質問 # 28
Mary is the project manager of the HGH Project for her company. She and her project team have agreed that if the vendor is late by more than ten days they will cancel the order and hire the NBG Company to fulfill the order. The NBG Company can guarantee orders within three days, but the costs of their products are significantly more expensive than the current vendor. What type of a response strategy is this?
- A. Internal risk management strategy
- B. Contingent response strategy
- C. Expert judgment
- D. External risk response
正解:B
解説:
Explanation/Reference:
質問 # 29
You are the project manager for your organization. You are working with your key stakeholders in the qualitative risk analysis process. You understand that there is certain bias towards the risk events in the project that you need to address, manage, and ideally reduce. What solution does the PMBOK recommend to reduce the influence of bias during qualitative risk analysis?
- A. Isolate the stakeholders by project phases to determine their risk bias
- B. Establish the definitions of the levels of probability and impact
- C. Involve all stakeholders to vote on the probability and impact of the risk events
- D. Provide iterations of risk analysis for true reflection of a risk probability and impact
正解:B
質問 # 30
A risk manager faces resistance as they try to implement the project's risk strategy. Some members of the project team believe it is a waste of time and money, What should the risk manager do?
- A. Reduce the number of risk management activities.
- B. Meet with team members to address their concerns.
- C. Continue to implement the risk strategy
- D. Raise the concerns with the project sponsor,
正解:B
解説:
Explanation
When facing resistance from team members, the risk manager should engage in open communication to address their concerns and clarify the importance of risk management in the project.
質問 # 31
A project is In the initiation phase. The project stakeholders are Invited to a meeting to share their thoughts that may impact the project In a positive or negative way.
What will be the main output of this meeting?
- A. Evaluating the project's impact
- B. Evaluating the project's probability of success
- C. Identifying threats and opportunities
- D. Performing a qualitative analysis
正解:C
解説:
Explanation
The main output of the stakeholder meeting in the initiation phase is to identify threats and opportunities that may impact the project in a positive or negative way. This information will be used to develop the risk management plan.
質問 # 32
The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?
- A. Quantify the risk exposure that exceeds project contingency.
- B. Advise the client that the project has exhausted contingency.
- C. Generate reports to assess and communicate the project risk level.
- D. Recommend the removal of risks to the project manager to reduce project risk exposure.
正解:C
解説:
Explanation
The project risk manager should generate reports to assess and communicate the project risk level to stakeholders. This helps in making informed decisions and taking appropriate actions to manage risks effectively.
質問 # 33
You work as a project manager for TechSoft Inc. You, the project team, and the key project stakeholders have completed a round of quantitative risk analysis. You now need to update the risk register with your findings so that you can communicate the risk results to the project stakeholders - including management. You will need to update all of the following information except for which one?
- A. Trends in quantitative risk analysis
- B. Risk distributions within the project schedule
- C. Probability of achieving cost and time objectives
- D. Probabilistic analysis of the project
正解:B
質問 # 34
Examine the figure given below.
What will be the expected monetary value of Risk C?
- A. -$27,000
- B. $175,000 if the risk event actually happens
- C. -$175,000
- D. -$113,750
正解:A
質問 # 35
You work as a project manager for BlueWell Inc. You are about to complete the quantitative risk analysis process for your project. You can use three available tools and techniques to complete this process. Which one of the following is NOT a tool or technique that is appropriate for the quantitative risk analysis process?
- A. Quantitative risk analysis and modeling techniques
- B. Data gathering and representation techniques
- C. Organizational process assets
- D. Expert judgment
正解:C
質問 # 36
You are the project manager of a large construction project. Part of the project involves the wiring of the electricity in the building your project is creating. You and the project team determine the electrical work is too dangerous to perform yourself so you hire an electrician to perform the work for the project. This is an example of what type of risk response?
- A. Avoidance
- B. Acceptance
- C. Transference
- D. Mitigation
正解:C
質問 # 37
A new resource is added to the project team from a matrix organization. How should the project's risk manager familiarize the new team member with the project's risk management process?
- A. Provide the new team member with a copy of the risk register and latest status report.
- B. Provide project specific risk training and mentor through the risk process.
- C. Send the new team member the risk management plan to read.
- D. The functional manager is responsible for providing the training.
正解:B
解説:
Explanation/Reference:
質問 # 38
You are the project manager of RTF project for your organization. You are working with your project team and several key stakeholders to create a diagram that shows causal factors for an effect to be solved.
What diagramming technique are you using as a part of the risk identification process?
- A. Predecessor and successor diagramming
- B. Cause and effect diagrams
- C. System or process flow charts
- D. Influence diagrams
正解:B
質問 # 39
A company is preparing a formal response to bid for an infrastructure engineering, procurement, and construction project. When should a risk register be developed to identify risks?
- A. When a client project kick-off meeting is held to introduce risk assessment process to the client.
- B. After a project budget is set up with a purchase order to charge hours for a risk workshop.
- C. Before a formal bid response is provided to the client to gain a greater understanding of the project's risk profile.
- D. During the project execution phase to allow the project manager to understand the risk attitudes of stakeholders.
正解:C
解説:
Explanation
A risk register should be developed before submitting a formal bid response to help the company understand the project's risk profile and account for potential risks in their proposal. This allows the company to make informed decisions about cost, schedule, and resources. (Reference: Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Sixth Edition, Section 11.2)
質問 # 40
Pete works as a project manager for BlueWell Inc. The Management has told him that he must implement an agreed-upon contingency response if the cost performance index in his project is less than 0.90. Consider that Pete's project has a budget at completion of $275,000. His project is 65 percent complete and he has spent $175,000 to date. However, Pete is scheduled to be 78 percent complete. What is the cost performance index for this project to determine if the
contingency response should happen?
- A. 0.90
- B. 1.02
- C. 0.89
- D. 0.96
正解:B
質問 # 41
While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.
What should the project manager do next?
- A. Develop risk response plans for all identified risks.
- B. Monitor and control secondary and residual risks in the risk register.
- C. Update the communications management plan to avoid future issues
- D. Identify secondary or residual risks for associated risk plans.
正解:B
解説:
Explanation
The project manager should monitor and control secondary and residual risks in the risk register. This will ensure that any new risks identified during the implementation of the risk response plan are captured and managed effectively. Monitoring and controlling risks is acontinuous process that helps in identifying, analyzing, and planning for new risks as well as updating the risk register as needed.
質問 # 42
Kelly is the project manager of the NNQ Project for her company. This project will last for one year and has a budget of $350,000. Kelly is working with her project team and subject matter experts to begin the risk response planning process. When the project manager begins the plan risk response process, what two inputs will she need?
- A. Risk register and the risk response plan
- B. Risk register and the results of risk analysis
- C. Risk register and the risk management plan
- D. Risk register and power to assign risk responses
正解:C
質問 # 43
You work as a project manager for BlueWell Inc. You are performing the quantitative risk analysis for your project. One of the project risks has a 50 percent probability of happening, and it will cost the project $55,000 if the risk happens. What will be the expected monetary value of this risk event?
- A. Negative $26,000
- B. Zero - the risk event has not yet occurred
- C. Negative $27,500
- D. Negative $55,000
正解:C
質問 # 44
Which of the following processes is described in the statement below? "This is the process of numerically analyzing the effect of identified risks on overall project objectives."
- A. Perform Quantitative Risk Analysis
- B. Perform Qualitative Risk Analysis
- C. Monitor and Control Risks
- D. Identify Risks
正解:A
質問 # 45
As a part of monitoring and controlling the project, the project manager should update the risk register. The project manager should update the risk register with information on risk reassessment, risk audits, and periodic risk reviews. What other information should the project manager update the risk register with?
- A. Actual cost of risk events.
- B. Actual outcomes of risk management duties by the project team.
- C. Actual costs and schedule delays of risk events.
- D. Actual outcomes of the project's risks and of the risk responses.
正解:D
質問 # 46
A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.
What should the risk manager do next to find out the correct limit?
- A. Use industry standard risk thresholds
- B. Review the agreed-upon risk tolerance
- C. Perform a sensitivity analysis of the risk
- D. Find out the stakeholders' risk appetite
正解:B
解説:
Explanation
The risk manager should review the agreed-upon risk tolerance to determine the correct limit for continuing construction based on the chance of rain. Risk tolerance is the level of risk an organization is willing to accept and should be established during the risk management planning process.
質問 # 47
......