質問 # 25
During the risk Monitor and Control Project Work process, the scope, schedule, and cost begin to increase.
What outputs should be updated and/or created?

  • A. Change requests, cost plan, and project documents
  • B. Enterprise environmental factors, change requests, and project management plan
  • C. Change requests, project management plan, and project documents
  • D. Project management plan, project documents, and human resource plan

正解:A


質問 # 26
Which positive risk response best describes a teaming agreement?

  • A. Share
  • B. Exploit
  • C. Venture
  • D. Enhance

正解:A


質問 # 27
You are the project manager of the NHH Project for your company and you have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Now, you would like to assign risk owners to the events. Which risk events should have risk response owners?

  • A. Each risk that has a risk response should have a risk response owner
  • B. Only the risks with a high risk rating
  • C. Each agreed-to and funded risk response should have a risk response owner
  • D. Only the risk events that are considered a negative risk event with a high risk rating

正解:C

解説:
Explanation


質問 # 28
Tom works as a project manager for BlueWell Inc. He is determining which risks can affect the project.
Which of the following inputs of the identify risks process is useful in identifying risks, and provides a quantitative assessment of the likely cost to complete the scheduled activities?

  • A. Cost management plan
  • B. Risk management plan
  • C. Activity duration estimates
  • D. Activity cost estimates

正解:D


質問 # 29
Holly is the project manager of the GHH Project. During risk identification and the subsequent risk analysis process she has identified a risk with a high probability and high impact for her project. She and the stakeholder agree that the project management plan should be changed to eliminate the risk threat entirely. What risk response has Holly used in this instance?

  • A. This is the transference risk response.
  • B. This is the avoidance risk response.
  • C. This is the risk mitigation response.
  • D. This is a scope change and not a risk response.

正解:B


質問 # 30
A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process.
What should the risk manager do next with the data set?

  • A. Perform Monte Carlo simulations
  • B. Perform a probability and impact assessment
  • C. Perform a risk data quality assessment
  • D. Perform a sensitivity analysis

正解:C

解説:
Explanation
After gathering cycle time data, the risk manager should perform a risk data quality assessment to ensure the data is accurate, reliable, and relevant for evaluating the current process and the new software.


質問 # 31
A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.
What should the risk manager of the related project have done to prevent this situation from happening?

  • A. Educated the project team on budget change requests.
  • B. Communicated better with the organization's CEO.
  • C. Reformed the risk monitoring and closing process properly.
  • D. Created the project work plan and budget more accurately.

正解:D

解説:
Explanation
The risk manager should have ensured a more accurate project work plan and budget to prevent the functional manager from requesting to use the project's contingency budget. A well-planned budget would have avoided the shortage in the functional manager's department budget.


質問 # 32
You are the project manager for your organization and you are working with Thomas, a project team member. You and Thomas have been working on a specific risk response for a probable risk event in the project. Thomas is empowered with a risk response and will control all aspects of the identified risk response in which a particular risk event will happen within the project. What title, in regard to risk, is bestowed on Thomas?

  • A. Risk expeditor
  • B. Risk team leader
  • C. Risk owner
  • D. Risk coordinator

正解:C


質問 # 33
A heavy industrial design firm has over US$3 billion in current contract value. As a result of quantitative risk analysis of a geographically separated project, opportunities have been identified and assessed as high priorities for the project.
What is the most effective method to capture these opportunities?

  • A. Establish a contingency reserve.
  • B. Schedule a project team meeting.
  • C. Integrate them into the RBS.
  • D. Formally notify the project manager.

正解:C


質問 # 34
Bill is the project manager for a project that will last six months and has a budget of $580,000. In this project a high-risk has been identified with the new materials the project will be using. Bill would like to assign one person, Beth, to be responsible to monitor this risk. Bill assigns Beth the authority to respond to the risk event if it appears in the risk events that is likely to happen. In addition, Bill hires a consultant to work with Beth on this area of the project. In this instance, who is the risk response owner?

  • A. Beth and the consultant are the risk owners
  • B. Beth, because she has the authority to respond to the risk event
  • C. The consultant working with Beth, because this is transference
  • D. Bill, because he is the project manager

正解:B


質問 # 35
Harry works as a project manager for BlueWell Inc. He is determining how to conduct the risk management activities for a project. According to the PMBOK, there are six inputs to the plan risk management process.
Which one of the following is NOT an input to this process?

  • A. Cost management plan
  • B. Project scope statement
  • C. Risk management plan
  • D. Schedule management plan

正解:C


質問 # 36
Joan is the project manager of the BTT project for her company. She has worked with her project to create risk responses for both positive and negative risk events within the project. As a result of this process Joan needs to update the project document updates. She has updated the assumptions log as a result of the findings and risk responses, but what other documentation will need to be updated as an output of risk response planning?

  • A. Risk Breakdown Structure
  • B. Technical documentation
  • C. Lessons learned
  • D. Scope statement

正解:B


質問 # 37
Which of the following would a proactive risk manager do during the Monitoring and Controlling Process?

  • A. Develop risk responses, create risk management plan, and stay alert for risk events.
  • B. Update the lessons learned documents, develop risk responses, and create the risk management plan.
  • C. Review identified risks, stay alert for risk events, and remind team members to keep the risk manager informed about risk triggers.
  • D. Review lessons learned document to identify risks, quantity risks, and lower impact ratings.

正解:C


質問 # 38
You are the project manager of the AFD project for your company. You are working with the project team to reassess existing risk events and to identify risk events that have not happened and whose relevancy to the project has passed. What should you do with these events that have not happened and would not happen now in the project?

  • A. Add the risks to a low-prioritywatchlist
  • B. Add the risk to the issues log
  • C. Add the risks to the risk register
  • D. Close the outdated risks

正解:D


質問 # 39
Yolanda is the project manager of a high-profile project for her organization. This project has 124 stakeholders from across the organization and many of the stakeholders have high demands and expectations for the project. Yolanda will need several pieces of project information as she begins to communicate and manage the stakeholder expectations. Which of the following inputs of the manage stakeholder expectations process directly addresses the risks that could affect the project and which must be communicated to the project stakeholders?

  • A. Issue log
  • B. Stakeholder register
  • C. Change log
  • D. Low-level risks watchlist

正解:C


質問 # 40
When selecting strategies as an activity of Plan Risk Response, what is the overall goal?

  • A. Select the strategies with the least financial impact.
  • B. Select the strategies with the greatest benefit to stakeholders.
  • C. Select the strategies with the least overall impact to resources.
  • D. Select the strategies with the greatest overall positive influence.

正解:D

解説:
Explanation
The overall goal of selecting strategies during the Plan Risk Response activity is to choose those strategies that have the greatest overall positive influence on the project, considering factors such as cost, schedule, and resources.