質問 # 47
The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.
What should the project manager do?
- A. Wait until the weather improves before sending the equipment.
- B. Ask the project sponsor to approve shipping the equipment.
- C. Proceed with the planned risk response to move the equipment.
- D. Request the shipment of the equipment to satisfy the client.
正解:C
解説:
Explanation
The project manager should proceed with the planned risk response to move the equipment (C) since the risk of weather-related delays was already identified and recorded in the risk register. This approach ensures that the project team is prepared to handle the situation andcan mitigate the impact of the risk. This is consistent with the PMI's PMBOK Guide, Sixth Edition.
質問 # 48
You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the project set aside for the risk contingency reserve?
- A. $41,750
- B. $23,750
- C. $232,000
- D. $142,000
正解:B
質問 # 49
Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. This workaround to the risk event is known as what type of risk response?
- A. Avoidance
- B. Acceptance
- C. Mitigation
- D. Transference
正解:D
質問 # 50
You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process. Which one of the following is NOT an output of the risk response planning?
- A. Risk-related contract decisions
- B. Organizational process assets updates
- C. Project document updates
- D. Risk register updates
正解:B
質問 # 51
Harry works as a project manager for the NHQ Project. He is performing quantitative risk analysis for his project. One of the project risks has a 40 percent probability of happening, and it will cost the project
$65,000 if the risk happens. What is the expected monetary value of this risk event?
- A. Zero - the risk event has not yet occurred
- B. $27,000
- C. Negative $26,000
- D. Negative $67,000
正解:C
質問 # 52
You are the project manager of the CUL project in your organization. You and the project team are assessing the risk events and creating a probability and impact matrix for the identified risks. Which one of the following statements best describes the requirements for the data type used in qualitative risk analysis?
- A. A qualitative risk analysis requires fast and simple data to complete the analysis.
- B. A qualitative risk analysis encourages biased data to reveal risk tolerances.
- C. A qualitative risk analysis requires accurate and unbiased data if it is to be credible.
- D. A qualitative risk analysis required unbiased stakeholders with biased risk tolerances.
正解:C
質問 # 53
You are the project manager of your organization. Your organization will receive a bonus if the project finishes by December 20. Management has communicated this bonus to you and your project team and has asked you to evaluate the project to see if it is possible to realize the reward. The bonus offered to your organization is $750,000. You have examined the project and believe that you can crash the project for an additional $275,000 and reach the December 20 date. Management is thrilled with your assessment and they approve the crash fee. What risk response is this?
- A. Crashing can be a type of the enhancing risk response.
- B. Crashing is the addition of labor, not a risk response.
- C. Crashing can be considered transference because of the $275,000 is actually paid from the bonus, which is paid by the project customer.
- D. Crashing can be a type of the exploit risk response.
正解:A
質問 # 54
You are the project manager of a large, high-profile project in your organization. You have realized that politics within your company may affect the true identification of risk events within the project. You decide that you'd like to use a method to identify risk events through an anonymous process. Which one of the following risk events will allow you to collect and distribute risk information without the stakeholders knowing what other stakeholders are communicating about the project risk events?
- A. Monte Carlo Technique
- B. Surveys
- C. Checklist analysis
- D. Delphi Technique
正解:D
質問 # 55
During a major project review, the project manager discovers that large groups of internal management issues are obstructing progress. In reviewing the risk management plan, the project risk categories largely contain technical and customer relationship type risks. The project manager wants the risk management plan revised to account for these risk areas, particularly because the project has several more months before completion.
Who should the project manager collaborate with to revise the risk management plan at this stage of the project?
- A. Risk manager, risk owners, and project sponsor
- B. Risk manager, technical manager, and customers
- C. Project sponsor, product owner, and risk owners
- D. Risk manager, product owner, and risk owners
正解:C
質問 # 56
Your organization, as part of its enterprise environmental factors, has established risk governance to be implemented in each project. Part of this governance is the reassessment of risks within each project. How much detail and repetition in approach for risks to be reassessed for probability and impact?
- A. The amount of detail of repetition that is appropriate depends on how the project progresses relative to its objectives.
- B. The level of detail and reassessment should reflect the priority of the project.
- C. The probability and impact of risk event should determine the level of reassessment throughout the project lifecycle.
- D. Each risk reassessment should go into the same depth as the original risk assessment activity.
正解:A
質問 # 57
Which one of the following is the only output for the qualitative risk analysis process?
- A. Project management plan
- B. Risk register updates
- C. Enterprise environmental factors
- D. Organizational process assets
正解:B
質問 # 58
You are the project manager of the NGH project for your organization. You want to create a causeand- effect diagram to help discover the root causes of the risks within the project. Harold, the CIO, recommends that you create an Ishikawa diagram instead. What is an Ishikawa diagram?
- A. It diagrams the risks according to the work breakdown structure including resources.
- B. It is the same thing as a root cause diagram.
- C. It shows how various elements of a system interrelate.
- D. It is a graphical representation of situations showing causal influences.
正解:B
質問 # 59
Elizabeth is a project manager for her organization and she finds risk management to be very difficult for her to manage. She asks you, a lead project manager, at what stage in the project will risk management become easier. What answer best resolves the difficulty of risk management practices and the effort required?
- A. Risk management only becomes easier when the project moves into project execution.
- B. Risk management only becomes easier the more often it is practiced.
- C. Risk management is an iterative process and never becomes easier.
- D. Risk management only becomes easier when the project is closed.
正解:B
質問 # 60
You work as a project manager for BlueWell Inc. Your project is running late and you must respond to the risk.
Which risk response can you choose that will also cause you to update the human resource management plan?
- A. Transference
- B. Crashing the project
- C. Teaming agreements
- D. Fast tracking the project
正解:B
質問 # 61
You are the project manager for the ABC organization. Your current project has 75 internal stakeholders and 245 external stakeholders. Many of the risks within your project will only affect the internal stakeholders, but several of the identified risk events will affect the external stakeholders. Management would like to know the total number of communication channels in the project. How many communication channels exist in this project?
- A. 51,040
- B. 102,080
- C. 0
- D. 1
正解:A
質問 # 62
You are the project manager of the GHY Project for your company. You need to complete a project management process that will be on the lookout for new risks, changing risks, and risks that are now outdated. Which project management process is responsible for these actions?
- A. Risk analysis
- B. Risk identification
- C. Risk planning
- D. Risk monitoring and controlling
正解:D
質問 # 63
You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should you document the proposed responses and the current status of all identified risks?
- A. Stakeholder management strategy
- B. Risk management plan
- C. Risk register
- D. Lessons learned documentation
正解:C
解説:
Explanation
質問 # 64
Frank is the project manager of the NHH Project. He is working with the project team to create a plan to document the procedures to manage risks throughout the project. This document will define how risks will be identified and quantified. It will also define how contingency plans will be implemented by the project team.
What document is Frank and the NHH Project team creating in this scenario?
- A. Project management plan
- B. Risk management plan
- C. Project plan
- D. Resource management plan
正解:B
解説:
Explanation/Reference:
質問 # 65
After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.
What should the risk manager do to facilitate the sponsor's ask?
- A. Qualitative risk analysis
- B. Monte Carlo analysis
- C. Quantitative risk analysis
- D. Sensitivity analysis
正解:C
解説:
Explanation
Quantitative risk analysis helps to numerically analyze the probability and impact of risks on project objectives. By performing quantitative risk analysis, the risk manager can present the risks with the most impact on achieving the project objectives to the project sponsor. (Reference: PMBOK Guide, 6th Edition, p.
423)
質問 # 66
......
PMI-RMP認定試験は、リスク管理の専門家の知識と技能を評価するために設計されています。試験は、Project Management Institute(PMI)によって実施され、プロジェクトのリスクを特定し、評価し、軽減する責任を持つ個人を対象としています。PMI-RMP認定は、リスク管理における卓越性の証として世界中で認められています。