質問 # 40
The least effective method of surface cleaning is most likely
- A. power tool cleaning.
- B. dry grit blasting.
- C. water blasting.
- D. hand tool cleaning.
正解:D
質問 # 41
Upon arrival of coating materials, the inspector should
- A. observe and document time frame and environmental conditions between each coat.
- B. observe and document the amount of material and batch numbers.
- C. review coating contractors' plans for storage of coating materials and confirm they meet national, local and owners' fire and environmental regulations.
- D. observe aryl document that the applicator WFT at regular intervals during application.
正解:B
質問 # 42
Using SSPC Vis 1 as a guide when performing a visual inspection of a steel surface prior to surface preparation a NACE Inspector would assign which designations to the surface condition:
- A. Surface Conditions E-G
- B. Rust Grades 1-4
- C. Rust Grades A-D
- D. Surface Condition H
正解:C
質問 # 43
Common errors that may produce inaccurate readings when using a Dial-Type Magnetic Pull-Off Dry Filth Thickness (DFT) gauge include:
Select All That Apply
- A. Taking measurements too far from the edge of a surface
- B. Failing to determine the base metal reading (BMR)
- C. Rotating the dial too fast when taking measurements
- D. Measuring ditty, tacky, or soft films
正解:B、C、D
質問 # 44
You are the NACE Inspector on a 5000 sq. ft. job where SSPC PA 2 has been specified.
Assuming all areas are in compliance, how many gauge readings and spot measurements are required?
- A. 75 Gauge Readings resulting in 25 Spot Measurements
- B. 105 Gauge Readings resulting in 35 Spot Measurements
- C. 225 Gauge Readings resulting in 75 Spot Measurements
- D. 45 Gauge readings resulting in 15 Spot Measurements
正解:C
質問 # 45
The most important factor resulting in improved job site safety is:
- A. Personal Protective Equipment
- B. Safety Enforcement
- C. Situational Awareness
- D. Engineering Controls
正解:C
質問 # 46
When working as a NACE Inspector in a situation where there is a difference of opinion, the Inspector needs to:
- A. Achieve consensus through negotiation
- B. Call the supervisor
- C. Go with the majority opinion
- D. Never change his/her mind
正解:B
質問 # 47
The primary difference between Non-Convertible vs. Convertible coatings is:
- A. Non-convertible coatings do not undergo a chemical change during curing whereas Convertible coatings do
- B. Convertible coatings do not undergo a chemical change during curing whereas Non-Convertible coatings do
- C. Convertible coatings cure solely by solvent evaporation whereas Non-Convertible coatings do not
- D. Non-Convertible coatings cure by co-reaction whereas Convertible coatings do not
正解:A
質問 # 48
Relative humidity is
- A. a measure of the amount of moisture in the air compared to the air temperature.
- B. the highest temperature at which moisture forms on a steel surface.
- C. a measure of the amount of moisture in the air compared to saturation level.
- D. the lowest temperature at which moisture forms on a steel surface.
正解:C
質問 # 49
Stripe coats are best applied by:
- A. Brush
- B. High volume low pressure spray
- C. Conventional spray
- D. Airless spray
正解:A
質問 # 50
You are an inspector on a project where SSPC SP 3 is specified.
What sort of tools should you expect the Contractor to use to achieve the standard?
- A. Hand tools
- B. Abrasive blast nozzles
- C. Airless spray equipment
- D. Power tools
正解:D
質問 # 51
The main responsibilities of the inspector are to
- A. observe and direct the work of the contractors.
- B. demonstrate to the contractor how to apply the coating.
- C. direct and perform the work stated in the specification.
- D. observe and report the quality of the work performed.
正解:D
質問 # 52
ASTM Standards are applicable:
- A. When specified
- B. In Asia
- C. In the USA
- D. In North America
正解:A
質問 # 53
You ate the NACE Inspector on a job where NACE No. 2/SSPC - SP 10 has been specified. You are finding the Contractor is leaving mill scale on the on surface and as a result you have been rejecting the blast. The Contractor is very upset and has told you that the standard permits up to 5% of the mill scale to remain and still be in be in compliance with the standard.
Your FIRST preferred course of action is to:
- A. Permit coating to take place so as not to lose the blast
- B. Review the relevant standard with the Contractor
- C. Call your supervisor
- D. Shut the job down
正解:B
質問 # 54
As a NACE Coating Inspector your responsibility with respect to safety is to:
- A. Check the PPE used by the Applicators
- B. Act in accordance with the site safety requirements and set an example
- C. Check the credentials of the Safety Officer on site
- D. Assume the role of the Safety Inspector
正解:B
質問 # 55
A successful coating inspector must be able to
- A. apply the coating with expert accuracy.
- B. advise the coating applicator on how to mix the coating.
- C. recommend the appropriate coating technique for the job to the contractor.
- D. look for problems or issues during application.
正解:D