives of the project.
  • B. Harry iscorrect, the risk probability and impact matrix is the only approach to risk assessment.
  • C. Sammy is correct, because she is the project manager.
  • D. Sammy is correct, because organizations can create risk scores for each objective of the project.

正解:D


質問 # 68
Frank is the project manager of the NHL Project for his company and he is starting the risk identification process for the project. Frank needs to ensure that the correct stakeholders are interviewed as part of risk identification. What document will help Frank to communicate and solicit inputs of the project stakeholders during risk identification?

  • A. Risk register
  • B. Requirements management plan
  • C. Stakeholder register
  • D. Project charter

正解:C

解説:
Explanation


質問 # 69
You are the project manager of the GHY project for your organization. You are about to start the qualitative risk analysis process for the project and you need to determine the roles and responsibilities for conducting risk management. Where can you find this information?

  • A. Risk register
  • B. Enterprise environmental factors
  • C. Risk management plan
  • D. Staffing management plan

正解:C


質問 # 70
......